River-class destroyer (2030s)
A rendering of the Canadian Surface Combatant
| |
Class overview | |
---|---|
Builders | Irving Shipbuilding |
Operators | Royal Canadian Navy |
Preceded by | |
Cost | $77.3 billion[1] |
Built | 2025–2050 |
In service | From early 2030s |
Planned | 15 |
General characteristics [2] | |
Type | Guided missile destroyer (DDGH) |
Displacement | 8,080 t (7,950 long tons) (standard) |
Length | 151.4 m (496 ft 9 in) |
Beam | 20.75 m (68 ft 1 in) |
Draught | 8 m (26 ft 3 in) |
Propulsion |
|
Speed | 27 knots (50 km/h; 31 mph) |
Range | 7,000 nmi (13,000 km; 8,100 mi) |
Complement | 210 |
Sensors and processing systems |
|
Electronic warfare & decoys |
|
Armament | *list error: list item missing markup (help)
|
Aircraft carried |
|
Aviation facilities |
|
Notes |
|
The River-class destroyer, formerly the Canadian Surface Combatant (CSC), and Single Class Surface Combatant Project is the procurement project that will replace the Iroquois and Halifax-class warships with up to 15 new ships beginning in the early 2030s as part of the National Shipbuilding Procurement Strategy.[14][15]
At approximately 8000 tonnes, the replacement vessels will have almost double the displacement of the existing Halifax-class frigates,[16] and presumably provide a wide-area air defence capability, anti-submarine as well as anti-ship warfare capability. The design of these ships is currently underway, and both the total number of ships and their capability will be dependent on the budget that is allocated to the project. In 2017, a new defence policy framework, entitled Strong, Secure and Engaged, was unveiled which promised significantly greater resources for the Surface Combatant Project - i.e. in the range of $60 billion. By 2021, the Parliamentary Budget Officer estimated the cost for the program of 15 Type 26 ships as $77.3 billion, "rising to $79.7 billion if there is a one-year delay in the start of construction and $82.1 billion if there is a two-year delay".[1]
By December 2017, the three submitted proposals were:[17]
- British Type 26 frigate design proposed by Lockheed Martin Canada and BAE Systems
- Dutch De Zeven Provinciën-class frigate-based design proposed by Alion Canada and Damen Group
- Spanish F-105 frigate design offered by Navantia
On 19 October 2018, the Type 26 was selected as the "preferred design", and the government entered "into negotiations with the winning bidder to confirm it can deliver everything promised in the complex proposal."[18][19] However, after Alion Canada, one of the failed bidders, began litigation in November 2018, the government was ordered to postpone any discussion of contracts until the investigation by the Canadian International Trade Tribunal was complete.[20] The Trade Tribunal dismissed the complaint for lack of standing on 31 January 2019,[21] and the Canadian government signed the $60 billion contract with the winning bidders on 8 February 2019.[22] Alion appealed the decision to Federal Court, but discontinued its challenge in November 2019.[23]
History
[edit]The Single Class Surface Combatant Project is a naval procurement program for the Royal Canadian Navy created to replace the aging Iroquois-class anti-air warfare destroyers and Halifax-class multi-role frigates. The Iroquois and Halifax ships have come to the end or are nearing the end of their service lives and require replacement.[24] The Iroquois class was originally scheduled for retirement around 2010 after 40 years in service; the ships were then expected to have their service lives extended until replacements were commissioned. However, all four have been decommissioned, the last being HMCS Athabaskan in March 2017. The Halifax class is projected to end their service lives in the 2020s.[25]
The navy had investigated adopting the active phased array radar (APAR), leading observers to suggest that APAR and the associated SMART-L would equip the Single-Class Surface Combatant or upgraded Halifax-class ships during the Frigate Equipment Life Extension (FELEX) project. Upgrades to the existing Halifax class with such a system would likely be difficult since the APAR requires its own mast and might make the Halifax-class design top-heavy.[26][27]
In the 2008 Canadian National Shipbuilding Procurement Strategy, $26 billion was planned for the construction of the 15 vessels of the Single Class Surface Combatant Project.[28][29] The first ships were slated to become available in 2026. The initial plan called for separate bids for design and integration of systems aboard the vessels. The government later investigated merging those bids.[30]
On 26 October 2012 a letter of interest was published by Public Works and Government Services Canada to announce a session in which interested firms could find out the needs of DND for the new class and the project in general. The closing date was 5 November 2012.[31] On 20 January 2015, Irving Shipbuilding was named the prime contractor for the program.[32] The role of the lead contractor gave Irving Shipbuilding overall control of the project, and the company had already won the right to build the vessels at its yard in Halifax, Nova Scotia. This led to questions concerning the bidding process and the awarding of the contracts.[33] In fall 2015, high increases in costs were reported, more than doubling to $30 billion from $14 billion for the new warships.[34] The total cost of the naval ship building program rose from $26.2 billion to $42 billion in a study. This put in jeopardy the number of ships that could be produced and raised the prospect of ships with reduced capabilities.[34]
In November 2015, seven companies were pre-qualified for the combat systems integrator role. Atlas Elektronik, DCNS, Lockheed Martin Canada, Saab Australia, Selex ES, Thales Nederland and ThyssenKrupp Marine Systems Canada all made the shortlist. For the warship designer role, the following companies were pre-qualified: Alion-JJMA, BAE Systems, DCNS, Fincantieri, Navantia, Odense Maritime Technology and ThyssenKrupp Marine Systems Canada.[35]
On 13 June 2016, Minister of Public Services and Procurement Judy Foote announced that the government would buy and modify an off-the-shelf design for the new warships, instead of designing them from scratch. The minister said a competitive bid for an existing design would knock about two years off the process and save money.[36] The nearly $2 billion saving in research and development costs would allow for more ships to be built and the integration of more advanced technology with increased capability, over the long term.[citation needed]
It was originally anticipated that two CSC ship variants would have been acquired to replace the specific capabilities of the Iroquois-class destroyers and Halifax-class frigates. As originally intended, both variants would have the necessary combat capabilities to operate in air, surface and subsurface threat environments. A small number of ships (up to five) would have additionally incorporated the sensors, guided weapons and command and fire control facilities necessary to perform large-area air defence, along with having the facilities to be task force flagships. The remaining ships would have replaced the capabilities provided by the current fleet of Halifax-class frigates as a more general purpose/antisubmarine warfare variant.[35] However, only one variant will be acquired due to cost effectiveness, crew training efficiencies, and being better suited to the navy's operational needs.[37]
On 20 October 2020, Alan Williams (former Assistant Deputy Minister, Supply Operations Service in Public Works and Government Services Canada, and former Assistant Deputy Minister of Materiel at the Department of National Defence) released a paper examining the estimated life-cycle costs of Canada's Canadian Surface Combatants. Williams estimated that acquisition, operating and supporting the Canadian Surface Combatants throughout their life-cycle of approximately 30 years will cost between $213.5 and $219.6 billion. Approximately two-thirds of these costs are attributable to the long-term operations and support (O&S) costs of the CSC.[38]
This report caught the attention of the House of Commons Standing Committee on Government Operations and Estimates. Additionally, the National Shipbuilding Strategy was set to have a planned Auditor General review in early 2021.[needs update] This level of watchdog review and spiralling cost estimates drew parallels to Canada's acquisition of F-35 Lightning II fighter jets.[39]
Bids
[edit]In October 2016 it was reported that twelve bidders had been asked to submit their designs by 27 April 2017. Foote announced that only designs from ships already in service or mature existing designs would be part of the process. However, concerns were raised when it was revealed that BAE Systems would be expected to submit their Type 26 frigate for consideration even though it had not yet been built.[40][41] Delays in the bidding process were announced by the government in February 2017 after a third of the entrants requested more time to compile a bid. Bids were to be submitted by 22 June with a winner expected to be declared in Fall 2017.[42] Further delay in the bidding process arose due to the Government of Canada's demand that any intellectual property associated with the vessel be transferred upon purchase. This led to a diplomatic exchange and one of the bidders' nations to demand direct negotiations between governments.[43] The selection of the design was pushed to Spring 2018.[44] The deadline for bids was first extended to 17 November, then again to 30 November 2017.[45][46]
On 28 November 2017, BAE Systems along with its partners Lockheed Martin Canada; CAE Inc.; L3 Technologies; MacDonald, Dettwiler and Associates; and Ultra Electronics, officially pitched their Type 26 warship design for the Canadian Surface Combatant project.[47] Another front-runner, a joint bid by Fincantieri and Naval Group (formerly DCNS) for their FREMM multipurpose frigate was offered informally on 6 November, directly to the National Defence Minister, Harjit Sajjan, which he did not accept. Fincantieri and Naval Group de facto withdrew from the process by not making a formal bid by 30 November 2017 deadline.[48] The company's fixed price offer of $20.9 billion was lower than the other bids. However, unlike the other bids, this price excluded the cost of design, infrastructure, spare parts, training, ammunition, contingencies and project management.[49] (Typically, the acquisition of the ships themselves only represents about 50-60% of the project's overall budget.) The unsolicited bid was rejected because it came outside of the official bidding process.[50] However, on 8 December 2017, Naval Group/Fincantieri announced they would continue to submit and support their unsolicited bid, with letters of project endorsement and promised long-term support from French Defence Minister Florence Parly and Italian Defence Minister Roberta Pinotti. Naval Group and Fincantieri said they could provide the vessels to the Canadian government for $20.9 billion and begin construction at Irving as early as 2019.[51] It was also alleged that due to concerns over possible fairness of the bidding process, two European shipbuilders declined to submit bids.[50]
Confirmed contenders
[edit]- Alion-JJMA – De Zeven Provinciën-class frigate[52]
- BAE Systems – Type 26 frigate[53]
- Navantia – F-105 frigate[54]
Rejected bids
[edit]In October 2018, the group led by BAE Systems and Lockheed Martin Canada and offering the Type 26, were selected as the preferred design.
In February 2019, the design and design team for Canada's future surface combatant had determined and the corresponding contracts were awarded.[56]
Construction
[edit]Given the need to fully develop the Canadian design, tool up the shipyard and first complete the preceding eight-vessel Arctic Offshore Patrol Ship project, the envisaged start date for construction is in 2025 with the first vessel to enter service in the early 2030s.[15][57][58][59]
The ships were ordered on 28 June 2024, which coincided with the announcement of the class's namesakes. The date also marked the start of construction on the production test module at Irving Shipbuilding. This module will be used to test and streamline building processes. The lessons learned from this process will then be applied in order to enable the start of full-rate production in 2025. Delivery of the first River-class destroyer, HMCS Fraser, is expected in the early 2030s, with the first nine ships projected to be built by 2040.[60] The final ship, of a projected total of 15 destroyers, is expected to be delivered by 2050.[61]
Ships
[edit]Italics indicate projected dates
Name | Hull classification symbol | Builder | Ordered | Laid down | Launched | Commissioned | Status | Namesake |
---|---|---|---|---|---|---|---|---|
Fraser | DDGH | Irving Shipbuilding and Lockheed Martin Canada-BAE Systems consortium, Halifax | 28 June 2024 | 2025/26[15] | Early 2030s | Ordered | Fraser River | |
Saint-Laurent | DDGH | St. Lawrence River | ||||||
Mackenzie | DDGH | Mackenzie River |
References
[edit]- ^ a b "The Cost of Canada's Surface Combatants: 2021 Update and Options Analysis". Office of the Parliamentary Budget Officer. 24 February 2021. Archived from the original on 24 February 2021. Retrieved 12 May 2021.
- ^ a b "RCN Canadian Surface Combatant (CSC) Factsheet" (PDF). Royal Canadian Navy. Retrieved 30 June 2024.
- ^ a b c d Gilpin, Bobby (Spring 2024). "Aegis Integration in Canada's Surface Combatant Program" (PDF). Maritime Engineering Journal. 107 (Spring 2024): 13–17. ISSN 0713-0058. Retrieved 1 June 2024.
- ^ "L3Harris to Supply Communications System for Canadian Surface Combatant". Naval News. 31 May 2024. Retrieved 1 June 2024.
- ^ "Lockheed Martin Signs SPY-7 Radar Contract for CSC Frigate". Naval News. 11 November 2020. Retrieved 18 February 2021.
- ^ "The Canadian Surface Combatant SPY-7 Radar Earns Official Government of Canada Designation". Canadian Defence Review. 7 June 2022. Retrieved 18 July 2022.
- ^ "Ultra awarded subcontract to provide TLFAS Variable Depth Sonar for CSC". Naval News. 3 February 2021. Archived from the original on 3 February 2021. Retrieved 3 February 2021.
- ^ "Ultra to provide Hull-Mounted Sonar for Canadian Surface Combatant". Naval News. 18 February 2021. Archived from the original on 18 February 2021. Retrieved 18 February 2021.
- ^ "Future Canadian Surface Combatants". Royal Canadian Navy. Retrieved 20 February 2024.
- ^ Pugliese, David. "Canada commits $200 million to development of next generation of Seasparrow missile". Ottawa Citizen. Archived from the original on 4 February 2019. Retrieved 3 February 2019.
- ^ Scott, Richard (6 November 2020). "Canada approved for SM-2 Block IIIC missile purchase". Janes.com. Archived from the original on 6 November 2020. Retrieved 8 November 2020.
- ^ "Canada Selects Leonardo Naval Gun Systems for the CSC Combat Ships". Naval News. 22 April 2021. Archived from the original on 22 April 2021. Retrieved 23 April 2021.
- ^ "Leonardo: New X-Gun 30 Solution and Lionfish Turret with First Naval Customers". Naval News. 30 April 2024. Retrieved 1 June 2024.
- ^ "New ships for navy, coast guard – National Shipbuilding Procurement Strategy to cost $38.6 billion". CBC News. 13 November 2013. Retrieved 20 March 2014.
- ^ a b c "Construction Begins for Canada's New Warship Fleet – the River Class Destroyers". Department of National Defence. 28 June 2024. Retrieved 28 June 2024.
- ^ "River-class destroyer". www.canada.ca. 15 March 2023. Retrieved 7 July 2024.
- ^ "Canada brushes off outside, fixed-price FREMM frigate offer for Canadian Surface Combatant project". Naval Today. 6 December 2017. Archived from the original on 7 December 2017. Retrieved 12 May 2021.
- ^ Brewster, Murray (19 October 2018). "Lockheed Martin selected as preferred designer for Canada's next generation of warships". CBC News. Archived from the original on 19 October 2018. Retrieved 12 May 2021.
- ^ "Government of Canada delivers on its commitment to the Navy by announcing next steps in fleet procurement" (Press release). Public Services and Procurement Canada. 19 October 2018. Retrieved 12 May 2021.
- ^ Brewster, Murray (28 November 2018). "Frigate design decision faces another delay after latest challenge". CBC News. Archived from the original on 29 November 2018. Retrieved 28 November 2018.
- ^ Brewster, Murray (1 February 2019). "Trade tribunal rejects rival's bid to block warship contract". CBC News. Archived from the original on 2 February 2019. Retrieved 9 October 2020.
- ^ Brewster, Murray (8 February 2019). "Ottawa makes its $60B frigate project official, even as rival's court challenge goes forward". CBC News. Archived from the original on 8 February 2019. Retrieved 17 February 2019.
- ^ "Procurement – Navy: Canadian Surface Combatant". Government of Canada. Archived from the original on 29 October 2020. Retrieved 9 October 2019.
- ^ "Canadian surface combatant". National Defence and the Canadian Armed Forces. 13 March 2013. Archived from the original on 2 October 2013. Retrieved 14 June 2016.
- ^ "Canada first: DND's procurement and industrial strategy [CAN2015D1]". janes.com. 27 May 2015. Archived from the original on 11 August 2016. Retrieved 14 June 2016.
- ^ Noseworthy, Scott. "The Frigate Life Extension Programme". cdnmilitary.ca. Archived from the original on 6 October 2007. Retrieved 12 May 2021.
- ^ "Backgrounder – Halifax-class Modernization (HCM) / Frigate Life Extension (FELEX)". National Defence and the Canadian Armed Forces. 21 August 2013. Archived from the original on 2 August 2016. Retrieved 20 March 2014.
- ^ "Irving leads next generation warship project". Cape Breton Post. The Canadian Press. 21 January 2015. Archived from the original on 22 January 2015. Retrieved 21 January 2015.
- ^ "Canada's biggest-ever military procurement at 'very high risk,' documents suggest". CTV News. 20 September 2015. Retrieved 14 June 2016.
- ^ Pugliese, David (23 February 2016). "Government considers changing course on $26B warship program in hopes vessels will be delivered sooner". National Post. Retrieved 14 June 2016.[dead link ]
- ^ "Future Destroyer – Canadian Surface Combatant". Canadian American Strategic Review. Archived from the original on 20 December 2016. Retrieved 6 September 2013.
- ^ Cudmore, James (20 January 2015). "Irving named prime contractor for Canadian surface combatant warships". CBC News. Retrieved 21 January 2015.
- ^ Ivison, John (21 January 2015). "John Ivison: $26B shock — Canada's largest ever defence procurement handed off in sole-source contract". National Post. Retrieved 21 January 2015.[dead link ]
- ^ a b Cudmore, James (1 December 2015). "Cost to build navy's new warships more than doubles to $30B". CBC News. Retrieved 14 June 2016.
- ^ a b Scott, Richard (26 May 2016). "Rebuilding Canada's navy [CANSEC2016D2]". janes.com. Archived from the original on 1 October 2016. Retrieved 1 October 2016.
- ^ Tutton, Michael (13 June 2016). "Federal government opts for off-the-shelf design to cut costs of new warships". CTV News. The Canadian Press. Archived from the original on 13 June 2016. Retrieved 14 June 2016.
- ^ Nucci, Christopher (November 2020). "The Future Canadian Surface Combatant". U.S. Naval Institute. Archived from the original on 4 November 2020. Retrieved 4 November 2020.
- ^ Williams, Alan (20 October 2020). "Estimated Costs for the Canadian Surface Combatants (CSC)". Esprit de Corps. Retrieved 9 January 2021.
- ^ Brewster, Murray (23 December 2020). "Battle of the budget: DND gears up to defend cost of new warships in the new year". CBC News. Retrieved 9 January 2021.
- ^ Brewster, Murray (27 October 2016). "Cost and Canadian content concerns hover over warship plans". CBC News. Archived from the original on 30 October 2016. Retrieved 29 October 2016.
- ^ Pugliese, David (13 October 2016). "Concerns over Canadian content, BAE's "paper" ship delay bids on new navy warships". Ottawa Citizen. Retrieved 29 October 2016.
- ^ Pugliese, David (17 February 2017). "Bidding on Canadian Surface Combatant program to be delayed, federal government confirms". Ottawa Citizen. Retrieved 22 February 2017.
- ^ Brewster, Murray (11 August 2017). "Impasse over intellectual property is tying up warship bids". CBC News. Retrieved 13 August 2017.
- ^ Brewster, Murray (6 September 2017). "Decision on navy's replacement frigate design pushed to 2018". CBC News. Retrieved 7 September 2017.
- ^ Keddie, Ian (28 September 2017). "Canadian Surface Combatant bid deadline extended to November". janes.com. Archived from the original on 6 December 2017. Retrieved 5 December 2017.
- ^ Pugliese, David (10 November 2017). "Submission of bids delayed again on Canadian Surface Combatant program". Ottawa Citizen. Retrieved 5 December 2017.
- ^ Brewster, Murray (28 November 2017). "British design first to be submitted in Canadian navy's warship contest". CBC News. Retrieved 28 November 2017.
- ^ Brewster, Murray (5 December 2017). "Shipbuilder appeals directly to Sajjan in warship design contest then doesn't deliver formal bid". CBC News. Retrieved 5 December 2017.
- ^ "Canada brushes off outside, fixed-price FREMM frigate offer for Canadian Surface Combatant project". Naval Today. 6 December 2017. Archived from the original on 7 December 2017. Retrieved 14 September 2018.
- ^ a b Pugliese, David (5 December 2017). "Liberals reject warship proposal that companies said would save taxpayers as much as $32B". National Post. Retrieved 6 December 2017.
- ^ Leblanc, Daniel (8 December 2017). "French and Italian governments endorse long-shot bid for 15 new ships for Canada's navy". The Globe and Mail. Retrieved 9 December 2017.
- ^ Pugliese, David (23 November 2017). "Dutch frigate design being offered by Alion for Canadian Surface Combatant program". Ottawa Citizen. Retrieved 28 November 2017.
- ^ Pugliese, David (28 November 2017). "Canadian Surface Combatant team, led by Lockheed Martin Canada, unveiled". Ottawa Citizen. Retrieved 28 November 2017.
- ^ "Navantia team submits proposal for CSC" (Press release). Navantia. 30 November 2017. Archived from the original on 2 December 2017. Retrieved 5 December 2017.
- ^ Tran, Pierre; Kington, Tom & Pugliese, David (6 December 2017). "Bold move backfires as Canada declines Naval Group-Fincantieri frigate offering". defensenews.com. Retrieved 19 February 2021.
- ^ Government of Canada, Public Services and Procurement Canada (3 May 2019). "Canadian surface combatant - Large vessel shipbuilding projects – Shipbuilding projects to equip the Royal Canadian Navy and the Canadian Coast Guard – National Shipbuilding Strategy – Sea – Defence and marine procurement – Buying and Selling – PSPC". www.tpsgc-pwgsc.gc.ca. Retrieved 27 January 2022.
- ^ Withers, Paul (17 February 2021). "Ceremony in Halifax marks 1st navy vessel named for Black Canadian". CBC News. Archived from the original on 17 February 2021. Retrieved 19 February 2021.
- ^ Berthiaume, Lee (2 February 2021). "National Defence grappling with new delay in $60B warship project". CTV News. The Canadian Press. Archived from the original on 2 February 2021. Retrieved 19 February 2021.
- ^ Gunn, Andrea (23 May 2019). "Irving to build two more Arctic patrol ships in Halifax". The Chronicle Herald. Archived from the original on 22 May 2019. Retrieved 19 February 2021.
- ^ Pugliese, David (28 June 2024). "Government to begin construction on new warships despite not knowing the final cost or design". Ottawa Citizen. Retrieved 29 June 2024.
- ^ Staff, Naval News (28 June 2024). "Canada Starts Construction on CSC / River-class Destroyers". Naval News. Retrieved 29 June 2024.