Jump to content

Grayston Pedestrian and Cycle Bridge

From Wikipedia, the free encyclopedia
Grayston Pedestrian and Cycle Bridge
Coordinates26°6′26.85″S 28°4′35.14″E / 26.1074583°S 28.0764278°E / -26.1074583; 28.0764278
CarriesCycle and pedestrian traffic
CrossesM1 motorway
LocaleJohannesburg
Official nameKopanang Bridge (proposed)
Characteristics
Total length176m
Width7.65m
Longest span100m
History
Opened18 May 2018
Location
Map

The Grayston Pedestrian and Cycle Bridge, previously also known as The Great Walk Bridge, forms part of a 5 km dedicated path between Alexandra on the eastern and Sandton on the western side of the M1 motorway in Johannesburg. Proposals have been made by City of Johannesburg to adopt the official name Kopanang Bridge.

Structural design

[edit]

The bridge is a cantilever spar cable-stayed bridge and is designed to fit snugly just north of the M40 Grayston Drive interchange with M1 motorway.[1] The straight central section of the bridge is 176m long and consists of three spans. The two short spans are 38 m long and cross the on and off ramps on the eastern and western sides respectively. The main span of the bridge is 100m long and consists of a single and continuous cable-stayed deck supported by a single 70m high inclined pylon 26°6′26.85″S 28°4′35.14″E / 26.1074583°S 28.0764278°E / -26.1074583; 28.0764278 on the western side and by a pier on the eastern side. The deck is suspended by means of nine cables extending diagonally from the pylon and attached to the deck along the median. The pylon is inclined towards the west and is restrained by a double set of nine cables extending down to a pair of plinths at ground level.

Collapse during construction

[edit]

On 14 October 2015 temporary works erected over the busy M1 motorway collapsed onto the passing traffic.[2] Two people were killed and 19 were injured in the collapse which blocked both the north and southbound traffic.[3] At the time of the collapse very little permanent works had been executed by the contractor. Piling on the western side in the vicinity of the foundations for the pylon had been completed and on day of the collapse blinding concrete was being placed to the base of the pylon pile cap. After the collapse the contractor adopted an alternative construction method which was analysed in December 2015.[4]

Deaths during construction

[edit]
  • A motorist Mr Adrian Doodnath and a taxi driver Mr Siyabonga Myeni were killed on 14 October 2015 when temporary works collapsed onto the vehicles they were driving.
  • A forty-one year old construction Mr Enoch Maphunye fell to his death from the height of several floors on 30 November 2017.

Section 32 Inquiry

[edit]
  • On 28 October 2015 the Department of Labour released a preliminary report and announced that a Section 32 inquiry in terms of the OSH Act would be held in public.[5]
  • On 19 November 2015 Commissioner Lennie Samuel was appointed Presiding Inspector for the Section 32 [6]
  • A media briefing was held on 8 December 2015. Labour hosts media briefing on Grayston Drive Pedestrian and cyclist structural bridge collapse.[7]
  • The first session of the Inquiry began on 16 February 2016.[8]
  • Inquiry scheduled to resume on 26 September 2017.[9]
  • Inquiry postponed until July 2018 after concluding with expert witnesses.[10]
  • On 8 March 2018 the Department of Labour announced the appointment of a new presiding officer.[11]

References

[edit]
  1. ^ "Construction of R130m Alex-Sandton bridge gets under way". jda.org.za. Retrieved 19 July 2017.
  2. ^ "UPDATE: Grayston temporary works for bridge collapses onto M1". www.enca.com. Retrieved 19 July 2017.
  3. ^ "Probes under way as M1 reopens". news24.com. Retrieved 19 July 2017.
  4. ^ "Analysis of construction stages for travelling formwork method". lentas.com.pl. Retrieved 1 September 2017.
  5. ^ "Department of Labour preliminary report on the incident investigation into Grayston Drive Pedestrian and cyclist structural bridge collapse — Department of Labour". Archived from the original on 2015-11-06.
  6. ^ ://www.enca.com/south-africa/presiding-inspector-appointed-grayston-bridge-collapse-inquiry
  7. ^ "Labour hosts media briefing on Grayston Drive Pedestrian and cyclist structural bridge collapse".
  8. ^ "Grayston bridge collapse inquiry begins next week".
  9. ^ "Grayston Bridge inquiry to resume in September — Department of Labour". Archived from the original on 2017-09-10.
  10. ^ "Archived copy". Archived from the original on 2017-09-29. Retrieved 2018-03-26.{{cite web}}: CS1 maint: archived copy as title (link)
  11. ^ "Department of Labour Chief Inspector appoints Maphaha as new presiding officer of Grayston Drive pedestrian and cyclist structural bridge collapse inquiry — Department of Labour". Archived from the original on 2018-08-11. Retrieved 2018-03-09.