Jump to content

LRT Line 2 (Metro Manila)

From Wikipedia, the free encyclopedia

LRT Line 2
Overview
StatusOperational
OwnerLight Rail Transit Authority
Line number2
LocaleMetro Manila & Rizal, Philippines
Termini
Stations13[1]
WebsiteOfficial website
Service
TypeRapid transit / Heavy rail
SystemManila Light Rail Transit System
Services1
Operator(s)Light Rail Transit Authority
Depot(s)Santolan, Pasig
Rolling stockLRTA 2000 class[1]
Daily ridership149,331 (2024)[2]
Ridership49,428,645 (2023)[3]
History
CommencedNovember 15, 1997; 27 years ago (1997-11-15)
OpenedApril 5, 2003; 21 years ago (2003-04-05)[1]
Last extensionJuly 5, 2021; 3 years ago (2021-07-05)[4]
CompletedOctober 29, 2004; 20 years ago (2004-10-29)
Technical
Line length17.6 km (10.9 mi)
Number of tracksDouble
CharacterElevated
Underground
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Loading gauge4,300 mm × 3,354 mm (14 ft 1.3 in × 11 ft 0 in)[5]
Minimum radiusMainline: 175 m (574 ft)
Depot: 100 m (330 ft)
Electrification1,500 V DC overhead catenary
Operating speed60 km/h (37 mph)
SignallingSiemens TBS100 fixed block ATC under ATO GoA 2 (STO), with subsystems of ATP, Rail9000 ATS, and Westrace MK1 CBI[6][7][8]
Highest elevation45 m (148 ft) at Antipolo station
Maximum incline5%[6]
Average inter-station distance1.28 km (0.80 mi)
Route map

Antipolo
Marikina–Pasig
Santolan
Bus interchange ferry/water interchange
Santolan Depot
Marikina River
Katipunan
Anonas
Left arrow Quirino Highway - FTI Right arrow
 NAIA Terminal 3 Right arrow
 MMS 
Araneta Center–Cubao
Left arrow North Avenue - Taft Avenue Right arrow
Betty Go-Belmonte
Gilmore
J. Ruiz
San Juan River
V. Mapa
Calamba Right arrow
Pureza
Legarda
Left arrow University Avenue
Recto
Left arrow North Triangle Common Station -Fernando Poe Jr. - Dr. Santos - Niog Right arrow
Left arrow Clark International Airport
approved
extension
Tutuban
Divisoria
Pier 4
ferry/water interchange

The Light Rail Transit Line 2, also known as LRT Line 2, LRT-2, or Megatren, is a rapid transit line in Metro Manila in the Philippines owned and operated by the Light Rail Transit Authority (LRTA). The line generally runs in an east–west direction between Recto in Manila and Antipolo. The line is officially referred to as the Purple Line.

Although commonly known as LRT-2, the line is a high capacity heavy rail line that uses large metro cars which are longer and wider than those used on the PNR network and roughly the same size as those used on the MTR in Hong Kong, instead of the light rail vehicles used in earlier lines.[9] Until the opening of MRT Line 7 in 2025, it will be the country's only line that uses these types of trains.[9]

Envisioned in the 1970s as part of the Metropolitan Manila Strategic Mass Rail Transit Development Plan, it was first planned in 1988 and stalled years later when Japan's official development assistance funds stepped in, the thirteen-station, 17.6-kilometer (10.9 mi)[10] line was the third rapid transit line to be built in Metro Manila when it started operations in 2003. The line became the first rapid transit line extending outside the Metro Manila area after its extension to Antipolo, Rizal opened in 2021.[4]

The line is integrated with the public transit system in Metro Manila, and passengers also take various forms of road-based public transport, such as buses and jeepneys, to and from a station to reach their intended destination. It is the least busy among Metro Manila's three rapid transit lines, with total ridership significantly below the line's built maximum capacity, serving about 140,000 passengers daily in 2023.[11] Regardless, the line encounters periods of peak ridership during rush hour in the morning and the evening. Expanding the network's revenue line to accommodate more passengers is set on tackling this problem, with plans of a three-station westbound extension in Manila by 2024 and another eastbound extension towards downtown Antipolo.[12][13]

History

[edit]
A eastbound train on the viaduct near Marikina River
J. Ruiz station platform area
LRT-2 train with wrap advertisement

Planning and early delays

[edit]

During the construction of the first line of the Manila Light Rail Transit System in the early 1980s, a Swiss company called Electrowatt Engineering Services designed a comprehensive plan for metro service in Metro Manila. The plan—still used as the basis for planning new metro lines—consisted of a 150-kilometer (93 mi) network of rapid transit lines spanning all major corridors within 20 years, including a line on the Radial Road 6 alignment, one of the region's busiest road corridor.

On March 16, 1988, the project was approved by the cabinet, and a feasibility study for the LRT Line 2, then called the MRT Line 2 project,[14][9] that would connect Marikina to the City of Manila via Aurora Boulevard and Ramon Magsaysay Boulevard was carried out in the same year.[15] Lavalin of Canada was interested in planning to build the line when the Philippine government would look to have a contract similar to the Bangkok system that was to be developed by the company (this was cancelled in 1992).[16] The project was to be bid out as a build-operate-transfer project together with the LRT Line 1 capacity expansion project in 1989.[15] In the same year, when President Corazon Aquino directed transportation secretary Rainerio Reyes to speed up the implementation of the line, the project was one of the 10 major infrastructure projects worth ₱8.7 billion.[17][18]

Although sixteen firms were reported to have submitted bids for the line's construction,[19] the bidding failed, causing delays. Only one consortium, made up of Japanese-European firms (Marubeni, Leighton, and Tractabel) and another Japanese firm, RRA International, attended the actual bidding. This means that the bidding for LRT 2 as a BOT project was unilaterally cancelled by transportation secretary Oscar Orbos, apparently in favor of a “ground-level” transit system.[15][20]

Another feasibility study was conducted in 1991 with financing from the Overseas Economic Cooperation Fund (OECF). The final revised project was approved on December 13, 1995 as a separate project from the LRT-1 capacity expansion project.[21][22][15] Early in 1994, the planned route was to run from Recto inside the Old Bilibid Prison to Katipunan, totaling 11.8 kilometers, but the actual route is 10 kilometers; the plan was also to have a depot located at the vacant site of Quezon Institute, and the plan was to have 26 2-car trains.[23]

Construction and opening

[edit]

The LRT Line 2 project officially began in 1996, twelve years after the opening of Line 1, with the granting of the official development assistance loans from the Japan Bank for International Cooperation (JBIC)[24] for the line's construction starting in March of that year.[11] The LRTA would have ownership of the system and assume all administrative functions, such as the regulation of fares and operations as well as the responsibility over construction and maintenance of the system and the procurement of spare parts for trains.

Construction started with a groundbreaking ceremony on November 15, 1997, after the LRTA signed the first three packages of the agreement with Sumitomo Corporation delivering Package 1 in which covers the construction of the depot and its facilities,[29][30] while the HanjinItochu joint venture delivered packages 2 and 3 in which covers the substructure and the superstructure plus the stations respectively.[31][32]

The project suffered delays in 1998 when the fourth package of the project, which includes the communications and fares systems, vehicles, and trackworks, were alleged to be anomalous, according to Senator Juan Ponce Enrile.[33] Although it was promptly corrected by the Estrada administration after it assumed power in the middle of that year, it encountered similar problems two years later. In April 2000, the National Economic and Development Authority (NEDA) met with officials from the Department of Transportation and Communications (DOTC). Out of the eight bidders, only two, Ansaldo; and Mitsui with Siemens, passed the technical evaluation process. To accommodate more bidders, especially that another two were disqualified, NEDA Secretary Felipe Medalla reportedly planned to lower the pre-qualification criteria from seventy percent to fifty percent, a move strongly opposed by the DOTC which reiterated that the seventy percent passing mark was only approved by the JBIC. However, Medalla reportedly justified his actions, saying that the JBIC was dissatisfied with the two qualified bidders and would stop all loans to the Philippines if more bidders were not added.[34]

Finally, in September 2000, Package 4 was awarded to the Asia-Europe MRT Consortium (AEMC), a consortium led by Marubeni and composed of Balfour Beatty, Toshiba, Daewoo Heavy Industries, and a local company which was D.M. Consuji Incorporated (DMCI).[35][24][36] AEMC, through Marubeni Corporation, entered into a contract with Singapore Technologies Engineering on December 12 of that year to supply and install the communications system, supervisory control and data acquisition (SCADA) system, automatic fare collection system, and the management information system.[28] The consortium provided the eighteen four-car trainsets built by Rotem and Toshiba.

During construction, the LRTA, along with the project consultants oversaw all the design, construction, equipping, testing, commissioning, and technical supervision of the project activities. Halcrow was appointed in 1997 as the lead consultant for the project.[37]

The pre-casting segmental method, a method used to launch girders and connect them to create a full span, was used in the construction of the original 13.8-kilometer (8.6 mi) line.[6][5][38]

On April 5, 2003, President Gloria Macapagal Arroyo inaugurated the line, effectively opening the first 4.3 kilometers (2.7 mi) from Santolan to Araneta Center-Cubao. Accompanying the president were former president Corazon Aquino, Transportation Secretary Leandro Mendoza, LRTA chief Teddy Cruz Jr., and other officials, who were the first official passengers of the "Megatren". Fares were free of charge until April 9.[39] All remaining stations opened on April 5, 2004,[38] except for Recto which opened on the following October 29.[40][41] However, ridership was initially moderate yet still far below expectations, since the passenger volume in this line is not yet fully achieved.[11]

To address passenger complaints on the lack of universal access on earlier train lines, the LRTA made sure during the construction phase that the stations were equipped with universal access by putting up escalators and elevators for easier access, as well as making passenger fares at par with the other existing lines. However, while all stations have elevators to and from the platform, not all stations have elevators to and from the station concourse on both sides of the road.

Extension to Antipolo

[edit]
Construction of Marikina–Pasig station in December 2018

Plans to extend the line to Antipolo in the province of Rizal were first laid out in 1999 as part of the Metro Manila Urban Transportation Integration Study Master Plan by the Japan International Cooperation Agency (JICA).[42] The extension was first approved by the Investment Coordination Committee (ICC) board of the National Economic and Development Authority (NEDA) in October 2003.[43][44]

On August 3, 2006, the Light Rail Transit Authority (LRTA) announced its intention to extend the line eastward to Antipolo, also intending to extend the line westward to Port Area, Manila.[45] In May 2011, LRTA secured commitments from the Philippine National Bank, Development Bank of the Philippines, and the Land Bank of the Philippines to fund the extension project.[46] JICA then released a feasibility study report the following October.[5] The 3.8-kilometer (2.4 mi) extension, starting from the eastern terminus of Santolan up to Antipolo station in Antipolo, called for two additional stations: Emerald station (now Marikina–Pasig) in Marikina near Sta. Lucia Mall and Robinsons Metro East; and Masinag (now Antipolo), in Antipolo near SM City Masinag. The ₱9.7 billion project, at its current form, was approved by the National Economic and Development Authority chaired by then-President Benigno Aquino III on September 4, 2012.[47] The Philippine national government funded the civil works contracts, while JICA funded the contract for the electrical and mechanical systems as part of its Capacity Enhancement of Mass Transit Systems in Metro Manila Project (CEMTSMMP) through a ¥43.2-billion loan for various projects of railway lines in Metro Manila.[48][49] The project aimed to accommodate an additional 80,000 passengers and reduce traffic congestion along Marcos Highway.[50]

The first two packages, awarded to D.M. Consunji Incorporated (DMCI), covered the design and construction of the viaduct and stations.[51][52] Unlike the original line which used the pre-casting segmental method of construction, the east extension viaduct made use of AASHTO girders with a deck slab above the girders.[5] Meanwhile, the third package, awarded to Marubeni and DMCI, covered the design and installation of the railway tracks and electrical and mechanical (E&M) systems of the extension.[53] The project broke ground on June 9, 2015, with an original 2017 deadline.[54] On May 30, 2017, another groundbreaking ceremony was held to mark the start of construction of the two stations.[52] The final phase of construction, covering the installation of the tracks, electrical and mechanical systems, commenced on April 16, 2019.[55] During construction, on March 10, 2017, a truck slammed in a concrete post of the east extension viaduct, killing one and injuring two.[56]

The initial 2017 deadline was not met, largely due to delays in the station's construction and the installation of the electrical and mechanical systems. It was repeatedly moved to 2020, before being delayed to 2021 due to the COVID-19 pandemic.[57][58][59][60] Nevertheless, the extension was inaugurated by President Rodrigo Duterte on July 1, 2021, before formally opening four days later with free rides for two weeks.[4][61][48]

In the following two months since its opening, a shuttle service was implemented between Antipolo and Santolan pending the completion of signaling integration, with one train running within the line's extension. This arrangement caused passenger complaints concerning its inefficiency, which was further exacerbated by the lack of operational trains.[62][63] Seamless end-to-end services were initially expected to begin within two weeks after opening,[64] but only started two months later on September 3, after integration works were completed.[a]

Extension to Cogeo

[edit]

Plans for the extension to Cogeo were mentioned in 1992.[67][68] The Japan International Cooperation Agency (JICA) has also proposed for a second phase of the east extension to extend the line to Cogeo and downtown Antipolo. There are provisions at the end of the current rail line at Antipolo station for an extension. Two proposals were presented by JICA: a 3-kilometer (1.9 mi), one-station underground extension, and a 6-kilometer (3.7 mi), five-station extension, both originating from Antipolo station.[13] As of November 2022, the feasibility study is nearing its conclusion. The extension would have three stations and the alignment is still being finalized.[69][70][71]

Route

[edit]
A train approaching Katipunan

The rail line serves the cities that Radial Road 6 passes through: Manila, San Juan, Quezon City, Marikina, Pasig (depot), and Antipolo. The rails are mostly elevated and erected either over or along the roads covered, with sections below ground before and after the Katipunan station, the only underground station on the line.

Stations

[edit]

The line serves 13 stations along its 17.6-kilometer (10.9 mi)-route.[72] The western terminus of the line is the Recto station at Recto Avenue, while the eastern terminus of the line is the Antipolo station along Marikina–Infanta Highway.

Three stations serve as connecting stations between other lines in the metro. Pureza is within walking distance to the Santa Mesa station of the PNR Metro Commuter Line; Araneta Center–Cubao is indirectly connected to the station of the same name on the MRT Line 3 through local streets and inter-connected mall passageways inside Araneta City; and Recto is indirectly connected to the Doroteo Jose station of the LRT Line 1 through a covered walkway. No stations are connected to other rapid transit lines within the paid areas.

LRT Line 2 stations timeline
Date opened Project Stations
April 5, 2003 Phase 1 SantolanAraneta Center–Cubao
April 5, 2004 Phase 2 Betty Go-BelmonteLegarda
October 29, 2004 Recto
July 5, 2021 East Extension Marikina–PasigAntipolo
Legend
Existing terminus
List of stations
Name Distance (km) Connections Location
Between
stations
Total
Antipolo 0.000
  •  3   56  SM Masinag
Antipolo, Rizal
Marikina–Pasig 2.232 2.232 Marikina
Santolan 1.795 4.027
Marikina / Pasig
Katipunan 1.970 5.997
  •  3  Katipunan
     18   36   39   41   50   51   56  Aurora Boulevard
Quezon City
Anonas 0.955 6.952
  •  3   51  Anonas
Araneta Center–Cubao 1.438 8.390
  •  1  Cubao
Betty Go-Belmonte 1.164 9.554
  •  3  Betty Go-Belmonte
Gilmore 1.075 10.629
  •  3  Gilmore
J. Ruiz 0.928 11.557
  •  3  J. Ruiz
San Juan
V. Mapa 1.234 12.791 Manila
Pureza 1.357 14.148
  •  2   3  Pureza
  • PUP Ferry Station
Legarda 1.389 15.537
  •  2   3  Legarda
Recto 1.050 16.587
  •  13   19   20   21  Avenida
     42  Recto
Tutuban
Mainline rail interchange  PNR
Divisoria none
Pier 4
  •  22   35  Recto
     44   45   46   47  Manila Northport
Stations, lines, and/or other transport connections in italics are either under construction, proposed, unopened, or have been closed.

Operations

[edit]

The line currently runs from 5:00 a.m. PST (UTC+8) until 9:30 p.m. on a daily basis.[73] It operates almost every day of the year unless otherwise announced. Special schedules are announced via the PA system at every station and also in newspapers and other mass media. During Holy Week, a public holiday in the Philippines, the rail system is closed for annual maintenance, owing to fewer commuters and traffic around the metro. Normal operation resumes after Easter Sunday.[74] During the Christmas and year-end holidays, the operating hours of the line are modified and shortened, due to the low ridership of the line during the holidays.[75]

Station facilities, amenities, and services

[edit]
Elevated pedestrian walkway
Bridge linking the Recto to the nearby Doroteo Jose

Station layout and accessibility

[edit]

Stations in the line are located above ground, except for Katipunan, which is located underground. Stations have a standard layout, with a concourse level and a platform level. The concourse contains ticket booths and is usually below the platform except for the underground station, with stairs, escalators and elevators leading down to the platform level. The levels are separated by fare gates. All stations are barrier-free inside and outside the station, and trains have spaces for passengers using wheelchairs.

Most station platforms are 100 meters (330 ft) long and 3.5 to 4.5 meters (11 to 15 ft) wide, with some stations having a length of 120 to 150 meters (390 to 490 ft).[6] All stations have side platforms, with the exception of Santolan, which as an island platform. Part of the platform at the front of the train is cordoned off for the use of pregnant women, children, elderly, and persons with disabilities. At side-platform stations, passengers are able to switch platforms at the concourse level without leaving the closed system, while passengers can easily switch sides at stations with island platforms. Stations have toilets at the concourse level, both inside and outside the closed system.

Folding bicycles are allowed to be brought into trains provided that it does not exceed the LRTA's baggage size limitations of 2 by 2 feet (20 by 20 in).[76] The last car of each train is also designated as "green zones", where folding bicycle users can ride with their bikes.[77]

The line has a total of 72 escalators and 40 elevators across all 13 stations.[78] However, by 2021, only a few elevators and escalators remain operational due to anomalies and corruption involving the procurement contracts,[79][80] causing complaints from passengers.[10] The elevators and escalators are being repaired and restored since 2022,[81] and more are being repaired and restored as of April 2022.[78]

Shops and services

[edit]

Stations have at least one stall or stand where people can buy food or drinks, which vary by station. Some stations, such as Araneta Center-Cubao, are connected at concourse level to nearby buildings, such as shopping malls, for easier accessibility.

Since November 19, 2001, in cooperation with the Philippine Daily Inquirer, passengers have been offered copies of the Inquirer Libre, a free, tabloid-size, Tagalog version of the Inquirer, which is available at all stations.[82][83]

Ridership

[edit]

The line is designed and was forecasted to carry 570,000 passengers daily.[11] However, the line operates under its designed capacity since its opening,[84] government officials have admitted that system extensions are overdue, although in the absence of major investment in the system's expansion, LRTA has resorted to experimenting with and/or implementing other solutions to maximize the use of the system, including having bus feeder lines.[85]

Before the pandemic, the line had a ridership of 200,000 passengers, but the ridership soon decreased in 2019 due to lack of trains and a power trip that closed three stations in October 2019 that was reopened in January 2021. The line served 33,267 passengers daily on average in 2021,[72] with eight trains available for revenue service running at an operating speed of 60 kilometers per hour (37 mph) in ten-minute intervals, and one train in reserve for rush hour services, which cuts the time intervals to a minimum of eight minutes.[86] Ridership through the year 2024 reached 138,455 daily passengers, while the line's annual total ridership increased to 49.42 million passengers, which serves as the highest total passenger ridership count in 3 years.[3] In August 2024, the total daily average of passengers commuting along the line reached 149,331 passengers.[2]

Statistics

[edit]
Year Daily Average[87] Yearly Total[87]
2003 9,221 2.36 million[88]
2004 Increase 61,337 Increase 23.03 million
2005 Increase 116,082 Increase 41.90 million
2006 Increase 132,154 Increase 47.57 million
2007 Increase 147,032 Increase 52.93 million
2008 Increase 161,846 Increase 58.59 million
2009 Increase 171,996 Increase 62.09 million
2010 Increase 175,501 Increase 63.36 million
2011 Increase 176,818 Increase 63.81 million
2012 Increase 194,268 Increase 70.33 million
2013 Increase 197,924 Increase 71.45 million
2014 Increase 201,794 Increase 72.85 million
2015 Decrease 172,318 Decrease 62.21 million
2016 Increase 185,071 Increase 67.00 million
2017 Decrease 182,708 Decrease 65.96 million
2018[89] Decrease 177,260 Decrease 64.70 million
2019[90] Decrease 156,110 Decrease 56.98 million
2020[72] Decrease 45,463 Decrease 12.50 million
2021[72] Decrease 33,267 Decrease 11.84 million
2022[91] Increase 88,597 Increase 31.63 million
2023[3] Increase 138,455 Increase 49.42 million

Rolling stock

[edit]
Interior of a 2000 class train

The line runs sixteen electric multiple units made in South Korea by Hyundai Rotem powered by Toshiba-made VVVF inverters.[92] The trains came in together with the fourth package during the system's construction. The four-car trains have a capacity of 1,628 passengers, which is more than the normal capacity of the rolling stock of Lines 1 and 3. The trains are capable of running at a maximum design speed of 80 kilometers per hour (50 mph), but only run at a maximum operational speed of 60 kilometers per hour (37 mph). These trains prominently use wrap advertising.

In 2017, the entire train fleet was retrofitted with the TUBE (formerly known as PARDS), a passenger information system powered by LCD screens installed near the ceiling of the train that shows news, advertisements, current train location, arrivals and station layouts.[93]

In 2019, the train ventilation was upgraded to replace the aging air-conditioning units and to alleviate complaints of the commuters for uncomfortable hot rides.[94] Two years later, three train sets underwent refurbishment and resulted in new fitted propulsion systems and train monitoring systems from Woojin Industrial Systems.[95]

The LRTA is also acquiring 14 additional train sets by 2020 to augment the existing 18 sets, due to the expected increase of passengers ahead of the East Extension, and the West Extension.[96] The purchase however was delayed to 2022.[97][needs update]

Included in the design-and-build contract of the west extension is the procurement of five four-car train sets.[98]

Depot

[edit]

The line maintains an at-grade depot in Barangay Santolan in Pasig, near Santolan station in the side of Barangay Calumpang in Marikina. The depot occupies approximately 10 hectares (25 acres) of space and serves as the headquarters for light and heavy maintenance.[37] Due to its location in a flood-prone area, the depot was raised 2 meters (6.6 ft) above ground level.[37] It is connected to the mainline network by a spur line.

The depot is capable of storing 24 sets of electric multiple units, with the option to expand to include more vehicles as demand arises. They are parked on several sets of tracks, which converge onto the spur route and later on to the main network.[99]

There are eight decommissioned 1000 class and one set of 1100 class trains formerly used in LRT Line 1 being stored in this depot due to the expansion of the Line 1 depot in Parañaque.

Other infrastructure

[edit]

Signaling

[edit]

The line uses a fixed block system with automatic train control (ATC), which has three subsystems: automatic train protection (ATP), automatic train operation (ATO), and Rail9000 automatic train supervision (ATS). The ATO subsystem automatically drives the trains, while the opening and closing of doors is controlled by an onboard train attendant. The ATP system, meanwhile, maintains safe operations and monitors the train's speed. Lastly, the Rail9000 ATS system is located at the operations control center at the line's Santolan Depot, which directs train operations and monitors the train movement along the line.[6] Other components of the signaling system includes train detection through track circuits and Westrace MK1 computer-based interlocking.[8][99]

The signaling equipment were manufactured by Westinghouse Signals (later Westinghouse Rail Systems, acquired by Siemens in 2013).[7]

The signaling system was upgraded with the replacement of its communication link and the upgrading of the Westrace interlocking module. The project started on February 15, 2022,[100] and was completed on March 29.[101]

Tracks

[edit]

The rails are 54-kilogram-per-meter (36 lb/ft) rails designed to the UIC 54 rail profile. The rails are supported by concrete plinths.[5][102]

Plans and proposals

[edit]

West extension

[edit]

A 3.02-kilometer (1.88 mi) extension of the line to the Manila North Harbor in Tondo, Manila has been proposed. It was first announced in August 2006, when the LRTA announced its intention to extend the line eastward to Antipolo and westward to the Pier 4 of the Manila North Harbor.[45] It was approved by the National Economic and Development Authority (NEDA) on May 19, 2015. The construction of this extension would create three stations, one near the Tutuban PNR station, one in Divisoria, and one near the North Port Passenger Terminal in Manila North Harbor's Pier 4 which would serve as its terminus.[103] In an interview, LRTA Administrator Ret. Gen. Reynaldo Berroya stated that they are aiming to finish the project by 2022 to 2023. The project is now expected to start construction in 2025.[104]

The total project cost is estimated to be ₱10.12 billion.[105] In 2019, WESTRAX Joint Venture was awarded the contract for the consultancy services for the project.[12]

In October 2019, the project was under bidding process, consisting 3 stations, Tutuban, Divisoria, and Pier 4, with the project scheduled to be completed by 2024.[12]

On August 27, 2020, the Light Rail Transit Authority published the bidding documents for the design-and-build contract for the west extension. According to the documents, the turn back area after the Pier 4 station will have three tracks; two of which are the main tracks and one serves as a pocket track. The three stations will feature side platforms.[98]

The project was originally planned to be funded through a public-private partnership (PPP) scheme, in line with the Marcos administration's policy to use the said scheme to complete various infrastructure projects. The contract would have also covered the procurement of five new four-car trains, along with the maintenance of the line and the refurbishment of the trains.[105] However, it was decided that the government will instead fund the project through the national budget.[69]

Privatization

[edit]

The privatization of the operations and maintenance of Line 2 was planned by the then-Department of Transportation and Communications (DOTC; later the Department of Transportation as part of the agency's improvement and modernization of the railway lines in the Philippines. The bidding process for this project begun on September 13, 2014.[106] In this project, the interested companies were required to submit pre-qualification documents and submit a bid proposal if the company is qualified for the bidding. In January 2015, four companies submitted pre-qualification documents for the project. The bidders included Aboitiz Equity Ventures with SMRT Transport Solutions (Aboitiz Equity Ventures and SMRT International Pte Ltd. through SMRT Trains),[107] DMCI Holdings with Tokyo Metro, Light Rail Manila 2 Consortium (RATP and Metro Pacific),[108] and San Miguel Corporation with Korea Railroad Corporation. All bidders were pre-qualified for the bidding.[109] However, the project would eventually be shelved in 2016.

In 2017, it was reported that the Metro Pacific Investments Corporation was interested in a possible auction for the privatization of the line.[110] The plan to privatize the operations and maintenance of the line was restarted in October 2019, following a power trip that damaged two rectifiers.[111] Since then, no new reports have surfaced about this plan as of 2021.

Capacity expansion and upgrade

[edit]

Due to the aging of the line, a capacity expansion project for the line was announced in April 2022. The project would include upgrades to the trains, signaling, telecommunications, power supply, overhead systems, railway tracks, and other system equipment. The project is still under the stages of the procurement of a consultant for the project, which would assess the current condition of the line.[112]

TÜV Rheinland has been shortlisted for the list of consultants and is the only consultant to be shortlisted in June 2022.[113]

Like the west extension, the upgrading of the train cars would be funded through a public-private partnership scheme. The contract would also cover the maintenance of the line and the construction of the west extension.[105]

Incidents

[edit]
  • On June 11, 2011, a man jumped in front of a moving train at the Araneta Center-Cubao station, leaving the man severely injured. This forced the line operations to be suspended.[114][115]
  • On May 9, 2017, at 4:03 PM, a tree fell to the tracks at the Anonas area, causing the line's operations to be disrupted and a 2000 class train nearby was hit. The Department of Public Works and Highways local office was doing roadworks at the site of the incident when they accidentally hit a tree that fell on the tracks. Partial operations between Recto and V. Mapa were implemented, until the line's operations were suspended an hour later. The incident area was cleared and full operations resumed at 7:41 PM.[116]
  • On May 30, 2018, a damaged cable between J. Ruiz and V. Mapa stations caused limited operations between Santolan and Araneta Center-Cubao stations at 11:46 AM. Normal operations resumed at 7:46 PM.[117]
  • On May 18, 2019, two trains collided between Anonas and Cubao stations, injuring 34 passengers, with none in critical condition.[118][119] Revenue operations were suspended to give way to maintenance checks, and normal operations resumed at 10:47 AM the next day.[120] Trainset no. 18 returned to service in June 2021,[121] while Trainset no. 13 returned to service in September 2021.
  • On October 2, 2019, at 9:43 am, a lightning struck the Gilmore station, causing the power transformers at the J. Ruiz and Araneta Center-Cubao stations to trip and disrupt the power supply. The operations of the line were suspended for safety checks and normal operations resumed at 10:11am.[122]
  • On October 3, 2019, another power trip caused rectifier substations located between Anonas and Katipunan stations and in the Santolan depot to catch fire at around 11 in the morning, cutting the line's power supply in the area. Line operations from Recto to Santolan were suspended at 11:24 am, and passengers were evacuated from the line with no injuries. The LRTA, MMDA and the Philippine Coast Guard immediately deployed shuttle buses to help ferry stranded passengers. Partial operations between Cubao and Recto stations resumed on October 8, 2019, while Santolan, Katipunan and Anonas Stations are expected to reopen after nine months. The initial estimated amount of damages is at around PHP428 million.[123] Due to the incident, the Light Rail Transit Authority claimed full operations would be back in 2 to 3 months.[124] As the initial deadline was not met the three stations that were caught in a power trip were expected to resume services at the end of June 2020.[125] However, this deadline was also not met due to delays brought by the COVID-19 pandemic, rescheduled for the first quarter of 2021.[126] Finally, the three stations were reopened, albeit in partial speed, on January 22, 2021.[50] The reopening was made possible by a temporary power supply system installed in the damaged portion while the proper systems are still on order and awaiting delivery.
  • On October 8, 2020, a fire broke out in the electrical room at Santolan causing the operations to be suspended at 5:10am. The fire damaged the station's uninterruptible power supply. Normal operations returned a few hours later.[127][128]
  • On September 17, 2021, a defective catenary wire at the east extension area caused disruptions in operations. A shuttle service between Santolan and Antipolo was implemented at 9:43 AM. On the same day, the line's operations were briefly suspended at 11:36 AM after a tangled t-shirt was seen hanging at the contact wires between Cubao and Anonas stations. Operations with the shuttle service resumed at 11:49 AM, while full end-to-end operations were known to be resumed the following day.[129]
  • On October 9, 2021, an entangled balloon was discovered between V. Mapa and Pureza stations, causing the line's operations to be temporarily suspended. The operations resumed after 30 minutes.[130]
  • On August 17, 2024, a street dweller was spotted in between the rail line’s Pureza and Legarda stations. The situation forced to limit the train line's service from Antipolo to V. Mapa. Normal operations resumed after a few hours.[131]
  • On August 19, 2024, a catenary cable caught fire between the Katipunan and Santolan stations. This led the line's operations to be limited from Recto to Cubao. It was only the following morning wherein full operations resumed.[132]
  • On September 11, 2024, a power supply problem halted operations between V. Mapa and Recto stations. Operations resumed five hours after the incident.[133]
  • On September 12, 2024, a damaged pantograph on a Class 2000 train at J. Ruiz station caused a brief halt on operations.[134]

Notes

[edit]
  1. ^ The date when the end-to-end operations between Antipolo and Recto and vice versa began varies per source. According to LRTA, it began on September 3, 2021.[65] Meanwhile, some news outlets state that end-to-end services begun on September 7.[66]

References

[edit]
  1. ^ a b c "The Line 2 System". Light Rail Transit Authority. Archived from the original on October 11, 2014. Retrieved June 10, 2014.
  2. ^ a b Rosales, Elijah Felice. "No budget allotment for LRT rehab in 2025". Philstar.com.
  3. ^ a b c "LRT-2 Sets New Ridership Record with Over 49 Million Passengers in 2023 | Light Rail Transit Authority". January 3, 2024.
  4. ^ a b c Grecia, Leandre (July 5, 2021). "The new LRT-2 stations in Marikina and Antipolo are now operational". Top Gear Philippines. Retrieved July 5, 2021.
  5. ^ a b c d e Japan International Cooperation Agency (October 2011). PREPARATORY STUDY FOR LRT LINE2 EXTENSION PROJECT : FINAL REPORT (PDF) (Report). Retrieved November 8, 2021.
  6. ^ a b c d e Light Rail Transit Authority (August 9, 2017). Maintenance of the Manila LRT Line 2 System, Terms of Reference (PDF) (Report). Light Rail Transit Philippines. Archived (PDF) from the original on June 12, 2020. Retrieved December 26, 2021.
  7. ^ a b Contract for the Supply of Various Signaling Equipment (Interlocking, Jointless Track Circuits, and Miscellaneous Wayside) or its approved equivalent (PDF) (Report). Light Rail Transit Authority. March 16, 2022. pp. 40–46. Retrieved March 22, 2022.
  8. ^ a b "Request for Proposal (Negotiated Procurement)" (PDF). Light Rail Transit Authority. March 3, 2021. Retrieved February 23, 2022.
  9. ^ a b c Madarang, Catalina Ricci S. (October 7, 2019). "It's a misnomer! Light Rail Transit Line 2 is actually a heavy rail-subway system". InterAksyon. Retrieved January 5, 2022.
  10. ^ a b Cordero, Ted (January 8, 2022). "LRTA apologizes for defective elevators, escalators; complaints filed vs officials allegedly involved in anomalous purchase". GMA News. Retrieved January 9, 2022.
  11. ^ a b c d Japan International Cooperation Agency (2009). Metro Manila Strategic Mass Rail Transit Development (I), (II), (III) (PDF) (Report). Retrieved April 4, 2022.
  12. ^ a b c "LOOK: Gov't to build 3 more Line 2 stations". ABS-CBN News. October 13, 2019. Retrieved October 14, 2019.
  13. ^ a b "ROADMAP FOR TRANSPORT INFRASTRUCTURE DEVELOPMENT FOR METRO MANILA AND ITS SURROUNDING AREAS (REGION III&REGION IV-A)" (PDF). March 2014. p. 14. Archived (PDF) from the original on June 27, 2020. Retrieved July 18, 2021.
  14. ^ "Tutuban-Cubao LRT okayed". Manila Standard. March 17, 1988.
  15. ^ a b c d World Bank (December 2, 2004). A Tale of Three Cities: Urban Rail Concessions in Bangkok, Kuala Lumpur and Manila – Final Report (PDF) (Report). Author. p. 17. Archived from the original (PDF) on April 24, 2006. (Prepared by Halcrow Group Limited).
  16. ^ "Doubly hurting". Manila Standard. December 10, 1988. p. 10.
  17. ^ "Cory: Speed up implementation of new LRT line". Manila Standard. March 11, 1989. p. 9.
  18. ^ "New LRT must be better". Manila Standard. April 20, 1989. p. 10.
  19. ^ Cuneta, Jopen (April 16, 1990). "16 foreign firms file bids for construction of LRT 2". Malaya.
  20. ^ "New bidding for LRT II mulled". The Philippine Star. May 3, 1990. p. 13.
  21. ^ "Manila rail project to get foreign loans". The Business Times. August 20, 1991. p. 18.
  22. ^ "P-26B LRT 2 project okayed". Manila Standard. December 13, 1995. p. 15.
  23. ^ "DOTC allots P15.7-B for LRT 2 Project". Manila Standard. June 20, 1994. p. 6.
  24. ^ a b Reyes, Miguel Paolo P. "It's Not You, It's Me? An Inquiry into the Problems of Philippine-Korean Cooperation for Metro Manila's Rail-based Mass Transit Systems" (PDF). The Mass Transit System in Metro Manila: From Tranvia to MRT, 1879-2014. University of the Philippines Diliman. Retrieved January 31, 2022.
  25. ^ COA, 1998: n.p.
  26. ^ "Philippines | Projects | Fujita". Fujita Corporation. Retrieved July 3, 2024.
  27. ^ "Metro Manila Mass Rail Transit - Line 2". Rizzani de Eccher. Retrieved May 20, 2024.
  28. ^ a b Singapore Technologies Electronics. "Electronics Systems Package for Manila Line 2, Philippines" (PDF). Singapore Technologies Engineering. Archived from the original (PDF) on November 18, 2006. Retrieved February 6, 2022.
  29. ^ "日本財団図書館(電子図書館) マニラ首都圏の公共交通整備に関する研修用ソフト制作事業 利用手引書". nippon.zaidan.info. Retrieved May 17, 2024.
  30. ^ "Package 1 - Depot". Metro Manila Strategic Mass Rail Transit Development Project Line 2 - Megatren. Light Rail Transit Authority. Archived from the original on May 5, 2006. Retrieved December 23, 2021.
  31. ^ "Package 2 - Substructure". Metro Manila Strategic Mass Rail Transit Development Project Line 2 - Megatren. Light Rail Transit Authority. Archived from the original on May 5, 2006. Retrieved December 23, 2021.
  32. ^ "Package 3 - Superstructure and Stations". Metro Manila Strategic Mass Rail Transit Development Project Line 2 - Megatren. Light Rail Transit Authority. Archived from the original on May 5, 2006. Retrieved December 23, 2021.
  33. ^ "Anomaly in LRT-2 bidding - Enrile". Today. February 3, 1998.
  34. ^ "LRT 2 bidding hounded by alleged anomalies". Philstar.com. May 3, 2000. Retrieved May 29, 2024.
  35. ^ Baetiong, May Czarina A. (September 13, 2000). "Marubeni-led consortium bags light railway contract". Business World.
  36. ^ "Package 4 - Systems, Vehicles and Trackworks". Metro Manila Strategic Mass Rail Transit Development Project Line 2 - Megatren. Light Rail Transit Authority. Archived from the original on May 5, 2006. Retrieved December 23, 2021.
  37. ^ a b c "Manila light rail transit – Purple Line". Halcrow. Archived from the original on April 26, 2010. Retrieved April 5, 2022.
  38. ^ a b "Railway Operations". Light Rail Transit Authority. Archived from the original on July 24, 2021. Retrieved September 3, 2021.
  39. ^ Villanueva, Marichu A. (April 6, 2003). "GMA leads Megatren inauguration". The Philippine Star. Retrieved June 27, 2024.
  40. ^ "The Metro Manila Strategic Mass Rail Transit Development Line 2 Project". Light Rail Transit Authority. Archived from the original on May 17, 2006. Retrieved December 23, 2021.
  41. ^ Bergonia, Allan (October 28, 2004). "Line 2 Recto Station Opens". People's Journal. Archived from the original on March 8, 2005. Retrieved May 11, 2006 – via lrta.gov.ph.
  42. ^ Abadilla, Emmie V. (July 1, 2021). "P4.5-B LRT-2 East Extension to start operation next week". Manila Bulletin. Archived from the original on March 9, 2022. Retrieved July 1, 2021.
  43. ^ "MRT Line 2 East Extension Project". Light Rail Transit Authority. Archived from the original on October 17, 2003. Retrieved February 18, 2022.
  44. ^ Ho, Abigail L. (October 14, 2003). "Extension of LRT Line 2 to Antipolo gets NEDA backing". Philippine Daily Inquirer. Archived from the original on March 12, 2007. Retrieved February 18, 2022.
  45. ^ a b "Gov't planning to extend LRT Line 2". GMA News. August 3, 2006. Retrieved April 4, 2022.
  46. ^ Amojelar, Darwin G. (May 9, 2011). "Govt secures commitments for LRT 2 extension funds". The Manila Times. Retrieved February 18, 2022 – via Public-Private Partnership Center.
  47. ^ Gonzalez, Mia M. (September 4, 2012). "Neda Board OKs 9 big projects". Business Mirror. Archived from the original on September 6, 2012. Retrieved September 6, 2012.
  48. ^ a b "Duterte: Free rides from Antipolo to Santolan stations, vice versa for 2 weeks". GMA News. July 1, 2021. Retrieved July 1, 2021.
  49. ^ Status of LRT Projects as of December 31, 2021 (PDF) (Report). Light Rail Transit Authority. January 19, 2022. p. 4. Archived from the original (PDF) on January 31, 2022. Retrieved January 31, 2022.
  50. ^ a b Ong, Ghio (January 10, 2021). "3 LRT-2 stations set to reopen". Philstar.com. Retrieved January 12, 2021.
  51. ^ a b "DMCI bags P2.3-B LRT-2 extension project". ABS-CBN News. January 27, 2015. Retrieved July 8, 2021.
  52. ^ a b c "DOTr AND LRTA BREAKS GROUND FOR LRT2 EAST EXTENSION PROJECT - PACKAGE 2". dotr.gov.ph. Department of Transportation. Archived from the original on July 9, 2021. Retrieved July 8, 2021.
  53. ^ a b "LRT Line 2 East Extension Project Awarded to Marubeni-DMCI". Marubeni Philippines Corporation. March 7, 2019. Retrieved July 8, 2021.
  54. ^ Manabat, Jacque (June 9, 2015). "Next stop, Antipolo: LRT-2 begins expansion". ABS-CBN News. Archived from the original on June 2, 2016. Retrieved April 27, 2022.{{cite news}}: CS1 maint: unfit URL (link)
  55. ^ Mercurio, Richmond (April 17, 2019). "Final phase of LRT-2 extension project starts". The Philippine Star. Retrieved November 30, 2021.
  56. ^ Bondoc, Marlly Rome C. (March 10, 2017). "One dead, two injured as dump truck slams into LRT-2 post in Marikina". GMA News. Retrieved November 10, 2021.
  57. ^ Quismorio, Ellson (February 26, 2021). "Anticipating Antipolo: DOTr hypes up April opening of new LRT-2 stations". Manila Bulletin. Archived from the original on May 21, 2022. Retrieved March 2, 2021.
  58. ^ Cordero, Ted (March 4, 2021). "LRT2 East Extension to commence ops on April 27". GMA News.
  59. ^ Rey, Aika (April 16, 2021). "COVID-19 curbs delay LRT2 East Extension opening to June 23". Rappler. Retrieved April 16, 2021.
  60. ^ "LRT-2 East Extension Project inauguration moved; weekend closures announced". CNN Philippines. June 21, 2021. Archived from the original on June 21, 2021. Retrieved June 22, 2021.
  61. ^ "Manila Light Rail Transit Line 2 East Extension Line Starts Operation". Marubeni Corporation. July 6, 2021. Retrieved July 8, 2021.
  62. ^ Grecia, Leandre (July 5, 2021). "New LRT-2 stations riddled with long queues on first day of operations". Top Gear Philippines. Retrieved November 24, 2021.
  63. ^ Rosales, Clara (July 2, 2021). "Free Rides, Fares, More: LRT-2 Marikina, Antipolo Stations Open Today". reportr.world. Retrieved November 24, 2021.
  64. ^ "More trains to operate in LRT-2 east extension after July 18 – LRTA". CNN Philippines. July 5, 2021. Archived from the original on July 6, 2021. Retrieved July 6, 2021.
  65. ^ "Updated LRT-Line 2 Operating Hours (Implementation of Full-line Operations)". Light Rail Transit Authority. September 3, 2021. Retrieved September 9, 2021.
  66. ^ Cerrudo, Aileen (September 7, 2021). "Full-line operation of LRT-2 East Extension stations begin". UNTV News and Rescue. Retrieved September 9, 2021.
  67. ^ "DOTC told to speed up on LRT phase II". Manila Standard. July 18, 1992. p. 15.
  68. ^ "LRT II to be constructed by year' end". Manila Standard. August 22, 1992. p. 7.
  69. ^ a b Rosales, Elijah Felice (November 1, 2022). "3 new stations mulled on Rizal end of LRT-2". The Philippine Star. Retrieved November 2, 2022.
  70. ^ "Antipolo discusses LRT-2 extension project, sees great benefits for the city". Politiko South Luzon. September 30, 2022. Retrieved October 1, 2022.
  71. ^ "LRT-2 extension under study". BusinessWorld Online. August 21, 2023.
  72. ^ a b c d YEAR-END ACCOMPLISHMENT REPORT (PDF) (Report). Light Rail Transit Authority. December 31, 2021. Retrieved March 8, 2022.
  73. ^ Regalado, Pia (June 17, 2022). "LRT-2 Extends Operating Hours at Night". reportr.world. Retrieved June 18, 2022.
  74. ^ "MRT, LRT-2 to suspend operations during Holy Week holidays". ABS-CBN News. March 13, 2023. Retrieved March 13, 2023.
  75. ^ Grecia, Leandre (December 21, 2021). "Here are the LRT-1, LRT-2, MRT-3 schedules for Christmas 2021". Top Gear Philippines. Retrieved December 21, 2021.
  76. ^ "Wala pong limit sa diameter ng wheels. Kaugnay naman po ng bagahe, hanggang 2 feet x 2 feet po ang maximum dimension na pinapayagan sa LRT-2". Twitter. Retrieved May 15, 2022.
  77. ^ Dedace, Sophia (November 18, 2009). "Bikes, trains, and fewer cars with LRT's Bike O2 project". GMA News Online. Retrieved May 15, 2022.
  78. ^ a b Layson, Mer (April 18, 2022). "Escalators, elevators ng LRT-2, operational na simula Lunes". Pilipino Star Ngayon (in Filipino). Retrieved April 19, 2022.
  79. ^ "LRTA management files corruption cases against agency execs, contractors linked to anomalous purchase of substandard equipment" (Press release). Light Rail Transit Authority. December 13, 2021. Retrieved January 5, 2022.
  80. ^ Villanda, Karen (December 13, 2021). "LRTA files graft case due to anomaly purchase of LRT-2 equipment". PTV News. Retrieved January 5, 2022.
  81. ^ Dela Cruz, Raymond Carl (January 20, 2022). "28 more LRT-2 elevators, escalators restored". Philippine News Agency. Retrieved January 21, 2022.
  82. ^ Ulanday, Abelardo S. (December 9, 2001). "The best things in life are Libre". Philippine Daily Inquirer. Retrieved August 14, 2014 – via Google News Archive.
  83. ^ Vega, Chito dela (January 16, 2017). "Libre renews train distribution contracts". INQUIRER.net. Retrieved June 8, 2024.
  84. ^ Climate-Eval (GEF IEO) (August 2009). Republic of the Philippines: Metropolitan Manila Strategic Mass Rail Transit Development-Line 2 (PDF) (Report). Author. Archived from the original (PDF) on August 21, 2014. Retrieved August 18, 2014. (Prepared by Sanshu Engineering Consultant)
  85. ^ Light Rail Transit Authority (October 29, 2013). Interim Performance Scorecard for CY 2013 (PDF) (Report). Author. Archived from the original (PDF) on August 21, 2014. Retrieved August 18, 2014.
  86. ^ "Status and availability of the Line 2 train fleet". eFreedom of Information. Government of the Philippines. Retrieved December 29, 2021.
  87. ^ a b "Monthly Ridership – Line 2 System Ridership" (PDF). Light Rail Authority. Retrieved January 4, 2019.
  88. ^ "LRT 2 Close to Hitting 2004 Ridership Target". Daily Tribune. August 9, 2004. Archived from the original on November 12, 2004. Retrieved March 29, 2022 – via Light Rail Transit Authority.
  89. ^ Annual Report 2018 (PDF) (Report). Light Rail Transit Authority. December 31, 2018. p. 20. Archived from the original (PDF) on January 2, 2020. Retrieved January 2, 2020.
  90. ^ Accomplishment Report - CY2019 (PDF) (Report). Light Rail Transit Authority. December 31, 2019. p. 17. Retrieved March 2, 2022.
  91. ^ Ong, Ghio (January 10, 2023). "MRT-3, LRT-2 post surge in ridership". The Philippine Star. Retrieved January 23, 2023.
  92. ^ Toshiba (2003). Power Systems and Industrial Equipment (PDF) (Report). Retrieved April 8, 2022.
  93. ^ "Line 2 unveils PARDS for passengers". ABS-CBN. ANC. May 6, 2017. Retrieved May 23, 2020.
  94. ^ Rita, Joviland (March 7, 2019). "Expect 'cooler' LRT2 trains as aircon units undergo temporary fix before being replaced". GMA News. Retrieved November 3, 2021.
  95. ^ Cordero, Ted (March 11, 2021). "LRT2 to add more running trains by April, says LRTA". GMA News. Retrieved March 19, 2022.
  96. ^ Pateña, Aerol John (March 7, 2019). "Expect more comfortable LRT-2 trains by April: LRTA". Philippine News Agency.
  97. ^ Balinbin, Arjay (February 11, 2020). "LRT-2 extension 77% complete". Bworldonline.com. Retrieved March 9, 2021.
  98. ^ a b "Bidding of the Design-and-Build Contract for One (1) Lot for LRT Line 2 West Extension Project" (PDF). Light Rail Transit Authority. August 27, 2020. Archived from the original (PDF) on December 15, 2023. Retrieved March 15, 2022.
  99. ^ a b Department of Transportation and Communications; Light Rail Transit Authority (September 2014). LRT LINE 2 OPERATIONS AND MAINTENANCE PROJECT (PDF) (Report). Archived from the original (PDF) on November 22, 2021. Retrieved November 22, 2021.
  100. ^ Cabuenas, Jon Viktor D. (February 13, 2022). "LRT-2 delays expected as signaling system undergoes upgrade". GMA News. Retrieved February 13, 2022.
  101. ^ Year-End Accomplishment Report (CY 2022) (PDF). Light Rail Transit Authority (Report). April 2023. Retrieved June 11, 2024.
  102. ^ Rail Section Profiles from TECHNICAL REQUIREMENTS - DRAWINGS (PDF). BIDDING DOCUMENTS - CAPACITY ENHANCEMENT OF MASS TRANSIT SYSTEMS IN METRO MANILA: PROCUREMENT OF TRACKWORKS, ELECTRICAL AND MECHANICAL SYSTEMS AND INTEGRATION WITH EXISTING SYSTEMS FOR LRT LINE 2 EAST (MASINAG) EXTENSION PROJECT (Report). Archived from the original (PDF) on December 27, 2021. Retrieved February 3, 2022.
  103. ^ Naguit, Roices (May 19, 2015). "President Aquino approves Line 2 extension to Manila port area, 6 other infra projects". Interaksyon. Archived from the original on May 22, 2015. Retrieved May 20, 2015.
  104. ^ Piad, Tyrone Jasper C. (January 2024). "LRT 2 project linking Recto, Tondo kicking off in 2025". Inquirer.net.
  105. ^ a b c Rosales, Elijah Felice (July 25, 2022). "Bidders sought for P10 billion LRT upgrade, extension". The Philippine Star. Retrieved July 25, 2022.
  106. ^ "DOTC awards LRT-1 Cavex PPP; starts bid for LRT-2 O&M". Official Gazette of the Republic of the Philippines. September 13, 2014. Retrieved September 19, 2021.
  107. ^ "Aboitiz Equity Ventures, Inc. and SMRT Transport Solutions Consortium" (PDF). PRE-QUALIFICATION OF THE LIGHT RAIL TRANSIT LINE 2 OPERATIONS AND MAINTENANCE PROJECT. February 17, 2015. Archived from the original (PDF) on December 27, 2021. Retrieved February 3, 2022.
  108. ^ "LRM2 Consortium" (PDF). PRE-QUALIFICATION OF THE LIGHT RAIL TRANSIT LINE 2 OPERATIONS AND MAINTENANCE PROJECT. February 17, 2015. Archived from the original (PDF) on December 27, 2021. Retrieved February 3, 2022.
  109. ^ Desiderio, Louella (April 2, 2016). "LRT-2 bidding postponed anew". The Philippine Star. Retrieved September 19, 2021.
  110. ^ Delavin, Imee Charlee C. (June 6, 2017). "Metro Pacific interested in possible LRT-2 O&M auction". BusinessWorld. Retrieved September 19, 2021 – via ppp.gov.ph.
  111. ^ Cervantes, Filane Mikee (October 8, 2019). "Solon pushes for LRT-2 privatization". Philippine News Agency. Retrieved September 19, 2021.
  112. ^ "Request for Expression of Interest (REI) for Consulting Services for the LRT Line 2 Capacity Expansion" (PDF). Light Rail Transit Authority. April 27, 2022. Retrieved April 27, 2022.
  113. ^ Consulting Services for the LRT Line 2 Capacity Expansion (PDF) (Report). Light Rail Transit Authority. June 2, 2022 [June 1, 2022]. Retrieved June 2, 2022.
  114. ^ Datu, Dennis; Ibanez, Jon; Gutierrez, Pia (June 11, 2011). "Man jumps in front of LRT train". ABS-CBN News. Retrieved July 11, 2021.
  115. ^ Man jumps in front of LRT. YouTube (video). June 19, 2011. Archived from the original on December 14, 2021. Retrieved July 11, 2021.
  116. ^ Esperas, Raoul (May 9, 2017). "LRT-2 operation resumes after clearing of tree branches". ABS-CBN News. Retrieved September 7, 2021.
  117. ^ "LRT-2 limits trips over damaged power lines". CNN Philippines. May 30, 2018. Archived from the original on April 16, 2021. Retrieved April 16, 2021.
  118. ^ Barcelon, Paolo (May 19, 2019). "Authorities to probe Line 2 collision that injured 34". CNN Philippines. Archived from the original on May 19, 2019. Retrieved May 19, 2019.
  119. ^ Rita, Joviland (May 19, 2019). "Probe underway into Line 2 trains collision; 34 hurt". GMA News Online. Retrieved May 19, 2019.
  120. ^ Dava, Bianca (May 19, 2019). "LRT-2 resumes operations after train collision". ABS-CBN News. Retrieved March 7, 2021.
  121. ^ "LRTA Line 2 TS #18 is back on track while TS #13 is 15% complete as of April 2021". Facebook. Retrieved July 13, 2021.
  122. ^ Ong, Ghio (October 3, 2019). "Power glitches disrupt LRT-2, MRT-3 operations". Philstar Global. Retrieved May 26, 2021.
  123. ^ "Line 2 temporarily halts operation due to power supply problem caused by fire". GMA News Online. October 3, 2019.
  124. ^ "Line 2 full operations eyed to resume in 2 to 3 months". ABS-CBN News. October 14, 2019. Retrieved February 4, 2020.
  125. ^ Luna, Franco (February 3, 2020). "Anonas, Katipunan and Santolan Line 2 stations to be repaired by end of June 2020". Philstar. Archived from the original on June 6, 2020. Retrieved February 4, 2020.
  126. ^ "LRT-2 aims to resume full operations by January 2021". cnn. Archived from the original on January 4, 2021. Retrieved December 20, 2020.
  127. ^ Grecia, Leandre (October 8, 2020). "LRT-2 operations suspended after fire breaks out at Santolan station". Top Gear Philippines. Retrieved April 7, 2021.
  128. ^ Dela Cruz, Raymond Carl (October 8, 2020). "LRT-2 back to normal ops hours after Santolan Station fire". Philippine News Agency. Retrieved April 7, 2021.
  129. ^ Ong, Ghio (September 18, 2021). "Tangled t-shirt stops LRT-2 train trips". The Philippine Star. Retrieved September 18, 2021.
  130. ^ Cordero, Ted (October 9, 2021). "LRT2 stops ops on Saturday morning due to entangled balloon". GMA News. Retrieved October 9, 2021.
  131. ^ Ong, Ghio. "LRT-2 limits trips as street dweller climbs post". Philstar.com. Retrieved August 20, 2024.
  132. ^ "LRT-2 on full line operation following catenary repair". GMA News Online. August 20, 2024. Retrieved August 20, 2024.
  133. ^ Rita, Joviland (September 11, 2024). "LRT2 in partial ops due to power supply problem". GMA Integrated News. Retrieved September 12, 2024.
  134. ^ Rita, Joviland (September 12, 2024). "Technical glitch stalls LRT2 operations anew". GMA Integrated News. Retrieved September 12, 2024.
[edit]