Metro Manila Subway
Metro Manila Subway | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overview | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Other name(s) | Mega Manila Subway[1] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Status | Under construction | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Owner | Department of Transportation | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line number | 9 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Locale | Metro Manila (phase 1) Bulacan and Cavite (phases 2 and 3) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Termini | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stations | 17 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Service | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Type | Rapid transit | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
System | Manila Metro Rail Transit System | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operator(s) | Department of Transportation | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Depot(s) | Ugong, Valenzuela | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Rolling stock | Sustina electric multiple units[2] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Daily ridership | 370,000 (projected)[3] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
History | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Commenced | February 27, 2019 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Planned opening | 2029 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Technical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Line length | 33 km (21 mi)[note 1] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Number of tracks | Double-track | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Character | Underground | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge[4] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Loading gauge | 4,150 mm × 3,000 mm (13 ft 7 in × 9 ft 10 in)[5] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Minimum radius | Mainline: 160 m (520 ft) Depot: 100 m (330 ft) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electrification | 1,500 V DC overhead lines[5] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating speed | 80 km/h (50 mph) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Signalling | Nippon Signal SPARCS moving block CBTC[6] | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The Metro Manila Subway,[7] formerly known as the Mega Manila Subway (MMS) is an under-construction underground rapid transit line in Metro Manila, Philippines. The 33-kilometer (21 mi) line, which will run north–south between Valenzuela, Quezon City, Pasig, Taguig, Parañaque and Pasay, consists of 17 stations between the East Valenzuela and Bicutan stations. It will become the country's second direct airport rail link after the North–South Commuter Railway, with a branch line to Ninoy Aquino International Airport.
Dubbed as the country's "Project of the Century", the Metro Manila Subway broke ground on February 27, 2019,[8] and construction began the following December. Subsequently, suffering delays due to the COVID-19 pandemic,[9] the line is scheduled to fully open in 2029. The project is expected to cost ₱355.6 billion (equivalent to US$7.06 billion in 2017 dollars).[10][11] Much of its cost is covered by a loan provided by the Japan International Cooperation Agency (JICA).[12][13][14]
The Metro Manila Subway is integrated with the public transit system in Metro Manila. Passengers may take various forms of road-based public transport, such as buses and jeepneys, to and from a station to reach their intended destination. The line is designed to connect with other urban rail transit services in the region; riders may transfer to LRT Line 1, MRT Line 3, and MRT Line 7 at the nearby North Triangle Common Station, which is also currently under construction. Other connections include the existing LRT Line 2 and PNR Metro Commuter Line, as well as the planned Makati Intra-city Subway, the MRT Line 4, and MRT Line 8.
History
[edit]Background
[edit]1973 UTSMMA | 1976 JICA | 2014/2015 JICA | MMSP | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Line no. | From | To | Length | Line no. | From | To | Length | Route name | From | To | Length | Scheme | From | To | Length |
1 | Quezon Memorial, Quezon City | Manila International Airport (now Ninoy Aquino International Airport), Parañaque | 21.7 km | 1 | University of the Philippines, Quezon City | Manila International Airport (now Ninoy Aquino International Airport), Parañaque | 25.2 km | Mass Transit System Loop | Bonifacio Global City, Taguig | Taft Avenue, Pasay | 20 km (11 km) | 2017 proposal | Quirino Highway, Quezon City | FTI, Taguig | 25 km |
2 | Manotoc Subdivision, Novaliches Quezon City | Pasig | 25.6 km | 2 | Novaliches, Quezon City | Guadalupe, Makati | N/A | Mega Manila Subway | Caloocan | Dasmarinas, Cavite | 59 km | 2019 proposal | Ugong, Valenzuela | FTI, Taguig/NAIA Terminal 3 | 33 km |
3 | Sangandaan, Caloocan | Roxas Boulevard, Pasay | 23.0 km | 3 | Malabon | Roxas Boulevard, Pasay | N/A | none | |||||||
4 | Baclaran, Parañaque | Cubao, Quezon City | 19.0 km | 4 | Baclaran, Parañaque | Cubao, Quezon City | N/A | ||||||||
5 | Tutuban, Manila | Marulas, Valenzuela | 8.0 km | 5 | Tutuban, Manila | Marulas, Valenzuela | N/A |
Early proposals and studies
[edit]The idea of building a subway in the Greater Manila Area had been forwarded as early as 1973, when the JICA (at the time known as the Overseas Technical Cooperation Agency or OTCA) and former Secretary of Public Works and Highways David Consunji conducted a study on what shall later be Metro Manila (formally constituted on November 7, 1975).[20] The 1973 plan was known as the Urban Transport Study in Manila Metropolitan Area (UTSMMA).[15]
The 1973 plan provided for the construction of five heavy rail subway lines in Metro Manila. The first line (Line 1) would have a length of 27.1 kilometers (16.8 mi), running from Constitution Hills (now Batasan Hills), Quezon City to Talon, Las Piñas. The second line (Line 2), meanwhile, would be 36 kilometers (22 mi) long from Novaliches, Quezon City to Cainta, Rizal, while Line 3 for 24.3 kilometers (15.1 mi) throughout Epifanio de los Santos Avenue. The fourth line (Line 4) would have been 30.1 kilometers (18.7 mi) long from Marikina to Zapote, Bacoor, and the fifth line would have a length of 17.6 kilometers (10.9 mi) from Rizal Avenue, Manila to Meycauayan, Bulacan. The plan would have resolved the traffic problems of Metro Manila and would have taken 15 years to complete, or until 1988.[16]
In 1975, a Reuters report said Manila was having traffic problems as many people feared that the population would grow, the number of commuters would increase, and there would be one day with only people on the streets with no vehicles. Also, it says that the team from JICA is studying the project that recommended the subway system and was expected to cost about US$930 million.[21]
In 1976, JICA conducted a feasibility study of the line, known as Rapid Transit Railway (RTR) Line 1. The study proposed a tentative route from Manila International Airport (MIA), now Ninoy Aquino International Airport, to the University of the Philippines in Quezon City, totaling 25.2 kilometers (15.7 mi). With the planned completion dates between 1983 and 2000 for that line with four stages, the other lines would have been constructed as part of the RTR network: Line 2 would connect Novaliches in Quezon City to Guadalupe, Makati; Line 3 would connect Malabon to Roxas Boulevard in Pasay; Line 4 would connect Baclaran in Parañaque to Cubao in Quezon City; and Line 5 would connect Binondo to Marulas in Valenzuela. Also, Pacific Consultants International and the Japan Overseas Consultants participated as a study team.[17] According to some critics of the LRT Line 1 that was built instead of the RTR Line 1, Marcos decided against the subway after being convinced by his advisers that the line could not be completed before Singapore finished its own first line.[22]
It was also proposed to be part of the 1977 Metro Manila Transport, Land Use and Development Planning Project (MMETROPLAN), which was funded by the World Bank. However, the plan was not included and implemented, for some of the areas included in the plan, such as Marikina and Cainta, are prone to flooding.[23][24][16] Instead, what was built was the LRT Line 1, opened on December 1, 1984, and completed on May 12, 1985. According to Felino Palafox, the LRT was the most feasible transport system at that time.[23] Nevertheless, the current Manila Light Rail Transit System (mostly elevated) is shorter than the line system forwarded in 1973.[16]
Proposals in the 1990s and 2000s
[edit]In 1995, the Mexican firm Grupo ICA, which also experienced Mexico City Metro, was in talks with the Department of Public Works and Highways (DPWH) to build a subway in the Philippines.[25] In 1998, the Department of Transportation and Communications (DOTC, later DOTr) signed a memorandum of understanding (MOU) with JK International Ltd. to conduct a feasibility study of a subway project; a route would have been linked between Port of Manila and NAIA.[26] In 2001, Italian firms Grandi Lavori Fincosit and Societa Esecuzione Lavori Idraulici signed an agreement with the DOTC, for a MOU. The 10-kilometer-long (6.2 mi) tunnel section of the subway would connect Bonifacio Global City (BGC), going through EDSA and connecting the Ortigas, Greenhills, and Shaw Boulevard commercial centers.[27] However, when former President Joseph Estrada resigned from office in the same year, the project never materialized.
Planning in the 2010s
[edit]The project was proposed once more in the 2014 Metro Manila Dream Plan as a 57.7-kilometer (35.9 mi) line that would serve as the second north–south mass transit backbone for the newly expanded Greater Capital Region (the first being the North–South Commuter Railway). The Metro Manila Dream Plan (formally titled the Roadmap for Transport Infrastructure Development for Metro Manila and Its Surrounding Areas) is an integrated plan, created on the basis of recommendations from a study conducted by the Japan International Cooperation Agency (JICA).[28] It was approved by the National Economic and Development Authority (NEDA) Board in June 2014, to last until 2030. The program aims to improve the transport system in Metro Manila, Philippines, with the hope of turning it into a focal point for addressing Metro Manila's interlinked problems in the areas of transportation, land use, and environment.[29][30]
In September of that year, British subway contractor Arup presented its profile to the DOTC in case the agency decides to build a subway system in Metro Manila, an official of the Makati Business Club said.[31] Applied Planning & Infrastructure Inc., in association with MKL Associates, proposed a version of the subway plan and conducted a business case as a private initiative for the project known as the Manila Central Subway. They lay out the definite alignment of the first 150 km (93 mi), approximate the next 150 km, and guess the last 82 km (51 mi); the first 150 km are to be further subdivided into workable segments of 30 to 40 km (19 to 25 mi) each. Locate optimal sites for subway stations and determine their basic requirements at least for the first 150 km; hire top-level consultants to prepare detailed engineering designs for the initial 150 km of tubes and various stations, optimal performance standards, environmental impact, economic and social benefits, value for money, and geotechnical and other technical analyses. The proposed lines are: the red line would run from North Triangle Common Station to Mall of Asia, while the extensions would lead to Tutuban and Taft Avenue MRT station; the brown line would connect NLEX in Valenzuela to FTI (using the same alignment as MMS Phase 1), and the extension would lead to Alabang; the blue line express would run along between the two lines; and finally, the green line would connect from Manila Bay to Tikling Junction, while the extensions would lead to Taytay and Holy Spirit, Quezon City.[32][33]
A year later, JICA published an information collection survey for the project, and the subway was to have 59 kilometers (37 mi) of route from Caloocan to Dasmarinas, Cavite, and the C4 route is the most suitable option. Meanwhile, the first phase is 22.6 kilometers (14.0 mi) from Mindanao Avenue and Quirino Highway in Quezon City to FTI in Taguig; Phase 2 leads to Bagong Silang, Caloocan, 10.2 kilometers (6.3 mi) up north; and Governor's Drive, Dasmarinas, is 26.1 kilometers (16.2 mi). Also, the intermodal terminal building was to be located at Market! Market! in BGC and to cater buses, jeepneys, and taxis at this terminal.[18]
Development
[edit]In 2015, the National Economic and Development Authority approved the construction of the Makati-Pasay-Taguig Mass Transit System Loop Line 5 (MTSL Line 5), which would have been a 20-kilometer-long (12 mi) underground railway from BGC to Taft Avenue, as identified in the JICA study, with two options: 32nd Street or 26th Street. Despite the fact that the route is 11 kilometers (6.8 mi) long, it passes through the central business districts. The project was to be funded through the public-private partnership scheme, but after former President Benigno Aquino III stepped down from office, the project stalled and was revived again by his successor, Rodrigo Duterte.[18][34][35] In January 2017, JICA was keen on developing a MTSL project, and in the same year, the Metro Manila Subway (then known as the Mega Manila Subway) was launched and included in the administration's Build! Build! Build! program.[36][37][38][39]
In August of that year, JICA published the preparatory survey for the project, which means the alignment would have run 25 kilometers (16 mi) from Quirino Highway to FTI, with the alignment along C-5. The alignment did not have an alignment going to NAIA before it was revised.[19]
The development of the project was approved by the Investment Coordination Committee (ICC) board of the National Economic and Development Authority on September 6, subject to secondary approval by the NEDA Board.[40] The development was approved by the NEDA Board headed by President Duterte six days later.[41] On March 16, 2018, the Philippine and Japanese governments signed a loan agreement for the subway. The first tranche of the official development assistance from JICA amounted to ¥104.5 billion (₱51.3 billion).[12] The second tranche of the loan, signed on February 10, 2022, amounted to ¥253.3 billion (₱112.1 billion).[13] On March 26, 2024, the third tranche of the loan was signed, amounting to ¥150 billion (₱55.37 billion).[14]
In June 2018, soil testing was conducted along the alignment. In the same month, the Department of Environment and Natural Resources (DENR) decided that the subway would not pass along the fault line because the West Valley Fault passes along C-5 road in Taguig.[42] The following November, OC Global, a Japanese consortium consisting of Oriental Consultants Global Co. Ltd., Tokyo Metro Co. Ltd., Katahira & Engineers International, Pacific Consultants Co Ltd., Tonichi Engineering Consultants, Inc., and Metro Development Co. Ltd., was appointed as the project consultant.[43][44]
Construction
[edit]Contract package | Scope of work | Contractors | Date awarded | Notes |
---|---|---|---|---|
CP 101[45] | Construction of first three stations | Shimizu Corporation Fujita Corporation Takenaka Corporation EEI Corporation |
February 2019 | JIM Technology Corporation was appointed to use tunnel boring machines for the construction.[46] |
CP 102[47] | Construction of the Quezon Avenue and East Avenue stations | Nishimatsu Construction DMCI |
September 2022 | |
CP 103[48][49] | Construction of Anonas and Katipunan stations | Sumitomo Mitsui Construction | September 2022 | |
CP 104[50] | Construction of Ortigas and Shaw stations | Megawide Construction Corporation Tokyu Construction Tobishima Construction |
April 2022 | |
CP 105[51] | Construction of Fort Bonifacio section and associated stations | TBA | Ongoing bidding | |
CP 106[52] | Electrical and mechanical (E&M) systems | Mitsubishi Corporation Colas Rail[note 2] Hitachi (formerly Thales)[note 3] Egis[note 4] (awarded by Mitsubishi)[54][55] |
September 2021 (Mitsubishi) February 2022 (Colas Rail, Thales (later acquired by Hitachi for ground transportation business in 2024), and Egis) |
Subcontractors: Nippon Signal (for CBTC signaling)[6] |
CP 107[56][57] | Rolling stock | Sumitomo Corporation J-TREC |
December 2020 | |
CP 108[51] | Construction of Lawton and Senate–DepEd stations | TBA | Ongoing bidding | |
CP 109[51] | Construction of NAIA spur line | |||
CP S-03b[58] | Construction of Senate–FTI section | Leighton Contractors (Asia) First Balfour |
February 2023 | This contract package is funded by the Asian Development Bank (ADB), which included FTI and Bicutan stations of the subway as part of packages for the southern segment of the North–South Commuter Railway. |
The Metro Manila Subway broke ground on February 27, 2019.[8] Ten months later, construction begun its clearing phase in Valenzuela on December 21.[59][60] As part of the initial partial operability section (the Qurino Highway, the Tandang Sora, and the North Avenue stations), the first three stations will be built alongside the Philippine Railways Institute (PRI), the country's first-ever railway training center.[59]
Massive tunnel boring machines were to be employed for the project. In September 2020, the Department of Transportation (DOTr) presented one of the six tunnel boring machines in an acceptance test ceremony through a video conference.[61][62] The first of 25 tunnel boring machines that will be used for the subway's construction was unveiled on February 5, 2021.[63]
On November 11, 2021, a groundbreaking ceremony was held at Camp Aguinaldo to mark the start of pre-construction activities at the Camp Aguinaldo station.[64] Meanwhile, the Ortigas and Shaw stations broke ground on October 3, 2022.[65] Work on the Katipunan and Anonas stations began on February 13, 2023.[66]
The underground and tunnel boring works for the subway were slated to start by the fourth quarter of 2021, but was delayed.[67] The first tunnel boring machine was ceremonially lowered on June 12, 2022,[68] while underground tunnel works began on January 9, 2023.[69]
The line was originally slated to begin partial operations by 2022.[70] However, in April 2022, the DOTr delayed this to 2025, with full operations by 2027, as the COVID-19 pandemic hindered construction.[9] On July 10, 2023, the DOTr scrapped its plan to begin partial operations by 2027, opting instead to fully open the subway by 2029.[71] Challenges related to right-of-way acquisition have hindered construction progress,[14] with completion as of June 2024 at only 14%.[72] An interagency committee for the two railway projects was established to address issues with the project's alignment.[73]
Route
[edit]The subway is estimated to be 33 kilometers (21 mi) long. The project involves the construction of 17 stations in its first phase (listed from north to south):[74]
Name | Distance (km) | District/Barangay | Connections | Location | ||
---|---|---|---|---|---|---|
Between stations |
Total | |||||
East Valenzuela | — | 0.000 | Ugong | none | Valenzuela | |
Quirino Highway | — | — | Talipapa |
|
Quezon City | |
Tandang Sora | — | — | Tandang Sora |
| ||
North Avenue | — | 3.886 | Project 6 |
| ||
Quezon Avenue | 1.331 | 5.217 | Bagong Pag-asa |
| ||
East Avenue | 1.719 | 6.936 | Pinyahan |
| ||
Anonas | 2.094 | 9.030 | Bagumbuhay |
| ||
Camp Aguinaldo | 1.642 | 10.672 | Camp Aguinaldo |
| ||
Ortigas | 3.075 | 13.747 | San Antonio |
|
Pasig | |
Shaw Boulevard | 1.280 | 15.027 | — | |||
Kalayaan | 2.107 | 17.134 | Fort Bonifacio |
|
Taguig | |
BGC | 1.075 | 18.209 |
| |||
McKinley Hill | 2.199 | 20.408 | — | |||
Nichols | 1.734 | 22.142 | — | |||
FTI | 3.988 | 26.130 | Western Bicutan |
| ||
Bicutan | 3.988 | 27.825 | San Martin de Porres |
|
Parañaque | |
NAIA extension spur line[40] | ||||||
NAIA Terminal 3 | — | — | District 1 | Pasay | ||
Stations, lines, and/or other transport connections in italics are either under construction, proposed, unopened, or have been closed. |
The following phases of the subway project would involve extending lines up to San Jose del Monte, Bulacan, north of Metro Manila (15.4 kilometers or 9.6 miles from General Luis Avenue in Caloocan), and down to Dasmariñas, Cavite, south of Metro Manila (20.7 kilometers or 12.9 miles from the proposed Ninoy Aquino International Airport station). The entire system, when completed, will serve up to 1.74 million passengers daily.[75]
The initial plan was later modified in June 2020, with DOTr adding the East Valenzuela, Lawton, and Senate stations.[76] The East Valenzuela station will be located in the subway's depot, while the Lawton and Senate stations replaced the Cayetano Boulevard station. However, these modifications are subject to the approval of NEDA and JICA.[76]
DOTr and JICA also propose a physical connection and interoperability between the North–South Commuter Railway and MMS. It proposes MMS rolling stock to switch over to the at-grade NSCR-South tracks around the FTI area, via a physical connection of the tracks and electrical supply, and operate through services to NSCR-South stations from Bicutan towards Calamba and vice versa.[77][78]
Design and infrastructure
[edit]The line will be the fourth heavy rail line in the country, after LRT Line 2, MRT Line 7, and the North–South Commuter Railway, and the first to be mostly underground. It is designed to run trains at 80 kilometers per hour (50 mph).[5] The tunnel diameter inside and outside is projected to be 5.2 meters (17 ft) and 5.65 meters (18.5 ft), respectively.[75] Since there are estimates of an expected magnitude-7.2 earthquake (which can be as powerful as magnitude 7.6) in the Marikina Valley Fault System,[79] it is designed to withstand a magnitude-8.0 earthquake. In addition, it may not be entirely underground. Assessment of the environmental and geographical considerations in the base alignment (initially 74.6 kilometers or 46.4 miles long) recommends 18% of the line to be at-grade and 9% to be running through viaduct.[75] Prior to final approval, some adjustments to the alignment were done so that it would reduce the risk of damage during earthquakes by travelling along solid adobe ground.
On September 5, 2020, in response to questions, Transportation Secretary Arthur Tugade provided assurances that the system would be flood-proof.[80]
Stations
[edit]The stations would have design features such as water-stop panels, a high-level entrance for flood prevention, earthquake detection, and a train stop system, akin to the Tokyo subway.[10] The stations are also designed to accommodate up to 1.5 million passengers daily. Full-height platform screen doors will also be built in the stations.[4]
The major stations of the line are planned to have two platform levels, one for a local train service and another for express routes. These stations are planned to have 6 floors designed for 2 platform floors, commercial shops, ticketing facilities and other amenities.[81]
Seven of the proposed stations, namely NAIA Terminal 3, Bicutan, Senate, Lawton, Katipunan, Quezon Avenue and North Avenue stations will be built on government property in order to boost property values in the surrounding areas.[82]
Signalling
[edit]The line will use a moving block signalling system based on communications-based train control (CBTC), which is the first railway line in the Philippines to use a moving block/CBTC system. Its subsystems include automatic train protection (ATP), automatic train operation (ATO), automatic train supervision (ATS), train detection through track circuits, and computer-based interlocking.[4] Nippon Signal will provide their SPARCS CBTC signalling solution for the line.[6]
Tracks
[edit]Two types of rails will be employed in the subway: 60-kilogram-per-meter (120 lb/yd) rails will be employed in the mainline while 50-kilogram-per-meter (100 lb/yd) rails will be employed in the depot.[4] The rails in the mainline will consist of continuous welded rails while the rails in the depot will be jointed rails with fishplates. The tracks will be supported by concrete sleepers except for the turnouts which will be supported by plastic/fiber-reinforced foam urethane railroad ties.[4]
Rolling stock
[edit]The Metro Manila Subway will use Sustina electric multiple units built by the Sumitomo Corporation and Japan Transport Engineering Company (J-TREC).[83] The same type has been ordered by the Philippine National Railways for its North–South Commuter Railway project as the PNR EM10000 class.[2] Hitachi, along with Sumitomo and Mitsubishi, bought bid documents for the design, execution, and completion of 30 train sets in February 2020.[84] An order for 240 railcars, arrangeable into thirty 8-car trainsets, has been finalized by the Department of Transportation on December 21.[56][85]
Trains will have a capacity of 2,242 passengers, which is more than the normal capacity of the rolling stock of the existing LRT Line 1, LRT Line 2, MRT Line 3, and the PNR Metro Commuter Line. At its base form, it is about twice longer than the 4-car trains of the LRTA 2000 class being used in the LRT Line 2. According to DOTr Undersecretary Timothy John Batan, each 8-car trainset will ease car traffic in Metro Manila equivalent to 1,300 cars, 220 jeepneys, or 60 buses.[56] It will be powered through 1,500 V DC overhead lines similar to those ordered by PNR.[5]
Rolling stock | Sustina EMU[5] | |
---|---|---|
Year | 2025–2027 | |
Manufacturer | Sumitomo Corporation Japan Transport Engineering Company | |
Model | TBD | |
Number to be built | 240 cars (30 sets) | |
Formation | 8 cars per trainset | |
Car length | 20 m (65 ft 7 in) | |
Width | 2.95 m (9 ft 8 in) | |
Pantograph lockdown height | 4.15 m (13 ft 7 in) | |
Floor height | 1.15 m (3 ft 9 in) | |
Body material | Lightweight stainless steel | |
Tare weight | 270 t (600,000 lb) | |
Axle load | 16 t (35,000 lb) | |
Capacity | Leading car: 266 standing, 45 seated Intermediate car: 285 standing, 54 seated Total: 2,242 | |
Seat layout | Rapid transit-style longitudinal seating | |
Doors per side | 4 | |
Traction control | Hybrid SiC–VVVF | |
Traction power | 1,500 V DC overhead catenary | |
Pantograph type | Single-arm pantograph[note 5] | |
Top speed | 120 km/h (75 mph) | |
Safety system(s) | ATP, ATO | |
Train configuration | Tc–M–M–T–T–M–M–Tc | |
Status | Ordered; to be built |
Depot
[edit]The line will have a depot in Ugong, Valenzuela, within the vicinity of the East Valenzuela station. It occupies 4 hectares (9.9 acres) of space and serves as the headquarters for the operations and maintenance of the line.[86] The trains are parked on several sets of tracks, which converge onto the spur route and later on to the main network.
A 20,000-square-meter (220,000 sq ft)[86] building will host the Philippine Railways Institute which will also be built within the depot vicinity.[59] In addition, a 900-meter (3,000 ft) test track and mock-ups of the tunnels, stations, and wayside equipment will be constructed for training purposes.[86]
Future
[edit]Phase 2 (extensions to Bulacan and Cavite)
[edit]In the 2023 plan, when the government approves the 194 flagship infrastructure projects, the subway's extension will lead to Bulacan and Cavite. The two routes will cover approximately 40 kilometers (25 mi). Also included in the plan is a 4-kilometer (2.5 mi) extension to Asia World, which will connect to an LRT-1 station and Paranaque Integrated Terminal Exchange (PITX).[87] The planned extensions are under study and are expected to be financed by the Asian Development Bank (ADB) under the Infrastructure Preparation and Innovation Facility.[88]
Planned expansions
[edit]In February 2023, the DOTr announced a collaboration with JICA to add more subways. At the time, transportation secretary Jaime Bautista said that the subways would be expanded to Cavite, and he also said there would be three to four lines. Although it is in the planning stage, it was announced during the state visit of President Marcos to Japan.[89] In the following year, JICA also said there will be future subways, and this time, they also conducted a study for a 30-year railway master plan for the Greater Capital Region.[90]
Notes
[edit]- ^ Line length from Valenzuela to Bicutan. The proposed line in 2014 is planned to be 57.7 km (35.9 mi) long from San Jose del Monte to Dasmariñas.
- ^ Responsible for the engineering and system integration, railway track and signaling, power distribution, depot equipment and overhead lines
- ^ Responsible for the communications and supervision systems as well as the automated fare collection (AFC) system
- ^ Responsible for the preliminary design of the E&M systems and the installation of >1,300 platform screen doors.[53]
- ^ Two outward-facing single-arm pantographs shall be used on cars 2 and 6.
References
[edit]- ^ Cabico, Gaea Katreena (October 4, 2019). "Temporary LRT-2 shutdown after fire highlights need for structural change, better inspections". The Philippine Star. Retrieved November 26, 2020.
- ^ a b "Order Received to Supply 240 Train Cars for Philippines' Metro Manila Subway". Sumitomo Corporation. December 21, 2020. Archived from the original on January 23, 2021. Retrieved March 6, 2021.
- ^ "Mega Manila Subway". Philippine Infrastructure Transparency Portal. Archived from the original on April 20, 2017.
- ^ a b c d e Part 2 – Employer's Requirements (PDF). METRO MANILA SUBWAY PROJECT PHASE 1 Package CP106: E&M Systems and Track Works (Report). Department of Transportation (Philippines). Archived (PDF) from the original on April 30, 2021. Retrieved February 14, 2022.
- ^ a b c d e Part 2 – Employer's Requirements (PDF). METRO MANILA SUBWAY PROJECT PHASE 1 Package CP107: Rolling Stock (Report). Department of Transportation (Philippines). Archived (PDF) from the original on July 15, 2022. Retrieved February 14, 2022.
- ^ a b c Nippon Signal receives the order of Signalling System for Metro Manila Subway Project in the Philippines (PDF) (Report). Nippon Signal. May 19, 2022. Retrieved May 20, 2022.
- ^ "PH, Japan to sign new loan for subway in Q1 next year". Philippine Daily Inquirer. November 2, 2020. Archived from the original on November 1, 2020. Retrieved November 26, 2020.
- ^ a b Manabat, Jacque (February 27, 2019). "Metro Manila Subway breaks ground". ABS-CBN News. Archived from the original on November 23, 2021. Retrieved November 23, 2021.
- ^ a b Mercurio, Richmond (April 19, 2022). "Metro Manila subway partial opening moved to 2025 – DOTr". The Philippine Star. Retrieved April 19, 2022.
- ^ a b Abadilla, Emmie V. (February 26, 2019). "36-km P355.6-B Metro subway launched". Manila Bulletin. Retrieved June 2, 2022.
- ^ "Japan set to fund Metro Manila subway, 2 other rail projects". Public-Private Partnership Center. Archived from the original on October 30, 2019. Retrieved April 20, 2017.
- ^ a b "Metro Manila Subway: PH, Japan sign loan deal". ABS-CBN News. March 16, 2018. Archived from the original on March 24, 2018. Retrieved April 3, 2018.
- ^ a b Rocamora, Joyce Ann L. (February 10, 2022). "Japan, PH sign Y253-B loan deal for Metro Manila Subway". Philippine News Agency. Archived from the original on February 10, 2022. Retrieved February 14, 2022.
- ^ a b c Cordero, Ted (March 26, 2024). "Philippines, Japan sign ¥150-B third tranche loan for Metro Manila subway". GMA Integrated News. Retrieved April 5, 2024.
- ^ a b "URBAN TRANSPORT STUDY IN MANILA METROPOLITAN AREA" (PDF). Overseas Technical Cooperation Agency. September 1973.
- ^ a b c d Jose, Ricardo; Mabazza, Daniel; Lagman, Marco Stefan; Villasper, Jonathan. "Planning Metro Manila's Mass Transit System" (PDF). Archived from the original (PDF) on April 20, 2017. Retrieved April 20, 2017.
- ^ a b "THE FEASIBILITY STUDY FOR MANILA RAPID TRANSIT RAILWAY LINE NO. 1" (PDF). Japan International Cooperation Agency. June 1976. Retrieved July 21, 2024.
- ^ a b c "INFORMATION COLLECTION SURVEY FOR THE MEGA MANILA SUBWAY PROJECT IN THE REPUBLIC OF THE PHILIPPINES: FINAL REPORT" (PDF). Japan International Cooperation Agency. September 2015.
- ^ a b "The Preparatory Survey for Metro Manila Subway Project in Philippines: Draft RAP Report" (PDF). Japan International Cooperation Agency. August 2017. Retrieved July 22, 2024.
- ^ Malasig, Jeline (December 28, 2018). "Story behind Metro Manila Subway and the 45 years since its first proposal". InterAksyon. Archived from the original on February 6, 2021. Retrieved May 31, 2022.
- ^ "Manila faces a traffic crisis". Reuters. December 8, 1975.
- ^ "What if Manila decided to build its first subway back in the 1970s?". Caught (up) in traffic. September 13, 2017. Retrieved July 20, 2024.
- ^ a b Garcia, Cathy Rose (September 19, 2013). "Why gov't rejected subway for Metro Manila in the 1970s". ABS-CBN News. Archived from the original on January 25, 2020. Retrieved May 31, 2022.
- ^ Palafox, Felino A. Jr. (June 3, 2015). "1977 plan still remains to be carried out". The Manila Times. Archived from the original on June 10, 2020. Retrieved April 20, 2017.
- ^ "Mexicans seek Philippine subway project partners". UPI. August 3, 1995.
- ^ "P6-B telecom bidding reset for Feb. 23". Manila Standard. February 16, 1998. p. 5.
- ^ Admin, Cms (January 5, 2001). "Agreement signed for Manila metro". Tunnels. Retrieved August 9, 2024.
- ^ Dela Paz, C. J. V. (September 2, 2014). "Plan seeks to untangle gridlock". Business World. New Manila, Quezon City, Philippines: BusinessWorld Publishing Corporation. Archived from the original on November 28, 2019. Retrieved September 18, 2014.
- ^ (The Philippines) MEGA MANILA INFRASTRUCTURE ROADMAP (Long Ver.). JICAChannel02: The Official Global Channel of the Japan International Cooperation Agency (JICA). Japan International Cooperation Agency (JICA), Republic of the Philippines National Economic Development Authority (NEDA). June 10, 2014.
- ^ Main Points of the Roadmap (PDF) (Report). Japan International Cooperation Agency. September 2014. Archived (PDF) from the original on February 6, 2021. Retrieved May 5, 2017.
- ^ "PH subway proposed".
- ^ "Review of Business Case for Manila Central Subway". Aninver.
- ^ Sicat, Glicerio V. (October 26, 2014). "Subway to solve Manila traffic woes". INQUIRER.net. Retrieved July 15, 2024.
- ^ Paz, Chrisee De La (November 4, 2015). "Makati-Pasay-Taguig subway auction targeted for next gov't". RAPPLER. Retrieved May 19, 2024.
- ^ Paz, Chrisee De La (August 18, 2016). "Duterte admin revives plan to build Metro Manila subway". RAPPLER. Retrieved July 15, 2024.
- ^ "JICA keen on funding Metro Manila subway".
- ^ Morallo, Audrey. "13 stations of the Mega Manila subway unveiled". Philstar.com. Retrieved July 15, 2024.
- ^ Yee, Jovic (April 18, 2017). "Duterte, Abe to sign deal paving for Mega Manila subway". INQUIRER.net. Retrieved July 15, 2024.
- ^ "Philequity Corner (April 24, 2017) By Wilson Sy" (PDF).
- ^ a b Dela Paz, Chrisee (September 6, 2017). "$7-B Metro Manila subway to be extended to NAIA". Rappler. Retrieved May 29, 2022.
- ^ Dela Paz, Chrisee (September 13, 2017). "NEDA Board approves Manila subway, longest railway". Rappler. Archived from the original on September 14, 2017. Retrieved May 21, 2022.
- ^ ABS-CBN News (June 21, 2018). Bandila: Subway project, hindi dadaan sa West Valley Fault: Phivolcs. Retrieved July 22, 2024 – via YouTube.
- ^ Nicolas, Bernadette D. (November 22, 2018). "Government awards P11-billion subway contract to Japanese group". BusinessMirror. Archived from the original on December 9, 2018. Retrieved December 8, 2018.
- ^ Caraballo, Mayvelin U. (November 22, 2018). "Japanese consortium bags subway contract". The Manila Times. Archived from the original on December 9, 2018. Retrieved December 8, 2018.
{{cite news}}
: CS1 maint: unfit URL (link) - ^ Mercurio, Richmond (February 25, 2019). "Japan-Filipino consortium bags Metro Manila subway project". The Philippine Star. Retrieved February 25, 2019.
- ^ "PROJECT". JIM TECHNOLOGY CORPORATION.
- ^ Balinbin, Arjay L. (October 3, 2022). "Nishimatsu-DMCI joint venture bags subway contract". BusinessWorld. Retrieved October 3, 2022.
- ^ Balinbin, Arjay L. (September 30, 2022). "Sumitomo bags P27-B Manila subway project". BusinessWorld. Retrieved October 3, 2022.
- ^ Rosales, Elijah Felice (September 30, 2022). "Sumitomo Mitsui bags contract to build 2 Metro Manila subway stations". The Philippine Star. Retrieved October 3, 2022.
- ^ Balinbin, Arjay (May 3, 2022). "Megawide, 2 Japanese firms secure P13-B subway deal". BusinessWorld. Archived from the original on May 3, 2022. Retrieved May 3, 2022.
- ^ a b c Rosales, Elijah Felice (February 14, 2023). "Final subway deals worth P60 billion to be awarded by Q2". The Philippine Star. Retrieved February 14, 2023.
- ^ "Notice of Award" (PDF). METRO MANILA SUBWAY PROJECT PHASE 1 Package CP106: E&M Systems and Track Works. Department of Transportation (Philippines). September 24, 2021. Archived (PDF) from the original on February 14, 2022. Retrieved February 14, 2022.
- ^ "Egis secures a major contract to design and equip the first underground metro in Manila" (PDF). Egis Group (Press release). February 25, 2022. Retrieved May 22, 2022.
- ^ Abadilla, Emmie V. (February 25, 2022). "Thales consortium wins P57.5-B contract for Metro Manila Subway". Manila Bulletin. Archived from the original on February 25, 2022. Retrieved February 28, 2022.
- ^ "Thales to provide key systems for Metro Manila Subway". Railway Technology. February 25, 2022. Archived from the original on February 25, 2022. Retrieved April 7, 2022.
- ^ a b c Dela Cruz, Raymond (December 21, 2020). "DOTr orders 240 train cars for Metro Manila Subway". Archived from the original on December 21, 2020. Retrieved December 21, 2020.
- ^ "Order Received to Supply 240 Train Cars for Philippines' Metro Manila Subway". Sumitomo Corporation. Archived from the original on January 23, 2021. Retrieved January 5, 2021.
- ^ "Leighton-First Balfour JV signs NSCR package". First Balfour. April 28, 2023.
- ^ a b c Talabong, Rambo (December 21, 2019). "LOOK: Metro Manila Subway construction enters clearing phase". Rappler. Archived from the original on December 21, 2019. Retrieved December 21, 2019.
- ^ Cordero, Ted (December 21, 2019). "DOTr begins clearing 'partial operability' site for Metro Manila subway". GMA News Online. Archived from the original on December 21, 2019. Retrieved December 21, 2019.
- ^ "Tunnel boring machines for Metro Manila subway to arrive in early 2021 – DOTr". Rappler. Archived from the original on September 22, 2020. Retrieved September 6, 2020.
- ^ Ramos, Mariejo S. (September 5, 2020). "Metro Manila subway project 'early Christmas gift' to Filipinos — Tugade". Philippine Daily Inquirer. Archived from the original on September 6, 2020. Retrieved September 6, 2020.
- ^ Balinbin, Arjay L. (February 5, 2021). "Deployment of 25 tunnel-boring machines signals big push for subway completion". BusinessWorld. Archived from the original on February 6, 2021. Retrieved February 7, 2021.
- ^ Dela Cruz, Raymond Carl (November 11, 2021). "Prep works for Metro Manila Subway at Camp Aguinaldo begins". Philippine News Agency. Archived from the original on November 23, 2021. Retrieved November 23, 2021.
- ^ Abadilla, Emmie V. (October 3, 2022). "2 Manila Subway stations break ground". Manila Bulletin. Retrieved October 3, 2022.
- ^ Marasigan, Lorenz S. (February 13, 2023). "Construction work starts on MMSP's Anonas and Camp Aguinaldo stations". BusinessMirror. Retrieved February 14, 2023.
- ^ "Underground work for Metro Manila subway to start in Q4". CNN Philippines. April 27, 2021. Archived from the original on May 1, 2021. Retrieved May 1, 2021.
- ^ Fernandez, Daniza (June 12, 2022). "Duterte leads commissioning of BRP Melchora Aquino, lowering of subway tunnel boring machine". Philippine Daily Inquirer. Retrieved June 12, 2022.
- ^ Abadilla, Emmie V. (January 9, 2023). "Tunneling on P488.5-B Metro Manila Subway starts today". Manila Bulletin. Retrieved January 9, 2023.
- ^ Vera, Ben O. de (March 16, 2018). "1st 3 Metro Manila subway stations seen operational by 2022". Archived from the original on April 3, 2018. Retrieved April 3, 2018.
- ^ Manabat, Jacque (July 10, 2023). "DOTr eyes full ops of Metro Manila Subway in 2029, scraps 2027 partial opening". ABS-CBN News. Retrieved June 4, 2024.
- ^ Layson, Mer (May 22, 2024). "Metro Manila Subway, fully operational na sa 2029". The Philippine Star (in Filipino). Retrieved June 4, 2024.
- ^ "Gov't forms body to resolve right-of-way woes of 2 flagship railway projects". GMA Integrated News. October 4, 2024.
- ^ Yu, Lance Spencer (March 8, 2024). "MAP: Metro Manila Subway stations". Rappler. Retrieved May 3, 2024.
- ^ a b c "Roadmap for Transport Infrastructure Development for Metro Manila and Its Surrounding Areas (Region III and Region IV-A): SUPPLEMENTARY REPORT ON MEGA MANILA SUBWAY PROJECT" (PDF). National Economic and Development Authority. Archived (PDF) from the original on November 12, 2020. Retrieved April 20, 2017.
- ^ a b Balinbin, Arjay L. (June 2, 2020). "Gov't adds more stations to Metro Manila subway". BusinessWorld. Archived from the original on June 14, 2020. Retrieved June 2, 2020.
- ^ Feasibility Study on the North South Railway Project-South Line (Commuter) in the Republic of the Philippines: DRAFT FINAL REPORT (PDF) (Report). Japan International Cooperation Agency. October 2018. Archived (PDF) from the original on April 11, 2021. Retrieved March 17, 2019.
- ^ Camus, Miguel R. (June 1, 2021). "Metro Manila subway, North-South railway set to be linked physically". Philippine Daily Inquirer. Archived from the original on May 31, 2021. Retrieved May 3, 2022.
- ^ Nelson, Alan R.; Personius, Stephen F.; Rimando, Rolly E.; Punongbayan, Raymundo S.; Tungol, Norman; Mirabueno, Hannah; Rasdas, Ariel (2000). "Multiple Large Earthquakes in the Past 1500 Years on a Fault in Metropolitan Manila, the Philippines". Bulletin of the Seismological Society of America. 90 (1). Seismological Society of America: 84. Bibcode:2000BuSSA..90...73N. doi:10.1785/0119990002. Archived from the original on August 20, 2017. Retrieved April 20, 2017.
- ^ "DOTr says Metro Manila Subway will be flood-proof". Philippine Daily Inquirer. September 5, 2020. Archived from the original on September 22, 2020. Retrieved December 5, 2020.
- ^ "Konstruksiyon ng Metro Manila Subway sisimulan na" [Construction of Metro Manila Subway will start]. ABS-CBN News (in Tagalog). February 27, 2019. Archived from the original on March 13, 2019. Retrieved March 18, 2019.
- ^ Pateña, Aerol John (March 6, 2019). "6 subway stations to rise on gov't properties". Philippine News Agency. Archived from the original on November 11, 2021. Retrieved March 8, 2019.
- ^ Balinbin, Arjay (July 28, 2020). "J-Trec group bids for subway train sets". BusinessWorld. Archived from the original on August 14, 2020. Retrieved August 13, 2020.
- ^ CEDTyClea (February 23, 2020). "More firms eye bidding for Manila subway contracts". BusinessWorld Online. Retrieved July 17, 2024.
- ^ "Order Received to Supply 240 Train Cars for Philippines' Metro Manila Subway" (PDF) (Press release). Japan Transport Engineering Company. December 20, 2020. Archived (PDF) from the original on December 19, 2021. Retrieved April 2, 2021.
- ^ a b c Pateña, Aerol John (March 1, 2019). "DOTr, JICA approve curriculum for PH Railway Institute". Philippine News Agency. Archived from the original on November 20, 2021. Retrieved April 7, 2022.
- ^ "Infrastructure Flagship Projects (IFPs) under the Build-Better-More Program" (PDF). Retrieved May 23, 2024.
- ^ "50288-001: Infrastructure Preparation and Innovation Facility" (PDF). Asian Development Bank. Retrieved May 23, 2024.
- ^ Flores, Helen (February 12, 2023). "DOTr eyes more subway projects in NCR, Cavite". Philstar.com. Retrieved May 23, 2024.
- ^ "More subways eyed as DOTr shows off progress on flagship infra". ABS-CBN News. February 27, 2024. Retrieved May 23, 2024.