Golden Line (Delhi Metro)
It has been suggested that Brown Line (Delhi Metro) be merged into this article. (Discuss) Proposed since July 2024. |
Golden Line (Line 10) | |
---|---|
Overview | |
Status | Under construction |
Owner | Delhi Metro |
Locale | Delhi |
Termini | |
Stations | 16 Elevated: 4 Underground: 12 |
Service | |
Type | Rapid transit |
System | Delhi Metro |
Operator(s) | Delhi Metro Rail Corporation |
History | |
Planned opening | March 2026[1] |
Technical | |
Line length | 25.82 km (16.04 mi) |
Character | Underground and Elevated |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge |
Electrification | 25 kV 50 Hz AC overhead catenary |
The Golden Line (Line 10 & Line 11) is an under-construction rapid transit line of the Delhi Metro. It will connect southern Delhi directly with Indira Gandhi International Airport to relieve the increasing traffic, congestion and pollution on roads. It will start from Terminal 1-IGI Airport, which was previously planned from Delhi Aerocity, and end in Tughlakabad.[2] It will be 25.82 km (16.04 mi) long with 16 stations, out of which four will be elevated and 12 will be underground. Construction began on the line in June 2022, as part of the fourth phase of the Delhi Metro's development, and is expected to be completed by March 2026.[3][4][5][6]
History
[edit]The Golden Line, initially named as Silver Line, was conceptualized by the Delhi Metro Rail Corporation (DMRC) under the Phase IV of Delhi Metro's future expansion and development in July 2016. As per the plan, six new lines covering a length of about 104 km (65 mi) have been planned to be added to the metro network, out of which the Golden Line would cover southern Delhi at a length of 20.2 km (12.6 mi). The plans were finalized for implementation by the Government of Delhi in December 2018; this time the length of the Golden Line increased to 23.6 km (14.7 mi).[7] In March 2019, the plans were approved for construction by the Government of India. Thus, land acquisition for Phase IV and Golden Line began from April 2019, and was completed by three years. Construction was supposed to begin from 2021, but was delayed due to the restrictions imposed by the government due to the COVID-19 pandemic. Hence, construction was started by Afcons Infrastructure and Larsen & Toubro in June 2022.[3][4] It was expected to be completed by 2024/25, which has been extended to March 2026, as of January 2024.[1]
In November 2020, the DMRC changed the alignment of the Golden Line as per the instructions of the Archaeological Survey of India (ASI) to circumvent the Qutb Minar and the Mehrauli Archaeological Park, so to avoid any harm to these critical historical sites during construction and operation.[6] As per the initial plan, the line was proposed to be extended to Terminal 1 of Indira Gandhi International Airport, in order to provide commuters a faster and direct link to the airport's premises. The proposal was approved by the Government of Delhi after the DMRC created and showed a Detailed Project Report (DPR) in December 2023, thereby increasing the line's length to 25.82 km (16.04 mi).[8][9] The name of the line was changed from 'Silver Line' to 'Golden Line' in January 2024.[5][10]
Stations
[edit]The stations being built on the Golden Line are:[6][11]
Main Line
[edit]Golden Line | |||||||||
---|---|---|---|---|---|---|---|---|---|
# | Station Name | Phase | Opening | Interchange Connection | Station Layout | Platform Level Type | Depot Connection | Depot Layout | |
English | Hindi | ||||||||
1 | Terminal 1 - IGI Airport | आईजीआई एयरपोर्ट - टर्मिनल 1 | 4 | 2026[12] | Magenta Line | Underground | Island | None | |
2 | Delhi Aerocity | दिल्ली एरोसिटी | Airport Express | ||||||
3 | Mahipalpur | महिपालपुुर | None | Side | |||||
4 | Vasant Kunj | वसंत कुंज | Vasant Kunj Depot | At Grade | |||||
5 | Kishangarh | किशनगढ़ | None | ||||||
6 | Chhatarpur | छत्तरपुर | Yellow Line | ||||||
7 | Chhatarpur Mandir | छत्तरपुर मंदिर | None | Island | |||||
8 | IGNOU | इग्नू | |||||||
9 | Neb Sarai | नेब सराय | |||||||
10 | Saket G-Block | साकेत जी-ब्लॉक | Golden Line (Phase 4 - Proposed Branch) |
Elevated | Side | ||||
11 | Ambedkar Nagar | अम्बेडकर नगर | None | ||||||
12 | Khanpur | ख़ानपुर | |||||||
13 | Sangam Vihar - Tigri | संगम विहार - तिगड़ी | |||||||
14 | Anandmayee Marg | आनंदमयी मार्ग | Underground | Island | |||||
15 | Pul Pehladpur | पुल पहलादपुर | |||||||
16 | Tughlakabad Station | तुग़लक़ाबाद स्टेशन | Violet Line |
Branch Line
[edit]Golden Line Branch | |||||||||
---|---|---|---|---|---|---|---|---|---|
# | Station Name | Phase | Opening | Interchange Connection | Station Layout | Platform Level Type | Depot Connection | Depot Layout | |
English | Hindi | ||||||||
1 | Saket G-Block | साकेत जी-ब्लॉक | 4 | 2026 | Golden Line (Phase 4 - Under Construction) |
Elevated | Side | None | |
2 | Pushp Vihar | पुष्प विहार | 2029 | None | |||||
3 | Saket District Centre | साकेत जिला केंद्र | |||||||
4 | Pushpa Bhawan | पुष्पा भवन | |||||||
5 | Chirag Delhi | चिराग दिल्ली | Magenta Line | ||||||
6 | Greater Kailash-1 | ग्रेटर कैलाश-१ | None | ||||||
7 | Andrews Ganj | एंड्रयूज़ गंज | |||||||
8 | Lajpat Nagar | लाजपत नगर | Pink Line Violet Line |
Project timeline
[edit]- July 2016: The Phase IV plan consisting of six new lines, including the Golden Line (then Silver Line) was created by the Delhi Metro Rail Corporation (DMRC).[10]
- December 2018: The Phase IV and the Golden Line were approved by the Government of Delhi.[7]
- March 2019: Both the Phase IV and the Golden Line were approved by the Government of India.[10]
- April 2019: Land acquisition begins for the Golden Line.[10]
- November 2020: The alignment of the line was changed as per the advice of the Archaeological Survey of India (ASI) to avoid possible impacts to the Qutb Minar and the Mehrauli Archaeological Park.[6]
- June 2022: Construction on the line started by Afcons Infrastructure and Larsen & Toubro.[3][4]
- December 2023: The proposal to extend the line to Terminal 1 of Indira Gandhi International Airport was approved by the Government of Delhi.[8][2]
- January 2024: The name of the line was changed to 'Golden Line' from 'Silver Line' by the DMRC. It is expected to be completed by March 2026.[5][1]
Train Info
[edit]Golden Line | |
---|---|
Rakes | Alstom Metropolis |
Train Length | 6 coaches |
Train Gauge | 4 ft 8+1⁄2 in (1,435 mm) standard gauge |
Electrification | 25 kV 50 Hz AC through overhead catenary (OHE) |
Train's Maximum Speed | 100 km/h |
Train Operation | Delhi Metro |
See also
[edit]- List of Delhi Metro stations
- Transport in Delhi
- Delhi Metro Rail Corporation
- Delhi Suburban Railway
- Delhi Transport Corporation
- National Capital Region (India)
References
[edit]- ^ a b c "Silver to Gold — Why Delhi Metro changed the colour code of this much awaited line". The Indian Express. 29 January 2024. Retrieved 29 January 2024.
- ^ a b "Delhi's Airport Metro set for silver line extension to terminal 1". Construction World. 12 January 2024. Retrieved 14 January 2024.
- ^ a b c "Delhi: Covid, green concerns put Phase-IV in low gear; push targets back". The Times of India. 14 June 2022. Retrieved 16 June 2022.
- ^ a b c "Afcons Begins Work on Delhi Metro Silver Line's Underground Section". The Metro Rail Guy. 15 June 2022. Retrieved 29 January 2024.
- ^ a b c "DMRC changes colour code of upcoming Delhi Aerocity–Tughlakabad Metro corridor". The Statesman. 29 January 2024. Retrieved 29 January 2024.
- ^ a b c d "Delhi Metro steers clear of Qutub Minar". The Times of India. 2 December 2020. ISSN 0971-8257. Retrieved 20 December 2023.
- ^ a b "Delhi Metro's Much-awaited Phase 4 Gets AAP Govt's Nod, Likely to be Ready by 2024". News18. 20 December 2018. Retrieved 29 January 2024.
- ^ a b "Delhi Metro's Silver Line to Aerocity may be extended to terminal 1". The Times of India. 19 December 2023. ISSN 0971-8257. Retrieved 19 December 2023.
- ^ "Good News For Air Travellers! Delhi Metro's Silver Line To Aerocity To Be Extended To Terminal 1". Times Now. 19 December 2023. Retrieved 19 December 2023.
- ^ a b c d "Delhi Metro Phase 4 – Information, Route Maps, Tenders & Updates". The Metro Rail Guy. Retrieved 29 January 2024.
- ^ "Delhi Metro map". www.delhimetrorail.com. Retrieved 21 April 2022.
- ^ "First section of Delhi Metro phase-IV to open by July 2024, says DMRC chief". TimesNow. 5 November 2023. Retrieved 24 November 2023.