Middelgrunden offshore wind park, 3.5 km outside Copenhagen. When built in 2000, it was the world's largest.[1]

Denmark was a pioneer in developing commercial wind power during the 1970s, and today a substantial share of the wind turbines around the world are produced by Danish manufacturers such as Vestas—the world's largest wind-turbine manufacturer—along with many component suppliers. Furthermore, Denmark has—as of 2022—the 2nd highest amount in the world of wind power generation capacity installed per capita, behind only neighboring Sweden.

In 2020, wind power produced 56% of total electricity generation in Denmark, up from 20% in 2010 and 11% in 2000.[2][3][4][5][6][7][8] This contributes to the government's target of 100% renewable power generation by 2030.[9][10]

Denmark had the 4th best energy architecture performance in the world in 2017 according to the World Economic Forum,[11] and the second best energy security in the world in 2019 according to the World Energy Council.[12]

History

[edit]
Wind turbines in Vendsyssel, 2004

Danish inventor Poul la Cour experimented, taught and constructed wind power projects around the year 1900.[13][14]

As concerns over global warming grew in the 1980s, Denmark found itself with relatively high carbon dioxide emissions per capita, primarily due to the coal-fired electrical power plants that had become the norm after the 1973 and 1979 energy crises.[15] Renewable energy became the natural choice for Denmark, decreasing both dependence on other countries for energy and global warming pollution.

Many countries tried to subsidise green technology such as wind power, and most failed to make it a viable industry. The Danish system was an exception, providing 30% of initial capital cost in the early years which was gradually reduced to zero, but still maintaining a feed-in tariff.[16] The capital cost subsidy was reduced to 20% in June 1985, when wind turbines received DKK 50 million per year. Other renewable energy forms received 37 million.[17] The research institution Teknologisk Institut identified many specific improvement needs, pushing development from ad hoc to systemised solutions.[18]

On 29 March 1985, one year before the Chernobyl disaster, the Danes passed a law forbidding the construction of nuclear power plants. In the process, the Danish grassroots movement had a substantial role. The Danish Anti-nuclear Movement's (OOA) smiling-sun logo "Atomkraft, Nej Tak" ("Nuclear Power, No Thanks") spread worldwide, and the renewable alternatives were promoted by the Danish Organisation for Renewable Energy (OVE).

Denmark adopted a target of cutting carbon emissions by 22% from 1988 levels by 2005.[15] Planning of wind power was deliberately streamlined by authorities to minimise hurdles.[19]

Policy measures

[edit]

In June 2005, the Danish government published Energy Strategy 2025, which replaced the previous strategy from 1996. The strategy formulates policy projects that are intended to accelerate the expansion of wind power and restructure the electricity market. [20] [21]

The Danish government also succeeded in drawing up energy agreements from 2008 to 2011 with broad-based support, which included the most far-reaching and effective programs for the expansion of wind energy to date.[22] The parties agreed that the share of renewable energies in Danish energy consumption should be 20 % in 2011. The price for wind energy was also increased in the agreement. The parties also agreed to construct new offshore wind turbines with a capacity of 400 MW by 2012. The agreement introduced a compensation scheme for residents living near wind turbines, a scheme for purchase rights and a guarantee fund.[23] [21]

After the government expressed the long-term vision of a Denmark 100% independent of reliance on fossil fuels[24] during the current agreement, in independent commission on climate change policy proposed detailed recommendations in September 2010 on how this vision can be achieved. This led to Energy Strategy 2050 a year later. The strategy consists of three tracks, as one of them focusses on more renewable energy with onshore and offshore wind power. It included tenders for over 1000 MW in offshore including Kriegers Flak in the Baltic Sea. Kriegers Flak is also used to connect Denmark and Germany with a 400MW cable, through the German Baltic 2 Offshore Wind Farm,[25] and it is the wind farm with the lowest guaranteed price (øre/kWh) for large offshore wind farms in Denmark.[26] In addition, the distance requirements for wind turbines were evaluated and revised. Such subsidies as compensation schemes for residents living near onshore windmills lost relevance and the offshore area was taken into focus.[27][21]

Ever since the first energy agreement with outstanding consensus in parliament in 2008, Denmark grew their wind power share in domestic electricity production from 19% to 55% in 2019.[28]

For the policy approach, one may note the adoption of incrementalism that helps this to be developed ahead of other more rational approaches such as those adopted by USA and UK. See the use of Wind Power development in the example section of Incrementalism.

Wind resources

[edit]
External images
image icon Wind map of Denmark Archive
image icon Today's wind power production
image icon Tomorrow's wind power prognosis, by Nord Pool Spot.
image icon Current power system data, provided by Energinet.dk
image icon Current power system data, provided by EMD
image icon Last 2 weeks of power system data

Denmark has relatively modest average wind speeds in the range of 4.9–5.6 m/s measured at 10 m height. Onshore wind resources are highest in the western part of the country, and on the eastern islands with coastlines facing south or west. Wind is higher in autumn and winter and lower in summer, and Denmark also has about 2.3 GW of solar power.[29][30] The country has very large offshore wind resources, and large areas of sea territory with a shallow water depth of 5–15 m, where siting is most feasible. These sites offer higher wind speeds, in the range of roughly 8.5–9.0 m/s at 50 m height.[31] There have been no major problems from wind variability, although there is a temporary problem resulting from the connection of a large bloc of wind power from offshore wind farms to a single point on a weak section of the transmission network.[32] The wind resource over Denmark was mapped in 1999 by EMD International A/S and Risø National Laboratory. The mapping was made using a 200 m grid resolution using the models in WindPRO and WAsP. The results were validated on more than 1200 wind turbines nationwide.[33]

Denmark is connected by transmission line to other European countries (e.g. Cross-Skagerrak)[34] at an electricity interconnection level (transmission capacity relative to production capacity) of 44% in 2015,[35] and increased since then. Denmark has also retained 6 GW of its traditional power plants,[30] therefore it does not need to install additional peak-load plants to balance its wind power. Instead, it purchases additional power from its neighbours when necessary. With some strengthening of the grid, Denmark plans to increase wind's share even further.[36] In 2010 the plan was to reach 50% of consumption in 2020[37] (which was almost met), and up to 84% in 2035.[38]

Analysts expect the cost of wind power to be 30 øre/kWh and its handling cost to be 15 øre/kWh, being lower than coal and natural gas at 55 øre/kWh minimum.[39] Due to their inability to follow load wind power gets a lower price.[40]

[edit]

Danish district heating plants use 100 petajoule/year,[41] but little of this consumption is from 180 MW of electrode boilers installed in powerplants or 374 MW of large heat pumps.[42] The boilers are only used to soak up the powerplant's own electricity when prices are negative, to avoid paying tax.[43][44][45][46] Expansion of wind powered district heating is calculated to be economically efficient without taxes.[47][48][49]

The number of household heat pumps has stalled at 70,000 in 2015 due to tax-free wood pellets, and the goal of 300,000 small heat pumps in 2035 is unlikely to be reached, reducing the value of more wind power unless electricity tax is reduced.[50]

Nameplate capacities and production

[edit]
Wind power in Denmark

At the end of 2015, Denmark's total nameplate capacity for wind power stood at 5,070 MW.

Denmark has the highest proportion of wind power in the world. In 2015, Denmark produced 42% of electricity from wind,[51][5] up from the 2014 record of 39% of total power consumption. For the month of January 2014, that share was over 61%. The month of lowest wind power share was July at 23%.[6] Denmark also had 548 MW of solar power[52] (790 MW in late 2015).[53] A peak generation period occurred on 21 December 2013 when the wind share was 102%, and for 1 hour the share was 135%.[8]

In 2005, Denmark had installed wind capacity of 3,127 MW, which produced 23,810 TJ (6.6 TW·h) of energy, giving an actual average production of 755 MW at a capacity factor of 24%.[54] In 2009, Denmark's wind capacity grew to 3,482 MW; most of the increase came from the 209 MW Horns Rev 2 offshore wind farm, which was inaugurated on 17 September 2009 by Crown Prince Frederik.[55] In 2010, capacity grew to 3,752 MW, and most of the year's increase came from the Rødsand II off-shore wind farm.

On 22 March 2012, a coalition of parties representing 95% of all members of the Danish parliament agreed that the Danish state would increase the country's offshore wind capacity by 1,500 MW.[56][57] The 1,500 MW extra capacity was achieved by constructing several offshore wind farms; the 400 MW Anholt wind farm in 2014,[6] the 407 MW Horns Rev 3 in the North Sea[57] at 77 øre/kWh[58] in 2019,[59][60] and the Kriegers Flak at 37.2 øre/kWh[61] with a capacity of 600 MW in the Baltic Sea close to the borders of Germany and Sweden in 2021.[57] Kriegers Flak is also used to connect Denmark and Germany with a 400MW cable, through the German Baltic 2 Offshore Wind Farm,[25] and Energinet ordered electrical equipment in early 2016.[62][63] Eight groups applied for pre-qualification for Kriegers Flak,[64] of which 7 were approved[65] – 3 more than the 4 companies approved to compete for Horns Rev 3,[66] both having more bidders than the single bidder for Anholt. By 2018, Danish offshore wind farms had average 40% capacity factor. Newer farms had higher CF than older.[67]

Offshore operators are required to secure a decommissioning fee.[68]

Wind power output reduces spot market prices in general via the Merit Order effect; in 2008 this caused a net reduction of pre-tax electricity prices (balancing the increase from the feed-in law).[69]

Statistics

[edit]
Wind power net electricity generation (GWh) 2007–2019
5,000
10,000
15,000
20,000
2007
2009
2011
2013
2015
2017
2019
Wind power net electricity generation 2007–2014[70][71]
External image
image icon Grid stability and wind share
Installed wind capacity, production, share in Denmark by year[72]
Year 1970 1971 1972 1973 1974 1975 1976 1977 1978 1979
Installed wind capacity (kW)[72] 52 813 1,090
Electricity generated (MW·h)[72] 120 240
Average capacity factor (%) 1.7 2.5
Year 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989
Installed wind capacity (MW)[72] 2.7 6.3 10.6 14.3 19.8 47.0 72.4 111.9 190.3 246.7
Electricity generated (GW·h)[72] 2 5 12 19 26 44 104 154 266 398
Average capacity factor (%) 8.5 9.1 12.9 15.2 15.0 10.7 16.4 15.7 16.0 18.4
Year 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999
Installed wind capacity (MW)[72] 326 393 436 468 521 600 814 1,123 1,438 1,753
Electricity generated (TW·h)[72] 0.57 0.68 0.83 0.92 1.06 1.09 1.19 1.89 2.76 3.00
Average capacity factor (%) 20.0 19.8 21.7 22.4 23.2 20.7 16.7 19.2 21.9 19.5
Year 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
Installed wind capacity (MW)[72] 2,390 2,497 2,890 3,116 3,123 3,127 3,135 3,124 3,163 3,482
Electricity generated (TW·h)[72] 4.22 4.31 4.86 5.56 6.58 6.61 6.11 7.14 6.98 6.72
Average capacity factor (%) 20.2 19.7 19.2 20.4 24.1 24.1 22.2 26.1 25.2 22.0
Wind power share in the electricity supply (%)[73] 12.1 12.2 13.9 15.8 18.5 18.5 16.8 19.7 19.1 19.3
Year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Installed wind capacity (MW)[8][72][74] 3,752 3,927 4,162 4,792 4,855 5,070 5,229 5,475 6,131 6,128
Electricity generated (TW·h)[70] 7.81 9.77 10.27 11.12 13.08 14.13 12.78 14.78 13.90 16.15
Average capacity factor (%) 23.8 28.4 28.2 26.5 30.8 31.8 27.9 30.8 25.9 30.1
Wind power share in domestic electricity production (%)[70] 20.2 28.0 33.7 32.2 41.0 49.2 42.5 48.6 46.1 55.2

The chart shows the minimum (guaranteed) price a plant receives during the FLH period in øre/kWh. Subsidy = guaranteed price minus market price. FLH=Full Load Hours; the amount of production the plant receives support for. After that, the plant usually receives market price. Transmission is included in the nearshore "Vesterhav", but not the other plants. The levels are usually below levels in Germany and UK.[75][76][77][78][61][79]

Peak records

[edit]
Breaking waves at the north sea coast of Denmark in the evening of 9 July 2015 as the new record in peak generation was reached.

As Denmark continues to install additional capacity, they continue to set new production records. This is a natural consequence of capacity growth. On 9 July 2015, in the evening, unusually strong wind conditions resulted in 116% of national electricity consumption being produced by wind farms and at 3 am the next morning at low demand, wind production exceeded 140% of current demand.[5][80][needs update][81]

Future parks in Denmark

[edit]

Offshore

[edit]

The 1,000 MW Thor offshore wind (a $2.5 billion project scheduled for 2027 in the North Sea) was agreed in December 2021. 5 of 6 bidders bid the same price of 0.01 øre/kWh, and drew lots to find the winner (RWE) for a Contract for difference,[79] which included connection costs and a potential DKK 2.8 billion (€377m) payment to the state.[82][83] The similar bids raised questions about the suitability of the auction.[84] Three days after the auction, the Parliament agreed on a further 2 GW offshore wind by 2031 due to the success of the Thor auction.[85]

In early June 2023, an agreement was made by Germany and Denmark to link the Danish island of Bornholm's wind energy producing capacity to the mainland by the early 2030s, with a minimum capacity of 3 gigawatts.[86]

Nearshore

[edit]
External image
image icon Visualization of North Sea nearshore turbines, near Hvide Sande

In addition 6 nearshore wind farms with a total capacity of up to 450 MW are scheduled along with 50 MW of experimental offshore wind farms. The nearshore differ from conventional offshore in having the being close enough to the coast to have the transformer on land, decreasing cost.[57] The first 350 MW were called for tenders in 2015, with a maximum price of 70 øre/kWh.[87][88][89] Vattenfall bid the lowest price for the 350 MW nearshore farms at 47,5 øre/kWh in September 2016,[90] but the political situation was unclear.[91]

Onshore

[edit]

In addition to the offshore projects, a further 500 MW additional net capacity of onshore windfarms is expected to be constructed until 2020. The 500 MW of additional net capacity is the expected result of the scrapping of 1,300 MW capacity from obsolete wind turbines combined with the simultaneous building of 1,800 MW capacity of modern wind turbines – a process also known as repowering.[92]

Electricity exports from Denmark

[edit]

In 2020, Denmark produced 16.3 TWh of wind power, of which 15 TWh (91.8%) were consumed in Denmark, measured hourly. A further 0.8 TWh of wind power were imported.[93]

In 2017, annual wind power production corresponded to about 43% of electricity consumed in Denmark.[94] The proportion of this that is actually consumed in Denmark has been disputed, as the larger hydropower resources of Norway (and to some extent, Sweden) is used as grid storage with low loss. Hydropower can rapidly reduce generation whenever wind farms are generating power, saving water for later, and can export electricity to Denmark when wind power output drops. Short term, Denmark imports electricity from Norway during daytime and exports in nighttime. Long term, Denmark imports electricity in summer and exports in winter. Wind is higher in autumn and winter, when consumption is also high.[95] This service of timeshifting production and consumption is also found around the world in pumped-storage hydroelectricity balancing coal and nuclear plants.

For timeshifting trade with Norway, Denmark exports at DKK 157/MWh and imports at DKK 212/MWh.[49] The correlation is low between wind power in Norway and Denmark.[95] Market price sometimes falls to near or below zero, particularly in high winds and low consumption.[96] In 2014, there were 46 hours with negative prices, costing DKK 37.7 million.[97] In 2015, negative prices occurred in 65 hours in West Denmark and 36 hours in East Denmark – less than 1% of the time. Danish prices are mainly negative when German prices are even more negative;[98] 90% of curtailment happens as a request from German power producers, and represents 2% (or DKK 80 million in 2018) of wind power production.[99] In most years, curtailment mainly happened at thermal power plants, but became mostly by wind turbines in 2020.[100] In 2019, Germany paid for curtailment of 420 GWh of Danish wind power, and the number increased to 1,463 GWh in 2020 (plus 1,066 GWh for thermal power), earning DKK 522 million.[101]

The 24-hour period of 2 September 2015 was the first occasion when most electricity came from wind, and no central power plants were running in West Denmark, while grid stability was maintained by compensators.[5][102]

Denmark is generally a transit country for electricity trade between the much larger markets in Norway, Sweden, Germany and Netherlands (COBRAcable),[102][103] and plans to add cables to England (Viking Link) as well, further increasing the function of being a crossroads for electricity.

From 2005 to 2010, claims of up to 40% of wind power being exported have been made[who?],[104][105] countered by claims that only 1% was exported.[106]

According to the first argument, power in excess of immediate demand is exported to neighbouring countries at lower prices. Part of the benefit of this goes to Denmark's northern neighbours: when Denmark exports power, it is sold at the spot market price which must be lower than at the importing market to be transmitted.

According to the second argument, the correlation between exports and wind power is weak, and a similar correlation exists with conventional thermal plants running partly for district heating; meanwhile, causal analysis shows that export from Denmark typically occurs as a consequence of the merit order effect, when large thermal plants have reserve capacities at times the spot market price of electricity is high.

In any case, the export price is the intermediate between the prices of the two areas, so the exporting TSO (Energinet) uses the profit to relieve tariffs[107] at around DKK 500 million per year.[108] Wind power organisations state that Denmark exports power at a higher price than it imports at.[109]

Economic conditions

[edit]

Wind turbine industry

[edit]
A Vestas wind turbine

The Danish wind turbine industry is the world's largest.[citation needed] Around 90% of the national output is exported, and Danish companies accounted for 38% of the world turbine market in 2003, when the industry employed some 20,000 people and had a turnover of around 3 billion euro.[110] The return on investment dropped from near 20% before the financial crisis, to 10% some years later.[111][112] The Danish wind turbine industry had a turnover of DKK 84 billion in 2014.[113]

The biggest wind turbine manufacturers with production facilities in Denmark are Vestas and Siemens Wind Power.[citation needed]

The development of wind power in Denmark has been characterised by a close collaboration between publicly financed research and industry in key areas such as research and development, certification, testing, and the preparation of standards.[114] For example, in the 1980s, a large number of small Danish companies were developing wind turbines to sell to California, and the Danish Risø laboratory provided test facilities and certification procedures. These resulted in reliable products and the rapid expansion of the Danish turbine manufacturing industry.[115] Components are tested at LORC in Odense, and new large prototype turbines between 4–8 MW (including some non-Danish ones) are being tested at Østerild. Limited production turbines (four Siemens 7MW with 66kV cabling) are to be supported at Nissum Bredning at a cost of DKK 300m, partially financed by local people.[116][117][118]

Danish wind economics

[edit]
External images
image icon EU industry electricity prices
image icon EU household electricity prices

How price of consumer electricity is composed[119]

  Cost (32%)
  PSO (9%)
  Tolls and VAT (59%)

Denmark's electricity costs (including PSO; costs for cleaner energy) are average in the EU,[120][121][122] but taxes increase the price to the highest in Europe.[123] The tax money is a considerable income for the state, and changing the composition of the taxes towards a "greener" mix is difficult. According to a government official, the majority of taxes are not based on environment concerns,[124] in contrast to the DKK 5 billion per year in PSO-money for cleaner energy, paid by electricity consumers to producers of clean electricity. These tolls are not available for government consumption.[125]

Actual consumer-paid incentives (PSO) to new wind turbines depend on year of commission, but is generally around 25 øre (3.4 eurocent) per kWh for a limited number of hours, although support is discounted if combined price exceeds 58 øre/kWh. PSO is also used for biomass, solar, and district heating; total PSO was DKK 5.8 billion in 2013, of which DKK 3.2 billion went to wind power.[125] In 2015, the cost of power was only 32% of the price, while PSO was 9%, and tolls and VAT the remaining 59%.[119] In 2021, the Thor offshore contract was the first time a developer had to pay connection costs in Denmark, and also pay the state.[82]

Wind power displaces coal, oil and gas to some degree, reducing running cost for fossil fuels. Consumption of coal was more than halved from 1990 to 2020.[126][30] Wind power reduces price variability slightly.[127]

Criticism

In 2009, the think tank Institute for Energy Research (IER) commissioned the Danish think-tank CEPOS (Centre for Political Studies) to report on electricity exports from Denmark and the economic impact of the Danish wind industry. The resulting report states that Danes pay the highest residential electricity rates in the European Union (mostly for government revenue, but partly to subsidise wind power), and that the cost of saving a ton of carbon dioxide between 2001 and 2008 has averaged 647 DKK (€87, US$124). It also estimated that 90% of wind industry jobs were transferred from other technology industries, and states that as a result Danish GDP is 1.8 billion DKK (US$270 million) lower than it would have been without wind industry subsidies of 1.7–2.6 billion DKK (roughly $320M – $480M) yearly in 2001–2005.[128] The report was later heavily criticised.[129] The Danish engineering magazine Ingeniøren claimed that the report was ordered and paid for by the American oil and coal lobby through IER.[130] Later, several Danish researchers and professors from all technical universities in Denmark wrote a joint response to the report, refuting it.[131][132] The report from CEPOS was even brought to government level, where minister of Climate and Energy Lykke Friis discredited the work done by CEPOS and the report.[133] The World Nuclear Association estimates that the report was IER's response to US president Obama's 2009 Earth Day speech in Newton, Iowa, claiming that the United States could generate 20% of its electricity from wind by 2030, as Denmark already was.[134][135]

Wind turbine cooperatives

[edit]

To encourage investment in wind power, families were offered a tax exemption for generating their own electricity within their own or an adjoining municipality.[136] While this could involve purchasing a turbine outright, more often families purchased shares in wind turbine cooperatives which in turn invested in community wind turbines. By 1996 there were around 2,100 such cooperatives in the country.[136] Opinion polls show that this direct involvement has helped the popularity of wind turbines, with some 86% of Danes supporting wind energy when compared with existing fuel sources.[110]

The role of wind turbine cooperatives is not limited to single turbines. The Middelgrunden offshore wind farm – with 20 turbines the world's largest offshore farm at the time it was built in 2000 – is 50% owned by the 10,000 investors in the Middelgrunden Wind Turbine Cooperative, and 50% by the municipal utility company,[137] as is the Avedøre near-shore turbines.

By 2001 over 100,000 families belonged to wind turbine cooperatives, which had installed 86% of all the wind turbines in Denmark.[138] By 2004 over 150,000 were either members or owned turbines, and about 5,500 turbines had been installed, although with greater private sector involvement the proportion owned by cooperatives had fallen to 75%.[110] The cooperative model has also spread to Germany and the Netherlands.

Samsø Island

[edit]

The island of Samsø erected 11 one-megawatt, land-based wind turbines in 2000, followed by ten offshore 2.3 MW wind turbines completed in 2003. Together with other renewable energy measures, this community of 4,200 achieved fame,[139] claiming that it is the largest carbon neutral settlement on the planet.[140] This claim exploits the general understanding that one can neglect carbon-dioxide and other pollution from fossil fuel consumption (cars, imported electricity, heating for houses, etc.), If the yearly average electricity production from sustained sources is higher than the total energy consumed.[citation needed] However, the government of Samsø is addressing the fossil fuel consumption issue in motoring – they've decided that all traffic on Samsø is to go electric.

See also

[edit]

References

[edit]
  1. ^ "Environmental Capital of Europe". Copenhagen, Environmental Capital of Europe. Archived from the original on 6 July 2007. Retrieved 5 January 2009.
  2. ^ "Share of electricity production from wind - Denmark". Our World in Data. 2023. Retrieved 15 July 2023.
  3. ^ "Denmark sources record 47% of power from wind in 2019". Reuters. 2 January 2020. Retrieved 14 January 2020.
  4. ^ "Denmark on track to have 50% renewable energy by 2030". Raidió Teilifís Éireann. 11 January 2018.
  5. ^ a b c d "New record-breaking year for Danish wind power". Energinet.dk. 15 January 2016. Archived from the original on 25 January 2016.
  6. ^ a b c Rasmussen, Jesper Nørskov. "Vindmøller slog rekord i 2014 Archived 2015-01-06 at the Wayback Machine" (in Danish) Energinet.dk, 6 January 2015. Retrieved 6 January 2015.
  7. ^ Kjetil Malkenes Hovland (3 September 2014). "Denmark's Wind Power Output Rises to Record in First Half". The Wall Street Journal.
  8. ^ a b c Carsten Vittrup. "2013 was a record-setting year for Danish wind power Archived 2014-10-18 at the Wayback Machine" (in Danish) Energinet.dk, 15 January 2014. Retrieved 20 January 2014.
  9. ^ Rosie Frost (17 October 2022). "These EU countries are aiming for 100 per cent clean power by 2030". Euronews. Retrieved 15 July 2023.
  10. ^ "Denmark". Climatescope. 2023. Retrieved 15 July 2023.
  11. ^ "Global Energy Architecture Performance Index Report 2017 – Table of Rankings". World Economic Forum. 22 March 2017. Retrieved 14 January 2020.
  12. ^ "World Energy Trilemma Index 2019" (PDF). World Energy Council. Retrieved 15 January 2020.
  13. ^ Lyngsø-Petersen, Erik. "Poul la Cour og hans tid" Ingeniøren, 6 September 1985
  14. ^ Hansen, Hans Christian (1985): "Poul la Cour, grundtvigianer, opfinder og folkeoplyser." Doctoral thesis in Danish with an English summary. Extract Archived 13 September 2016 at the Wayback Machine
  15. ^ a b Soren Krohn (22 February 2002). "Wind Energy Policy in Denmark: Status 2002" (PDF). Danish Wind Industry Association. Archived from the original (PDF) on 27 September 2007. Retrieved 8 September 2007.
  16. ^ Sørensen, Bent. Renewable energy: its physics, engineering, use, environmental impacts, economy, and planning aspects page 762. Academic Press, 2004. ISBN 0-12-656153-2, ISBN 978-0-12-656153-1 Retrieved: 6 November 2010.
  17. ^ Møller løber med støtten, Ingeniøren, 6 September 1985
  18. ^ Opfind noget til en vindmølle, Ingeniøren, 6 September 1985
  19. ^ Streamline Renewable Energy Policy and make Australia a World Leader Energy Matters, 11 August 2010. Retrieved 6 November 2010.
  20. ^ "Energy Strategy 2025" (PDF). The Danish Ministry of Transport and Energy. 2005. Retrieved 23 December 2023.
  21. ^ a b c "Energy Policies of IEA Countries: Denmark 2011". International Energy AgencyEnergistyrelsen. 2012. Retrieved 2 November 2023.
  22. ^ Arnold, David (2021). Windkraft in Dänemark: Eine Governance-Erfolgsgeschichte mit Nachahmungspotential? , p. 83 et seqq.
  23. ^ "Renewable Energy Act" (PDF). Danish Energy Agency. 2008. Retrieved 15 November 2023.
  24. ^ "Denmark: 100% renewable energy supply". Nordic Energy Research. 2015. Retrieved 1 January 2024.
  25. ^ a b "Verdens første offshore elnet bliver en realitet i Østersøen". Ingeniøren. 25 September 2015.
  26. ^ "Vattenfall wins Kriegers Flak with record €49.90/MWh". 9 November 2016. Retrieved 30 December 2023.
  27. ^ "The Danish Energy Model: Energy Strategy 2050" (PDF). Energistyrelsen. 2011. Retrieved 12 November 2023.
  28. ^ "Annual and monthly statistics". ens.dk. Danish Energy Agency. 1 May 2020. Retrieved 1 January 2024.
  29. ^ Hildebrandt, Sybille (20 September 2022). "Nettilslutning af solceller er steget med 20 procent | GridTech (PRO)". pro.ing.dk (in Danish). Ingeniøren.
  30. ^ a b c "MILJØRAPPORT 2020" (PDF). Energinet.dk. 2020.
  31. ^ Case Study: Wind energy in Denmark Archived 25 July 2008 at the Wayback Machine. Managenergy.net. Retrieved 11 June 2011.
  32. ^ Diesendorf, Mark (2007). Greenhouse Solutions with Sustainable Energy, UNSW Press, p. 121.
  33. ^ Danish Wind Resource Map (1999). Available online at www.emd.dk/windres Archived 19 July 2011 at the Wayback Machine. Emd.dk. Retrieved 11 June 2011.
  34. ^ Gellert, Bjarne Christian. Electricity interconnections Archived 9 February 2013 at the Wayback Machine Energinet.dk, 22 August 2011. Retrieved 6 December 2011.
  35. ^ "Achieving the 10% electricity interconnection target Archived 2015-12-25 at the Wayback Machine" page 2-5. European Commission, 25 February 2015. Note: Slovakia has 61% and Hungary has 29%
  36. ^ Diesendorf, Mark (2007). Greenhouse solutions with sustainable energy, UNSW Press, pp. 121–22.
  37. ^ Lund 2010, p. 21 "Denmark has a strategy to raise this share to 50 percent and the necessary measures are in the process of being implemented".
  38. ^ Lindboe, page 3
  39. ^ Lindboe, page 6
  40. ^ Lindboe, page 14
  41. ^ Lindboe, page 29
  42. ^ Bernth, Martin (20 December 2020). "Fjernvarmens varmepumpe-kapacitet er næsten firdoblet i år". Ingeniøren (in Danish). Archived from the original on 21 December 2020.
  43. ^ Wittrup, Sanne. "Dong: Vores kraftværker bruger allerede billig vindmøllestrøm i elpatroner" Ingeniøren, 15 January 2015. Retrieved January 2015.
  44. ^ Blarke, Morten Boje. "Liste over el-drevne varmepumper i fjernvarmen Archived 2016-01-19 at the Wayback Machine" SmartVarme.dk, 12 February 2014. Retrieved January 2015.
  45. ^ Capion, Karsten. "Analyse nr. 9 – Mulighederne for den fremtidige fjernvarmeproduktion i decentrale områder Archived 2015-12-08 at the Wayback Machine" Danish Energy, 15 January 2014. Retrieved 15 January 2015.
  46. ^ "Dansk Energi – Stor interesse for reduceret pulje til grøn fjernvarme". Archived from the original on 31 January 2016. Retrieved 29 October 2015.
  47. ^ Lindboe, page 7
  48. ^ Blarke, Morten Boje. "Store eldrevne varmepumper[permanent dead link]" Aalborg University, 17 April 2013. Retrieved January 2015.
  49. ^ a b Wittrup, Sanne. "Varmepumper kunne have øget værdien af vindstrøm med 1,75 mia. på fem måneder" Ingeniøren, 8 June 2015. Retrieved 29 October 2015.
  50. ^ Sanne Wittrup (25 March 2016). "Sløvt varmepumpemarked truer elektrificering af varmeforsyningen". Ingeniøren. Retrieved 26 March 2016.
  51. ^ "Denmark breaks its own world record in wind energy". EurActiv – EU News & policy debates, across languages. 15 January 2016.
  52. ^ "Global Market Outlook for Photovoltaics 2014–2018" (PDF). epia.org. EPIA – European Photovoltaic Industry Association. p. 34. Archived from the original (PDF) on 25 June 2014. Retrieved 12 June 2014.
  53. ^ "Kæmpe solcelleparker slår bunden ud af energiforlig". 5 February 2016.
  54. ^ "Danish Annual Energy Statistics 2008" (PDF). Retrieved 31 July 2010.[permanent dead link]
  55. ^ Matthew McDermott. "Denmark Inaugurates World's Largest Offshore Wind Farm – 209 MW" Treehugger.
  56. ^ "Så er energiforliget på plads" (in Danish). Ingeniøren. 22 March 2012. Retrieved 17 April 2014.
  57. ^ a b c d Therese Kofoed Jensen, Adviser, Danish Energy Agency (14 March 2014). "Offshore investments in Denmark" (PDF). Danish Energy Agency. Archived from the original (PDF) on 18 April 2014. Retrieved 17 April 2014.{{cite web}}: CS1 maint: multiple names: authors list (link)
  58. ^ Wittrup, Sanne. "Svenske Vattenfall skal bygge Danmarks næste havmøllepark Archived 2015-02-26 at the Wayback Machine" Ingeniøren, 26 February 2015. Retrieved 26 February 2015.
  59. ^ "Horns Rev 3 havmøller" (in Danish). Energinet.dk. 7 April 2014. Archived from the original on 18 April 2014. Retrieved 17 April 2014.
  60. ^ "Horns Rev 3" (in Danish). Vattenfall. Retrieved 25 August 2019.
  61. ^ a b c Steel, William (9 November 2016). "Vattenfall wins Kriegers Flak with record €49.90/MWh". Recharge. Archived from the original on 10 November 2016. Retrieved 10 November 2016.
  62. ^ "Energinet.dk køber komponenter til Kriegers Flak Havmøllepark". Energinet.dk. Archived from the original on 30 January 2016. Retrieved 20 January 2016.
  63. ^ "Core component ordered for new German-Danish interconnector". Energinet.dk. Archived from the original on 11 March 2016. Retrieved 10 March 2016.
  64. ^ Wittrup, Sanne. "Otte selskaber vil bygge mega-havmøllepark i Østersøen " Ingeniøren, 1 October 2015. Retrieved 2 October 2015.
  65. ^ Wittrup, Sanne. "Danmark tiltrækker masser af nye konsortier til kæmpe havmøllepark " Ingeniøren, 28 October 2015. Retrieved 28 October 2015.
  66. ^ Wittrup, Sanne. "Horns Rev 3 er en godbid" Ingeniøren, 16 February 2015. Retrieved 12 March 2015.
  67. ^ "Capacity factors at Danish offshore wind farms – Energy Numbers". energynumbers.info. 1 March 2019. Archived from the original on 20 January 2022.
  68. ^ Wittrup, Sanne (20 February 2016). "Aldrende havmølleparker åbner marked for klog nedrivning". Ingeniøren (in Danish). Archived from the original on 31 October 2021.
  69. ^ Lund 2010, p. 6 "The cost of wind power is paid solely by the electricity consumers and the net influence on consumer prices was as low as 1–3 percent on average in the period 2004–2008. In 2008, the net influence even decreased the average consumer price, although only slightly."
  70. ^ a b c "Annual and monthly statistics". ens.dk. Danish Energy Agency. 1 May 2020. Retrieved 28 July 2020.
  71. ^ "Energinet.dk / Previous environmental reports". Archived from the original on 29 June 2016. Retrieved 13 November 2016.
  72. ^ a b c d e f g h i j Spliid, Iben. Stamdataregister for vindmøller HTML-spreadsheet, column E Archived 10 June 2012 at the Wayback Machine Danish Energy Agency November 2014. Retrieved 6 January 2014.
  73. ^ Månedlig elforsyningsstatistik, HTML-spreadsheet Archived 3 March 2012 at the Wayback Machine summary tab B58-B72 Danish Energy Agency 18 January 2012. Retrieved 11 March 2012.
  74. ^ "Global Wind Power Statistics by 2019 – Wind Energy International Platform". library.wwindea.org. Retrieved 13 June 2020.
  75. ^ "Nearshore wind farms". Energinet.dk. 24 November 2014. Archived from the original on 17 May 2017. Retrieved 14 September 2016.
  76. ^ "Nearshore Wind Tender". Energistyrelsen. 17 June 2016. Retrieved 14 September 2016.
  77. ^ "Kriegers Flak". Energistyrelsen. 17 June 2016. Retrieved 14 September 2016.
  78. ^ "Prices adjusted for inflation, page 14" (PDF).
  79. ^ a b Bernth, Martin (1 December 2021). "Tysk energiselskab skal bygge Danmarks første støttefrie havvindmøllepark | GridTech PRO". pro.ing.dk (in Danish). Ingeniøren. Archived from the original on 1 December 2021.
  80. ^ Arthur Neslen (10 July 2015). "Wind power generates 140% of Denmark's electricity demand". The Guardian.
  81. ^ "Solar and wind records". ENERGI DATA PORTAL.
  82. ^ a b Franke, Andreas (1 December 2021). "RWE secures concession for 1 GW Thor wind farm off Danish coast". spglobal.com. Archived from the original on 4 December 2021.
  83. ^ Foxwell, David (1 December 2021). "RWE wins contract to build Thor, Denmark's largest offshore windfarm". Riviera. Archived from the original on 9 December 2021.
  84. ^ Richard, Craig (17 December 2021). "'We need new auction model after Thor offshore wind lottery' – Wind Denmark". windpowermonthly.com. Archived from the original on 18 December 2021.
  85. ^ "Partier er enige om at fordoble strøm fra havvind". Ritzau (in Danish). Kristeligt Dagblad. 4 December 2021.
  86. ^ "Germany, Denmark sign offshore wind power cooperation deal". www.reuters.com. Reuters. 1 June 2023.
  87. ^ Wittrup, Sanne. "Discount-udbud af 350 MW havmøller skudt i gang " Ingeniøren, 20 February 2015. Retrieved 22 February 2015.
  88. ^ "New nearshore wind tenders" (PDF). Archived from the original (PDF) on 22 February 2015. Retrieved 22 February 2015.
  89. ^ "Kystnære havvindmøller | Energistyrelsen". Archived from the original on 22 January 2016. Retrieved 24 January 2016.
  90. ^ "Rekordlav pris: Vattenfall vinder kystmølleudbud med 47,5 øre pr. kWh". Ingeniøren. 12 September 2016. Retrieved 12 September 2016.
  91. ^ "ANALYSE: 350 MW kystmøller klemt i højpolitisk spil". Ingeniøren. 12 September 2016. Retrieved 12 September 2016.
  92. ^ "Markant udbygning af vindenergi" (PDF) (in Danish). Klima-, Energi- og Bygningsministeriet. 27 March 2012. Archived from the original (PDF) on 21 April 2014. Retrieved 20 April 2014.
  93. ^ "Miljødeklarering af 1 kWh el, 2020" (PDF). Energinet.dk. 1 June 2021.
  94. ^ "Denmark on track to have 50% renewable energy by 2030". Raidió Teilifís Éireann. 11 January 2018.
  95. ^ a b Hannele Holttinen, Simo Rissanen, Xiaoli Larsen, Anne Line Løvholm. "Wind and load variability in the Nordic countries" pages 20, 25, 53. VTT Technical Research Centre of Finland, 2013. Quote: "correlation between Finland and Denmark, and Norway and Denmark is almost non-existent"
    "Wind power production is higher during autumn and winter in all countries and the Nordic region."
    "in Denmark where the production is at the highest level in the afternoons from 1 to 5 pm"
  96. ^ "Nord Pool Spot implements negative price floor in Elspot from October 2009" (Press release). Nord Pool Spot. 4 February 2009. Archived from the original on 15 August 2010. Retrieved 14 April 2010.
  97. ^ "Elkunder betalte 37,7 millioner kr. til overflødig grøn strøm i 2014". Ingeniøren. 16 February 2015.
  98. ^ "2021 slår rekord i grøn strøm fra solen". energinet.dk (in Danish).
  99. ^ Hinrichsen, Michael Bilde (4 December 2019). "Stoppede vindmøller er kommet for at blive | Dansk Energi". www.danskenergi.dk (in Danish). Archived from the original on 30 October 2021.
  100. ^ "Statistik over specialregulering". energinet.dk (in Danish). 11 January 2021.
  101. ^ Andreasen Rasch, Sebastian (28 January 2021). "Når tyskerne betaler: Mere end tre gange så meget vindmøllestrøm gik til spilde i 2020". TV MIDTVEST (in Danish).
  102. ^ a b Tyske elpriser smitter af i Vestdanmark Archived 8 March 2016 at the Wayback Machine Energinet.dk, 19. november 2010
  103. ^ Import og eksport Archived 8 March 2016 at the Wayback Machine Energinet.dk, 30 April 2015
  104. ^ "Analysis of Wind Power in the Danish Electricity Supply in 2005 and 2006" (PDF). Techconsult. 8 October 2007. Retrieved 4 April 2009. It is often said that wind power covers ca. 20% of Danish electricity consumption. It is more correct to say that the production of power by Danish wind turbines corresponds to about 20% of electricity demand. But a considerable part of the wind energy produced is exported to neighbouring countries and thus does not cover any part of Danish electricity consumption. (...) For the whole country the degree of cover in 2005 was 13.6% (not 18.7% as stated by the Wind Turbine Industry), and in 2006 it was 10.3%, not 17%. Translation of "Analyse af Vindkraft i Dansk Elforsyning 2005 og 2006", Summary.
  105. ^ Sharman, Hugh (May 2005). "Why Wind Power Works in Denmark" (PDF). Proceedings of ICE, Civil Engineering. Thomas Telford, Ltd.: 66–72. Archived from the original (PDF) on 29 January 2011. Retrieved 4 April 2009.
  106. ^ Lund 2010, pp. 20–21 "the wind export in 2008 was only 61 GWh, equal to approx. 1 percent of the wind power production"
  107. ^ TSO Congestion rent Archived 21 November 2010 at the Wayback Machine Nord Pool Spot. Retrieved 24 September 2010.
  108. ^ Danske forbrugere tjener styrtende på vindstrøm Politiken, 16 September 2015.
  109. ^ "Denmark sells power at a higher price than we buy" VidenOmVind, 25 May 2012. Retrieved 5 September 2013.
  110. ^ a b c The world's leader in Wind Power, Scandinavica.com, published 2004. Retrieved 22 June 2007. Archived 25 January 2018 at the Wayback Machine
  111. ^ KASPER BRØNDGAARD ANDERSEN (20 September 2015). "Indtjeningsfest i vindmølleindustrien".
  112. ^ Analyse af leverandører til vindindustrien. Markedsudvikling 2013 Archived 4 March 2016 at the Wayback Machine, page 5. Deloitte
  113. ^ "Vindmøllebranchen tilbage på sporet efter krisen". Ingeniøren. 28 May 2015.
  114. ^ "Wind energy: A visionary match". Risø National Laboratory. Archived from the original on 12 October 2007. Retrieved 31 July 2010.
  115. ^ Boyle, 2004, p. 414.
  116. ^ Korsgaard Nielsen, Michael. "Vestjyder får havvindmøllepark til 300 mio. kroner" Berlingske, 10 February 2016
  117. ^ "Nissum Bredning Vind Offshore Wind Farm - Fully Commissioned - Denmark | 4C Offshore". www.4coffshore.com.
  118. ^ "Danish pilot to cut operating costs". 4c Offshore.
  119. ^ a b Afgiftsstruktur gør el langt dyrere end olie CSR.dk, 29 February 2016
  120. ^ Forbedring af den nationale elprisstatistik for erhverv page 7. Danish Energy Agency
  121. ^ Electricity price statistics EuroStat, November 2019
  122. ^ Electricity prices (table) Eurostat, October 2015
  123. ^ Electricity and natural gas price statistics EuroStat, May 2015.
  124. ^ "Derfor er omlægning af energiafgifter en svær øvelse". Ingeniøren. 12 April 2016. Retrieved 17 April 2016. The main part of tolls are not based on environment concerns
  125. ^ a b "Fremskrivning af PSO-udgifter" page 6+17. Danish Energy Agency, 19 May 2014. Retrieved 17 January 2015.
  126. ^ Energy statistics, 2014 Archived 21 January 2016 at the Wayback Machine page 12
  127. ^ Mauritzen, Johannes. "Windonomics : empirical essays on the economics of wind power in the Nordic electricity market" page 32. Thesis from Norwegian School of Economics, 2012. Handle page. Quote: "wind power has the effect of lowering intraday variability for both the entire Nordic system price as well as in the two Danish price areas"
  128. ^ Sharman, Hugh; Meyer, Henrik. "Wind Energy: The Case of Denmark" (PDF). Archived from the original (PDF) on 21 May 2010. Retrieved 17 August 2010.
  129. ^ Ritzau (18 March 2010). "Kul- og olielobby betalte Cepos-rapport". jv.dk. Retrieved 15 January 2020.
  130. ^ Andersen, Kasper Brøndgaard. "Omstridt CEPOS-rapport var betalt af kul- og olielobby Disputed CEPOS report was paid for by coal and oil lobby Ingeniøren, 18 March 2010. Retrieved January 2015.
  131. ^ Lund 2010 "the results of the CEPOS study are in general not correct"
  132. ^ "Danish Wind Power - Export and Cost" (PDF). Archived from the original (PDF) on 23 November 2015. Retrieved 13 September 2016.
  133. ^ Andersen, Kasper Brøndgaard. "Lykke Friis: CEPOS-rapport giver »fortegnet« billede af vindkraft Archived 11 February 2011 at the Wayback Machine Ingeniøren, 19 March 2010. Retrieved January 2015.
  134. ^ "Nuclear Energy in Denmark". World Nuclear Association. Archived from the original on 5 March 2016. Retrieved 7 March 2016. the CEPOS report was funded by American Institute of Energy Research .. and seems to be aimed at addressing the analogy made by President Barack Obama in his 22 April 2009 Earth Day speech, where he cited the example of Denmark and claimed that, by 2030, the USA could generate 20% of its electricity from wind
  135. ^ Obama, Barack. "Remarks by the President in Newton, IA Archived 2017-01-26 at the Wayback Machine" White House Office of the Press Secretary, 22 April 2009. Quote: "Even as we're conserving energy, we need to change the way we produce energy. Today, America produces less than 3 percent of our electricity through renewable sources like wind and solar – less than 3 percent. Now, in comparison, Denmark produces almost 20 percent of their electricity through wind power."
  136. ^ a b Paul Gipe (1996). "Community-Owned Wind Development in Germany, Denmark, and the Netherlands". Wind Works. Retrieved 21 June 2007.
  137. ^ Hans Christian Sørensen; Lars Kjeld Hansen; Jens H. Mølgaard Larsen (2002). "Middelgrunden 40 MW offshore wind farm Denmark: Lessons Learned" (PDF). SPOK Consult. Archived from the original (PDF) on 20 August 2006. Retrieved 21 June 2007.
  138. ^ Jens H. Larsen, Copenhagen Environment and Energy Office (2001). "The world's largest off-shore windfarm, Middelgrunden 40 MW". Middelgrunden Wind Turbine Co-operative. Archived from the original on 17 August 2007. Retrieved 21 June 2007.
  139. ^ Kolbert, Elizabeth. (7 January 2009) A Reporter at Large: The Island in the Wind. The New Yorker. Retrieved 2011-06-11.
  140. ^ Denmark's carbon-neutral island, Deutsche Welle, 27 September 2011

Sources

[edit]

Bibliography

[edit]
[edit]