Xianghe Water Conservancy Hub Project
The Xianghe Water Conservancy Hub Project (Chinese: 湘河水利枢纽工程) and its accompanying irrigation project, or Xianghe Reservoir (Chinese: 湘河水库), are situated in Namling County, Shigatse City, within the Tibet Autonomous Region.[1] This project is one of the 172 significant water conservancy initiatives designated by the State Council and constitutes a key element of the 13th Five-Year Plan for the reform and development of water conservancy in Tibet. It commenced in April 2019 and is scheduled for completion in December 2022, with a total investment of RMB 2.71 billion.[2]
This project focuses on irrigation, water supply, and improving the natural environment in the protected area, as well as power generation. The reservoir possesses a total capacity of 113.4 million cubic meters, serves a population exceeding 30,000, and has a multi-year average water supply of 111.8 million cubic meters, with 62.76 million cubic meters allocated for irrigation purposes.[3]
Construction
[edit]Construction of the Xianghe Water Conservancy Hub and Supporting Irrigation District Project began in April 2019, and it finished the water storage safety assessment in June 2022.[4] This laid the groundwork for downgate storage and made it easier to reach the 2022 goal of generating power from the first unit. On October 12, the Tibet Xianghe Water Conservancy Hub and its associated irrigation district project commenced operations with lower gate storage. The construction team completed the crucial task of elevating the stator of the first unit (4#) in November and installed electrical equipment, with the goal of achieving grid-connected power generation by the end of December 2022.[5][6]
The project primarily comprises a barrage, cave spillway, diversion spillway, power diversion system, power plant, and fish passage.[7] This is a substantial water conservancy hub project primarily focused on agriculture and water delivery, with consideration for power generation. On June 30, 2023, the Xianghe Hydroelectric Power Station commenced operations following the completion of the second phase of water storage at the Xianghe Reservoir.[1]
See also
[edit]References
[edit]- ^ a b "国家重点水利工程西藏湘河水利枢纽投产发电". 人民日报-有品质的新闻 (in Chinese). 2023-06-30. Retrieved 2024-12-03.
- ^ "西藏湘河水利枢纽工程湘河水电站正式投入商业运行_西藏自治区人民政府". www.xizang.gov.cn. Retrieved 2024-12-03.
- ^ "西藏湘河水利枢纽及配套灌区工程正式下闸蓄水 计划总投资超27亿元". 手机鳳凰網 (in Chinese). 2022-10-12. Retrieved 2024-12-03.
- ^ "西藏湘河水电站首台机组启动_电力网". 电力网 - 电力行业门户网站 (in Chinese). 2023-01-16. Retrieved 2024-12-03.
- ^ "国家重大水利工程西藏湘河水利枢纽工程投入商业运行". 中国水电三局. 2023-07-03. Retrieved 2024-12-03.
- ^ "西藏湘河水电站正式投入运行". 每经网 (in Chinese). 2023-07-01. Retrieved 2024-12-03.
- ^ "西藏湘河水电站正式投入运行-数智电力-CPEM全国电力设备管理网". 新型电力-CPEM全国电力设备管理网-能源电力门户网站 (in Chinese). 2019-12-20. Retrieved 2024-12-03.