Kajang line

From Wikipedia, the free encyclopedia
(Redirected from MRT Kajang Line)

Kajang Line
Semantan Platform 1 viewing KLCC at the background.
A Siemens Inspiro EMU stock designed by BMW Group Designworks leaving KG14 Semantan station.
Overview
Other name(s)MRT 1, MRT Line 1, KG Line, KGL
Native nameMRT Laluan Kajang
StatusFully operational
OwnerMRT Corp
Line number9 (green)
LocaleKlang Valley
Termini
Stations29 & 3 reserved
Websitemyrapid.com.my
Service
TypeRapid transit
SystemRapid KL (brand) Rapid KL
ServicesKwasa DamansaraKajang
Operator(s)Rapid Rail
Depot(s)Sungai Buloh Depot and Kajang Depot
Rolling stockSiemens Inspiro
58 four-car trainsets
Width: 3.1 m (10 ft) - wide profile
Length: 90.18 m (295.9 ft)[1]
Daily ridership220,868 (Q2 2024)[2]
Ridership66.5 million (2023)
History
OpenedPhase 1:
16 December 2016; 7 years ago (2016-12-16)[3]
Sungai Buloh  KG01 [note 1]Semantan  KG14 
Phase 2:
17 July 2017; 7 years ago (2017-07-17)
Muzium Negara  KG15 Kajang  KG31 
Technical
Line length47 km (29 mi)
Elevated: 37.5 km (23.3 mi)
Underground: 9.5 km (5.9 mi)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail
Conduction systemAutomated and driverless
Operating speed100 km/h (62 mph)
Route map

KG04
Kwasa Damansara
Parking Integrated Transport Terminal Sungai Buloh
KG05
Kwasa Sentral
Parking
KG05A
Teknologi
(future)
KG06
Kota Damansara-Thomson Hospital
KG07
Surian
KG08
Mutiara Damansara
KG09
Bandar Utama Parking
Shah Alam Line
to Johan Setia
KG10
Taman Tun Dr Ismail-Deloitte
KG12
Phileo Damansara Parking
KG12A
Bukit Kiara Selatan
(future)
KG13
Pavillion Damansara Heights-
Pusat Bandar Damansara
Parking
KG14
Semantan
KG15
Muzium Negara
KL Sentral KTM ETS
Kuala Lumpur KTM ETS
MR1
KG16
Pasar Seni
KG17
Merdeka
AG8
SP8
Plaza Rakyat Pudu Sentral
MR6
Bukit Bintang
KG18A
Pavillion Kuala Lumpur-Bukit Bintang
KG20
Tun Razak Exchange –
Samsung Galaxy
KG21
Cochrane
KG22
AEON-Maluri Parking
AG13
Maluri
KG23
Taman Pertama
KG24
Taman Midah
KG25
Taman Mutiara
KG26
Taman Connaught
Parking
KG27
Taman Suntex Parking
KG28
Sri Raya
KG29
Bandar Tun Hussein Onn
Parking
KG30
Batu 11 Cheras
KG31
Bukit Dukung
Parking
KG32
Taman Mesra
(future)
KG33
Sungai Jernih
Parking
KG34
Stadium Kajang
KG35
Kajang
Parking KTM ETS

Interchange stations

integrated paid area
single fare trip
non-integrated paid area
multiple fare trips
interchange within same building
or cross-platform interchange
Map
Route of the Kajang line

The MRT Kajang Line, previously known as the MRT Sungai Buloh–Kajang Line, is a Mass Rapid Transit (MRT) line servicing the Klang Valley, Malaysia. It is the second fully automated and driverless rail system in the Klang Valley region after the LRT Kelana Jaya Line. Owned by MRT Corp and operated as part of the Rapid KL system by Rapid Rail, it forms part of the Klang Valley Integrated Transit System. The line is numbered 9 and coloured green on official transit maps.

It is one of three planned MRT rail lines under the Klang Valley Mass Rapid Transit Project by MRT Corp. Phase 1 operations between Sungai Buloh and Semantan commenced service on 16 December 2016.[4] Phase 2 operations between Muzium Negara and Kajang was opened on 17 July 2017, as a free shuttle service, by former Malaysian Prime Minister, Dato' Seri Najib Tun Razak in a ceremony at the Tun Razak Exchange station. Full revenue service between Sungai Buloh and Kajang began the following day.[5][6][7]

History

[edit]

Initial LRT proposal

[edit]

In August 2006, the LRT Kota Damansara–Cheras line proposal was first made known to the public by the then Deputy Prime Minister Datuk Seri Najib Tun Razak under a RM10 billion government allocation for the improvement and expansion of the public transportation network in the Klang Valley as a new light rapid transit (LRT) system. The line is also targeted to alleviate traffic congestion in the Klang Valley by encouraging more commuters to opt for public transport.[note 2] It is also aimed to reduce overcrowding on the KL Monorail and to provide an alternative transport mode due to rising fuel prices.[9] It is estimated to be approximately 30 km (19 mi) in length.[8] This is planned in-line with the extension of the LRT Kelana Jaya Line and the LRT Sri Petaling Line, to Subang Jaya and Puchong respectively and converging at Putra Heights.[9] The combined cost of the new line and the proposed extensions were estimated at RM7 billion. Syarikat Prasarana Nasional Berhad (SPNB) was in charge of the construction of these lines. The line was planned to be served by 140 coaches, and the track gauge to be almost similar to existing LRT lines.[10] The Ministry of Transport had approved the alignment of the new line in July 2007 which would then be tabled to the Cabinet for approval.[11] The Finance Ministry's Parliamentary Secretary announced that the line from Kota Damansara to Cheras and Balakong would be completed by 2012.[12] The line would be 40 km (25 mi) long, serving densely populated areas in Damansara and Cheras via "The Golden Triangle" of Kuala Lumpur city.[note 3] The alignment was to be from Persiaran Surian to the Balakong Interchange on the Cheras-Kajang Expressway, passing through the Damansara-Puchong Expressway (LDP), Sprint Highway, the city, Jalan Tun Razak and Jalan Cheras, stopping at around 30 stations. Ownership of the line belonged to SPNB, and would be operated by Rapid Rail. The estimated construction cost is between RM4 billion and RM5 billion.[9]

In September 2008, Executive Director of SPNB said that a 5.9 km (3.7 mi) section of the line in central Kuala Lumpur will be underground, serving 5 stations. [citation needed] However, the locations of underground stations were not announced. It was during this time that the line was said to be 42 km (26 mi) with 32 stations in total, which would serve areas of Bandar Utama, Bangsar, KL Sentral, Bukit Bintang, Bandar Tasik Selatan and Cheras. The line was being considered for as a Mass Rapid Transit (MRT) system after taking into consideration the catchment area serving a population of 878,000. It was also reported that the detailed design stage for the line would commence in the second quarter of 2009 and the opening date is expected to be in 2014.[14][note 4]

New alignment and conversion to MRT

[edit]

On 14 September 2009, SPNB managing director Datuk Idrose Mohamed was reported as saying that the new line could end up longer than the earlier announced alignment although he did not offer any further details. A public display of the alignment was launched a day after the announcement. SPNB has raised the necessary funds from Islamic investments of RM2 billion and hopes to gain approval from the Ministry of Transport to call out for tenders.[16] In April 2010, a proposal to extend the line by 16 km (9.9 mi) was being studied by the government.[note 5] The proposal includes extensions from Kota Damansara to Sungai Buloh (additional 3 km (1.9 mi)) and from Cheras to Kajang (additional 9 km (5.6 mi)). This is to provide convenient interchanges to the existing Keretapi Tanah Melayu (KTM) stations at Sungai Buloh and Kajang, as well as supporting the upcoming development of some 3,000-acre (1,200 ha) land in Sungai Buloh. An additional branch line from Damansara Utama to Kelana Jaya (additional 4 km (2.5 mi)) aimed to relieve congestion on the LDP Highway was also being studied, bringing the total length of the line to 59 km (37 mi).[17]

Unofficial statements in 2009 claimed that the proposed line was changed to an MRT line.[18] In June 2010, during the tabling of the 10th Malaysia Plan, [19] Prime Minister Najib Tun Razak announced that the government was now considering a RM36 billion Klang Valley MRT proposal from Gamuda Berhad and MMC Corporation Berhad, which is the largest national infrastructure project.[20] The proposal includes 3 lines, including one which is similar to the Kota Damansara—Cheras proposal.[note 6] The MRT lines were to be mostly underground with stations 500 m (1,600 ft) to 1 km (3,300 ft) apart in areas with high demand. The concept was envisioned to be inspired by Singapore's Mass Rapid Transit (MRT) system.[21][22][note 7] The project, aimed to improve public transport in the Klang Valley, was approved by the Malaysian cabinet on 16 December 2010 and construction of the first line from Sungai Buloh to Kajang would begin in July 2011 with a duration of five to six years.[23] Gross national income from these future lines is between RM3 bil and RM12 bil. [citation needed] The government had appointed MMC-Gamuda JV Sdn Bhd as Project Delivery Partner where it would play the role project manager, supervised by the Land Public Transport Commission (SPAD). The whole project would be divided into nine parcels in which will be done on open tender basis. 10 km (6.2 mi) of the line would be underground and the remaining 50 km (31 mi) above ground with 35 new stations. MMC-Gamuda would be barred from bidding for any tender except for tunnelling works (the most expensive portion). Ownership of the lines would be given to SPNB.[24][25]

To seek for further consultation from the public, SPAD held a 3-month public display of the alignment of the MRT Kajang Line.[26] On 8 July 2011, Razak officially launched the project. The final alignment was adjusted following the public display, having a length of 51 km (32 mi) with 31 stations where 16 have Park and Ride facilities. Construction was said to be completed in December 2016 and the line would start operations a month after.[27] On 17 August 2011, the government announced that Mass Rapid Transit Corporation Sdn Bhd (MRT Corp), a new company under the Finance Ministry had been formed to take control of the project from Prasarana. MRT Corp would be the asset owner of the project and officially take over the project from Prasarana on 1 September 2011.[28] After the MRT project was formally launched on 8 July 2011, the following amendments have been made to the original proposed alignment following the public display exercise between March and May 2011:[27][29]

  • 31 stations instead of 35 stations will be built and provisions have been made for 3 more stations [citation needed]
  • The location of the proposed TTDI station was moved around 300 m (980 ft) southwards to the former Caltex petrol stations. This was due to complaints from Taman Tun Dr Ismail and Damansara Kim residents.[30][31][32][33]
  • Bukit Bintang East and West stations have been combined into one, moved and integrated with KL Monorail station. The station was named Bukit Bintang Central Station and subsequently Bukit Bintang Station.[citation needed]
  • Park-and-ride facilities has been increased to 16 from 13 previously.
  • Adjustments to the alignment:
    • Shifting alignment into the former Rubber Research Institute of Malaysia land in Sungai Buloh to cater for future development
    • Adjusting the alignment adjacent to Bandar Kajang station to avoid going through the town centre and through Kajang Stadium.

Contract allocation

[edit]

On 21 October 2011, MRT Corp shortlisted 5 companies to construct the underground parts of the line including MMC Gamuda Joint Venture and Sinohydro Group.[34] On 26 January 2012, MRT Corp announced the award of the first two civil works contracts for the construction of the MRT Kajang line. IJM Construction Sdn Bhd was appointed the contractor for Package V5 at a tender price of RM974 million, while Ahmad Zaki Sdn Bhd was appointed the contractor for Package V6 at a tender price of RM764 million. Package V5 is from the Maluri portal to Plaza Phoenix (now Taman Connaught) station while Package V6 covers the section between Plaza Phoenix and Bandar Tun Hussein Onn stations.[35] MRT Corp announced the pre-qualification of 28 companies to bid for six System Works Packages for the MRT line on 8 March 2012.[36] Subsequently, in September 2012, another 31 companies were pre-qualified to bid for the remaining five System Works Packages.[37][38]

Construction

[edit]
All stations are fitted with platform screen doors (PSD), as seen here at Semantan station.

All stations are to be equipped with platform screen doors, where this contract was awarded to the Singaporean company Singapore Technology Electronics Ltd.[39] 33kV Main Switching Substations are to be constructed at 4 stations, namely Taman Industri Sungai Buloh (now Kwasa Sentral), Section 16 (now Phileo Damansara), Taman Cuepacs (now Sri Raya) and Kajang stations. The other 3 substations are added at the Cochrane launch shaft, Sungai Buloh depot and Semantan portal. Two more 132/33kV Transmission Main Intakes are constructed at Cochrane Launch shaft and Semantan portal. Tenaga Nasional Berhad (TNB) agreed to supply 116.5MW of power on the Kajang Line which costs RM173.1 million.[40]

On 1 November 2011, the 70's Klang bus stand ceased operations and was demolished to make way for the underground platforms and new entrances of Pasar Seni station. When construction of the station is completed, a new bus hub will be reconstructed.[41] On 1 August 2012, MRT Corp announced that the project was in active construction phase.[32] MRT Corp said that the project cost would not exceed the limit of RM23 billion. The first section between Sungai Buloh and Semantan was expected to open in December 2016, with the entire line opening in July 2017.[42]

On 30 May 2013, tunnel excavation works for the Kajang Line began with the world's first Variable Density Tunnel Boring Machine (VDTBM). This TBM was jointly designed by MMC Gamuda KVMRT Tunnelling and Herrenknecht AG, a German company. Commencement of tunnelling works was launched by former Malaysian Prime Minister Najib Tun Razak at the Cochrane Launch Shaft, which would later become the Cochrane MRT station.[43] The shaft is 30 m (98 ft) deep and this TBM was to dig a distance of 1.2 km (0.75 mi) towards Pasar Rakyat (now Tun Razak Exchange) station. 10 TBMs were used to construct the 9.5 km (5.9 mi) tunnelled section of the line, where 6 are Variable Density and 4 are Earth Pressure Balance TBMs.[44] The tunnels are to have a diameter of 6 m (20 ft), where the first breakthrough of the TBM excavations occurred on 25 December 2013.[45]

Opening

[edit]

On 16 December 2016, Phase 1 of the Kajang Line which spans 23 km from opened between Sungai Buloh to Semantan.

The fare of this part of the line and its feeder bus routes was free of charge until 16 January 2017.[46] Two days later, MRT Corp confirms cost of 51 km of Kajang Line would be RM21 billion.[47] On 17 July 2017, Phase Two of the line from Semantan to Kajang began operations.[48]

The line is operated by a subsidiary of Prasarana Malaysia, Rapid Rail.[49]

Overview

[edit]

Route

[edit]
KG04 Kwasa Damansara is an interchange station between MRT lines.

The MRT line covers a span of 47 kilometres (29 mi) from Kwasa Damansara to Kajang, passing the Kuala Lumpur city centre where the alignment goes underground. [citation needed] The line serves a corridor with 1.2 million residents within the Klang Valley region from the northwest to the southeast of Kuala Lumpur. [citation needed] The line starts from Kwasa Damansara which is located to the northwest of Kuala Lumpur, and runs on an elevated guideway to the Semantan portal, passing through Kota Damansara, Bandar Utama, Seksyen 17 Petaling Jaya, Phileo Damansara and Damansara Town Centre. [citation needed] Kwasa Damansara provides a cross-platform interchange between the MRT Kajang Line and the MRT Putrajaya Line. [citation needed] The line continues in twin-bore tunnels underground to the Maluri portal, passing through the city centre and the Golden Triangle of Kuala Lumpur. [citation needed] Interchanges to other lines are provided from Muzium Negara to Maluri with the exception of Cochrane station in Kuala Lumpur. [citation needed] Beyond Taman Pertama, the line passes through Cheras and ends in Kajang via an elevated guideway. [20][50]

Station designs

[edit]
A view of former Kajang line station: Kampung Selamat MRT station from Entrance A.

For the seven underground stations, the overall inspiration was from the Klang Gates Quartz Ridge, a pure quartz dyke found in the Klang Valley which has multi-faceted characteristics and has kaleidoscopic reflections.[citation needed] These features resemble Malaysia's multi-racial, multi-cultural and progressive society.[51] The concept is used in the designs of the different murals in the underground stations. Muzium Negara is fitted with tiles that depict the transition of the city's mode of public transport while Pasar Seni is "painted" with 'Y's, which represents the convergence of the Klang and Gombak rivers. [citation needed] Merdeka has the Rukun Negara sculpted on the walls of the concourse. Tun Razak Exchange has designs of blue and grey motives representing a modern Islamic Corporate theme. Cochrane features harmonious red and yellow colours while Bukit Bintang has vibrant red patterns. Maluri is filled with bright green, blue and yellow tiles which symbolises urban renewal.[51][52]

All stations are wheelchair accessible, with lifts and escalators serving each platform.[51] All platforms are equipped with platform screen doors.[39]

List of stations

[edit]
Station Code Station Name Image Opened Position Park & Ride Connecting Bus Lines Working Name Interchange/Notes
 KG04  Kwasa Damansara 16 December 2016 Elevated N/A Kota Damansara Northern terminus of both the MRT Kajang Line and MRT Putrajaya Line.

Cross-platform interchange with  PY01  MRT Putrajaya Line.

KWSP Tower (Headquarters) is located near this station.

 KG05  Kwasa Sentral 5 lines

T772 
T801 
T802 
T803 
T804 

Taman Industri Sungai Buloh Feeder Bus T804  to  KS03  Terminal Skypark for the KTM KL Sentral-Terminal Skypark Line.
 KG05A  Teknologi - - - - - Provisional station[27]
 KG06  Kota Damansara–Thomson Hospital 16 December 2016 Elevated N/A 2 lines

T805 
780 

PJU 5
 KG07  Surian N/A 4 lines

T807 
T808 
780 
802 

Dataran Sunway Feeder Bus T807  to  KJ25  Lembah Subang for the LRT Kelana Jaya Line.

Exit to Tropicana Gardens Mall and Sunway Nexis.

 KG08  Mutiara Damansara N/A 6 lines

T809 
T810 
PJ06 
780 
801 
802 

The Curve Exit to The Curve, IPC Shopping Centre, IKEA and Lotus's Mutiara Damansara.
 KG09  Bandar Utama 6 lines

T811 
T812 
PJ05 
PJ06 
780 
802 

One Utama Exit to 1 Utama Shopping Centre.

Future interchange with  SA01  LRT Shah Alam Line.

 KG10  Taman Tun Dr Ismail–Deloitte (TTDI) N/A 2 lines

T813 
T814 

TTDI
 KG11  Seksyen 17 - - - - - - Shelved station
 KG12  Phileo Damansara 16 December 2016 Elevated 2 lines

T815 
T816 

Seksyen 16 Feeder bus T815  to University of Malaya
 KG12A  Bukit Kiara Selatan - - - - - Provisional station.

Proposed interchange with  CC01  MRT Circle Line.

 KG13  Pavilion Damansara Heights–Pusat Bandar Damansara 16 December 2016 Elevated 1 lines

T817 

Pusat Bandar Damansara Feeder bus T817  to Mid Valley South Gate, providing access to  KB01  Mid Valley on the KTM Batu Caves-Pulau Sebang Line.

Exit to Pavilion Damansara Heights.

 KG14  Semantan N/A 5 lines

T818 
T819 
T820 
T821 
T852 

Semantan Feeder bus T819  to Hilton Kuala Lumpur, which is walking distance from  KA01  KS01  KJ15  KE1  KT1  MR1  KL Sentral and  KG15  Muzium Negara, and to  KA05  Segambut on the KTM Port Klang Line
 KG15  Muzium Negara 17 July 2017 Underground N/A 1 line

GOKL 03 

KL Sentral Connecting station, without paid-area integration, to KL Sentral, linked via a 600-meter pedestrian walkway, for:


Theme: Transition, History of Kuala Lumpur's Public Transportation

Exit to NU Sentral via an underground walkway.

 KG16  Pasar Seni 13 lines

GOKL 02 
180 
600 
640 
650 
750 
751 
770 
772 
780 
782 
821 
851 

Pasar Seni Interchange station with  KJ14  LRT Kelana Jaya Line

Connecting station, without paid area integration, to  KA02  Kuala Lumpur for KTM Batu Caves-Pulau Sebang Line, KTM Tanjung Malim-Port Klang Line and KTM ETS via a pedestrian bridge across the Klang River.

Bus hub to Puchong, Subang Airport, Petaling Jaya, Klang, Shah Alam and Subang Jaya.


Theme: Confluence Between Two Rivers

 KG17  Merdeka N/A Merdeka Interchange station with  AG8  SP8  Plaza Rakyat for the LRT Ampang and Sri Petaling Lines.


Theme: Independence, Spirit of Nationhood

Exit to Merdeka 118.

 KG18A  Pavilion Kuala Lumpur–Bukit Bintang 7 lines

GOKL 01 
GOKL 02 
GOKL 04 
400 
420 
421 
580 

Bukit Bintang Sentral Connecting station, without paid-area integration, to  MR6  KL Monorail.

Pedestrian access to  KJ10  KLCC on the LRT Kelana Jaya Line and  MR7  Raja Chulan for the KL Monorail via an elevated walkway from Pavilion Kuala Lumpur.

Theme: Dynamic

Exit to Lot 10, Sungei Wang Plaza, Fahrenheit 88, The Starhill and Pavilion Kuala Lumpur.

 KG20  Tun Razak Exchange–Samsung Galaxy (TRX) 2 lines

T407 
402 

Pasar Rakyat Cross-platform interchange with  PY23  MRT Putrajaya Line.


Theme: Islamic Corporate

Exit to The Exchange TRX via an underground link.

 KG21  Cochrane 4 lines

T352 
T400 
T401 
GOKL 11 
420 

Cochrane Feeder bus T401  to  SP12  Cheras for the LRT Sri Petaling Line.

Theme: Urban Living

Exit to IKEA Cheras and MyTOWN Shopping Centre via an underground link.

 KG22  AEON–Maluri 8 lines

T352 
T400 
T401 
GOKL 10 
GOKL 11 
400 
402 
450 

Maluri Interchange station with  AG13  for LRT Ampang Line.

Feeder bus T401  to  SP12  Cheras for the LRT Sri Petaling Line.

Theme: New Generation

Exit to Sunway Velocity and AEON Mall Taman Maluri.

 KG23  Taman Pertama
Elevated N/A 3 lines

T305 
400 
450 

Taman Bukit Ria
 KG24  Taman Midah 4 lines[53]

T305 
T402 
400 
450 

Taman Bukit Mewah

Feeder bus T402  to  SP13  Salak Selatan for the LRT Sri Petaling Line and Hospital Canselor Tuanku Muhriz UKM.

Proposed interchange with  CC22  MRT Circle Line.

 KG25  Taman Mutiara N/A 4 lines

T408 
T409 
400 
450 

Leisure Mall Exit to EkoCheras Mall and Cheras Leisure Mall.
 KG26  Taman Connaught N/A 4 lines

T410 
T411 
T412 
450 

Plaza Phoenix Feeder bus T410  to  KB04  SP15  KT2  Bandar Tasik Selatan.

Exit to Cheras Sentral Mall.

 KG27  Taman Suntex 3 lines

T413 
T406 
450 

Taman Suntex Exit to You City III Retail.
 KG28  Sri Raya 3 lines

T414 
T406 
450 

Taman Cuepacs
 KG29  Bandar Tun Hussein Onn 2 line

T415 
KJ03 

Bandar Tun Hussein Onn
 KG30  Batu 11 Cheras N/A 5 lines

T416 
T417 
T569 
450 
590 

Balakong
 KG31  Bukit Dukung 4 lines
T453 

T454 
T455 
450 

Taman Koperasi
 KG32  Taman Mesra - - - - - - Shelved station
 KG33  Sungai Jernih 17 July 2017 Elevated 2 line

T456 
450 

Saujana Impian
 KG34  Stadium Kajang N/A 8 lines

T450 
T451 
T457 
T458 
T459 
T460 
KJ01 
450 

Bandar Kajang Feeder bus T451  to Universiti Kebangsaan Malaysia via  KB06  Kajang and  KB07  UKM stations along the KTM Batu Caves-Pulau Sebang Line.
 KG35  Kajang 6 lines

T451 
T461 
T462 
T463 
T464 
450 
451 

Kajang Southern terminus.

Connecting station, without paid-area integration to  KB06  KTM Batu Caves-Pulau Sebang Line and KTM ETS.[54]

Proposed interchange with Putrajaya Monorail

Rolling stock

[edit]
MRT SBK real time passenger information display system (PIDS)
MRT SBK interior rolling stock designed by BMW Group Designworks

According to MRT Corp, the four-car train sets are servicing the line with an average headway of 3.5 minutes in an hour, equivalent to 400,000 passengers per day.[55]

The rolling stock is manufactured by Siemens/CSR Nanjing Puzhen in a partnership with SMH Rail Consortium Sdn Bhd. The trains will be driverless with a capacity of 1,200 passengers in a 4-car trainsets formation. The Siemens Inspiro rolling stock will be supplied with the same configuration as the trainsets supplied for Warsaw Metro M1.[56]

  • 29 June 2014: The first two train car bodies arrived in Westport, Port Klang, Selangor. The train will be assembled in the country's first train assembly plant in Rasa, Hulu Selangor. The purpose built plant for the KVMRT project is solely owned and operated by SMH Rail Sdn Bhd. SMH Rail had a consortium partnership with Siemens AG and Siemens Malaysia. Work to assemble the trains began immediately after the first two train car bodies arrived in Westport. The time taken to assemble one train set is about 30 days. The plant has two assembly lines, allowing work on four trains sets to be carried out at the same time.[57]
  • 30 November 2014: Another 14 train car bodies had arrived.

Car length (over coupler): 22.89 m (75 ft 1 in) (end car), 22.2 m (72 ft 10 in) (intermediate car)[1]

Number of passenger doors per car side / door width: 4 / 1400 mm

Traction power supply: 750 V DC, third rail

The 4-car trainsets are maintained at 2 purpose built facilities, Sungai Buloh and Kajang depots, located nearby Kwasa Damansara and Sungai Jernih stations respectively.[58]

Approximately 42 trains are required during peak hour operations.[59]

Formation

[edit]

The train consist of four cars, with cars 1 towards Kajang and cars 2 towards Kwasa Damansara.

Set designation 1 3 4 2
Formation Cabin Middle Car Middle Car Cabin

As of December 2023, a maximum of 31 of the 58 train fleet are used during peak hours.[60] According to Transport Minister Anthony Loke, this is because the remaining fleet are awaiting wheel replacements, which is being carried out in stages from June 2022.[61]

Ridership

[edit]
Kajang Line Ridership[62][63]
Year Month/Quarter Ridership Annual Ridership Note
2024 Q4 61,452,371
Q3 22,028,898
Q2 20,099,040
Q1 19,324,433
2023 Q4 19,020,393 66,501,508
Q3 17,247,227
Q2 15,757,999
Q1 14,475,889
2022 Q4 13,753,773 45,359,948
Q3 13,688,093
Q2 10,682,308
Q1 7,235,774
2021 Q4 6,822,387 19,573,010
Q3 2,666,394
Q2 4,714,785
Q1 5,369,444
2020 Q4 6,179,979 33,168,335
Q3 9,608,104
Q2 3,406,537
Q1 13,973,715
2019 Q4 17,420,684 63,952,805
Q3 16,370,286
Q2 15,243,503
Q1 14,918,332
2018 Q4 14,558,640 51,314,240
Q3 13,424,667
Q2 11,997,681
Q1 11,333,252
2017 Q4 10,365,061 22,253,637
Q3 9,318,373  KG14  Semantan KG35  Kajang section opened on 17 July 2017
Q2 1,161,218
Q1 1,505,856
2016 Dec - - Phase One opened on 16 December 2016 but ridership was not officially tabulated

In the second quarter of 2018, the quarterly ridership is a little short of 12 million, following an overall rising trend. However, the line is deemed to have inadequate ridership to cover the construction, operation and maintenance costs. A target of 250,000 daily passengers is required for the line to break even with its operation costs.[64]

Depots

[edit]
Sungai Buloh Depot

There are two maintenance depots for the Kajang Line, namely the Sungai Buloh depot and Kajang depots. The former is accessible by trains to the north of Kwasa Damansara station, while the latter is located near Sungai Jernih, where trains access the depot from Bukit Dukung instead.[65][66]

See also

[edit]

Notes and references

[edit]

Notes

[edit]
  1. ^ The terminus station is currently Kwasa Damansara  KG04  since 16 June 2022.
  2. ^ As of 2006, the percentage of public transport passengers was only 11%.[8]
  3. ^ The Golden Triangle is Malaysia’s leading business hub, spanning areas to the north of Jalan Pudu and Jalan Changkat Thambi Dollah, west of Jalan Tun Razak and south of Jalan Ampang.[13]
  4. ^ By May 2009, tenders for the LRT Kelana Jaya Line and LRT Ampang Line extension projects would be called as the designs have been finalised but there was no news on the implementation of the Kota Damansara-Cheras Line.[15]
  5. ^ The main section of the line is to be extended by 12km while a branch line will extend the line by 4km.[17]
  6. ^ The second line is expected to be connecting Sungai Buloh, Kepong, the city and Serdang while the third line is an orbital route.[21]
  7. ^ Developers in KL city had been asked to redesign their upcoming mixed-development projects to integrate with MRT stations.[21][22]

References

[edit]
  1. ^ a b "Metro Klang Valley Kuala Lumpur - 58 driverless four-car metro trains" (PDF). Siemens Mobility.
  2. ^ "Ridership". Rapid Rail Performance Update. RapidKL. 26 July 2024. Archived from the original on 7 August 2024. Retrieved 8 August 2024.
  3. ^ Rapid Rail to take over SBK line ops from Dec 15
  4. ^ Ruban, A. (16 December 2016). "A quiet start to Malaysia's first MRT, but commuters happy". The Malay Mail Online. Retrieved 18 December 2016.
  5. ^ "Najib launches Phase 2 of Sungai Buloh-Kajang MRT line". The Star Online. Retrieved 17 July 2017.
  6. ^ "PM picks '17-7-2017' start date for MRT phase two". The Malay Mail. Retrieved 9 June 2017.
  7. ^ "Phase 2 of Sg Buloh-Kajang MRT to be launched on July 17". Free Malaysia Today. 8 June 2017. Retrieved 9 June 2017.
  8. ^ a b "Rail Travel Expansion". The Star. 30 August 2006. Archived from the original on 27 October 2018.
  9. ^ a b c "Kota Damansara-Cheras Rail Line Right on Track". The Star. 15 June 2008. Archived from the original on 27 October 2018.
  10. ^ "Putting The Best Route Forward". The Star. 24 September 2006. Archived from the original on 27 October 2018.
  11. ^ "New LRT Lines Approved". The Star. 7 July 2007. Archived from the original on 27 October 2018.
  12. ^ "LRT Projects Set For Next Year". The Star. 20 April 2007. Archived from the original on 27 October 2018.
  13. ^ "Golden Triangle's Renaissance". Star Property. 5 August 2016. Archived from the original on 27 October 2018. Retrieved 27 October 2018.
  14. ^ "Laluan LRT Bawah Tanah Baru Di KL" (PDF) (in Malay). Utusan. 5 September 2008. Archived from the original (PDF) on 22 July 2011.
  15. ^ "Govt May Invite Tenders For LRT Extension in 3 Months". TheEdgeDaily. 21 May 2009. Archived from the original on 25 May 2009.
  16. ^ "RM6-7 billion for LRT extensions". TheEdgeDaily. 14 September 2009. Archived from the original on 30 October 2018.
  17. ^ a b "Additional routes for Cheras-Kota Damansara line". TheEdgeDaily. 9 April 2010. Archived from the original on 3 March 2012. Retrieved 30 October 2018.
  18. ^ "NU Sentral Set To Improve Urban Transportation, Says Najib". Bernama. 11 August 2009. Archived from the original on 23 May 2012.
  19. ^ "Tenth Malaysia Plan". Archived from the original on 27 December 2012. Retrieved 20 November 2018.
  20. ^ a b "MRT". Archived from the original on 15 May 2015. Retrieved 24 April 2015.
  21. ^ a b c "RM30b MRT plan". The New Straits Times. 8 June 2010. Archived from the original on 11 June 2010.
  22. ^ a b Au Foong Yee (7 June 2010). "KL to have MRT system, say sources". The Edge. Archived from the original on 3 March 2012. Retrieved 20 November 2018.
  23. ^ "Kajang Line". MRT Corp. Retrieved 17 July 2023.
  24. ^ Loh Foon Fong (18 December 2010). "PM: Construction of RM36bil KL Mass Rapid Transit (MRT) to begin July". The Star. Archived from the original on 19 December 2010.
  25. ^ Loh Foon Fong (19 December 2010). "RM36b MRT project to be broken down to nine parcels for open tender". The Star. Archived from the original on 21 December 2010.
  26. ^ "Klang Valley MRT Public Display Shows Majority Want The Project" (PDF) (Press release). 7 June 2011. Archived (PDF) from the original on 20 November 2018. Retrieved 20 November 2018.
  27. ^ a b c Chooi, Clara. "Najib launches MRT project at glitzy do". Malaysian Insider. Archived from the original on 11 July 2011. Retrieved 8 July 2011.
  28. ^ "Putrajaya puts MRT under new project owners". Malaysian Insider. 19 August 2011. Archived from the original on 3 September 2011. Retrieved 19 August 2011.
  29. ^ transitmy. "MRT Update: MyRapidTransit launching & public viewing on 8 July 2011 at KL Convention Centre". Malaysian Transit. Archived from the original on 20 July 2012. Retrieved 11 July 2011.
  30. ^ "Designing a World Class MRT". The Star. 30 May 2017. Archived from the original on 4 December 2018. Retrieved 4 December 2018.
  31. ^ "TTDI Residents Against MRT System". The Star. 16 January 2011. Archived from the original on 4 December 2018. Retrieved 4 December 2018.
  32. ^ a b "MRT project moves into active construction phase". The Star. 2 August 2012. Archived from the original on 3 August 2012. Retrieved 3 December 2018.
  33. ^ Achariam, Noel (30 May 2011). "Proposed TTDI MRT station shifted". New Straits Times. Archived from the original on 5 December 2018. Retrieved 6 June 2011.
  34. ^ "KL shortlists bidders for RM7b rail works". Business Times, New Straits Times. 21 October 2011. Archived from the original on 22 October 2011. Retrieved 21 October 2011.
  35. ^ "IJM, AZRB win MRT jobs". The Star. 27 January 2012. Archived from the original on 3 December 2018. Retrieved 3 December 2018.
  36. ^ "Twenty Eight Companies Pre-qualify For Six MRT System Work Packages" (PDF) (Press release). MRT Corp. 8 March 2012. Archived (PDF) from the original on 3 December 2018. Retrieved 3 December 2018.
  37. ^ "MRT Corp Awards 4 Work Packages" (PDF) (Press release). MRT Corp. 12 July 2012. Archived (PDF) from the original on 3 December 2018. Retrieved 3 December 2018.
  38. ^ "MRT Corp awards five contracts worth RM3.74bil for Sungai Buloh-Kajang line". The Star. 15 September 2012. Archived from the original on 3 December 2018. Retrieved 3 December 2018.
  39. ^ a b "MRT Corp awards 3 system work contracts worth RM302mil". The Star. 6 February 2013. Archived from the original on 3 December 2018. Retrieved 3 December 2018.
  40. ^ "Electricity Supply Agreement between MRT Corp and TNB". myMRT. 14 December 2012. Archived from the original on 4 December 2018. Retrieved 4 December 2018.
  41. ^ "Klang Bus Stand to cease operations". Star Metro. Archived from the original on 21 October 2011. Retrieved 21 October 2011.
  42. ^ "Sungai Buloh-Kajang MRT project wont cost over RM23bil, says CEO". The Star. 21 December 2012. Archived from the original on 3 December 2018. Retrieved 3 December 2018.
  43. ^ Syed Umar Ariff (31 May 2013). "MRT project on track, says PM". New Straits Times. Archived from the original on 27 August 2013.
  44. ^ "World's First Variable Density Tunnel Boring Machine Launched". myMRT. 30 May 2013. Archived from the original on 4 December 2018. Retrieved 4 December 2018.
  45. ^ "First Breakthrough for MRT Project". The Star. 25 December 2013. Archived from the original on 4 December 2018. Retrieved 4 December 2018.
  46. ^ "Najib: Free MRT, feeder bus rides until Jan 16". The Star. 15 December 2016. Archived from the original on 4 December 2018. Retrieved 4 December 2018.
  47. ^ Adrian Lai (18 December 2016). "MRT Corp says Rafizi got it wrong, RM21bil for both Phase 1 and 2 of SBK Line". New Straits Times. Archived from the original on 22 December 2016.
  48. ^ "PM picks '17-7-2017' start date for MRT phase two | Malay Mail".
  49. ^ "Government goes with Prasarana to operate Sg Buloh-Kajang MRT line". The Malaysian Insider. 16 June 2014. Archived from the original on 17 June 2014.
  50. ^ "Sungai Buloh-Kajang (SBK Line)". myMRT. Archived from the original on 4 December 2018. Retrieved 4 December 2018.
  51. ^ a b c "Sungai Buloh—Kajang line - Stations". myMRT. Archived from the original on 20 November 2018. Retrieved 20 November 2018.
  52. ^ "MRT stations designed to tell the story of M'sia". The Star. 3 August 2017. Archived from the original on 4 December 2018. Retrieved 4 December 2018.
  53. ^ "MyRapid". www.myrapid.com.my. Retrieved 9 April 2018.
  54. ^ "MRT". MyRapid. Retrieved 7 September 2021.
  55. ^ "MYMRT | MRT Corp - Official webpage for the Klang Valley My Rapid Transit". Archived from the original on 18 January 2013. Retrieved 15 January 2013.
  56. ^ MRT Corp (14 September 2012). "MRT CORP AWARDS RM3.474 BILLION WORTH OF CONTRACTS" (PDF) (Press release). MRT Corp. Archived (PDF) from the original on 3 July 2020. Retrieved 4 July 2020.
  57. ^ "MRT Newsletter" (PDF) (Press release). MRT Corp. July–December 2014. Archived (PDF) from the original on 3 July 2020. Retrieved 4 July 2020.
  58. ^ Progress Report (PDF). MRT Corp. 2012. p. 13. Archived from the original (PDF) on 4 March 2016.
  59. ^ Mohamad Azmi, Kamarul Azhar (9 February 2023). "Cover Story 2: Getting the Klang Valley Rail System Back on Track". Archived from the original on 13 February 2023. Retrieved 13 February 2023.
  60. ^ "Rapid Rail Performance Update". MyRapid. Retrieved 25 November 2023.
  61. ^ "Rapid Rail issues update on LRT, MRT and Monorail upgrading works; timeline for frequency improvement - paultan.org". Paul Tan's Automotive News. 27 October 2022. Retrieved 25 November 2023.
  62. ^ "Prasarana's Ridership". 18 January 2024. Archived from the original on 18 January 2024. Retrieved 18 January 2024.
  63. ^ "Statistic of Rail Transport". Ministry of Transport (Malaysia). Archived from the original on 12 January 2023.
  64. ^ "MRT needs 250,000 daily passengers to break even".