This article was reviewed by member(s) of WikiProject Articles for creation. The project works to allow users to contribute quality articles and media files to the encyclopedia and track their progress as they are developed. To participate, please visit the project page for more information.Articles for creationWikipedia:WikiProject Articles for creationTemplate:WikiProject Articles for creationAfC articles
This article is within the scope of WikiProject Singapore, a collaborative effort to improve the coverage of articles related to Singapore on Wikipedia. If you would like to participate, please visit the project page, where you can join the discussion and see a list of open tasks.SingaporeWikipedia:WikiProject SingaporeTemplate:WikiProject SingaporeSingapore articles
This article is within the scope of WikiProject Law, an attempt at providing a comprehensive, standardised, pan-jurisdictional and up-to-date resource for the legal field and the subjects encompassed by it.LawWikipedia:WikiProject LawTemplate:WikiProject Lawlaw articles
In the "Facts" section I read (I added the [square backets] for emphasis):
Spandeck had [overestimated] the costs required for the project and subsequent payments to sub-contractors, which went over-budget, were not certified by DSTA.
Should this sentence actually read:
Spandeck had [underestimated] the costs required for the project and subsequent payments to sub-contractors, which went over-budget, were not certified by DSTA.
That is, Spandeck's estimate of the costs was too low (an underestimate), the actual costs were higher than expected, and consequently the project went over-budget.