Jump to content

Suburban Rail Loop East

From Wikipedia, the free encyclopedia

SRL East
Suburban Rail Loop map, with SRL East alignment highlighted in green
Overview
StatusUnder construction
OwnerVicTrack (Projected)
LocaleMelbourne, Australia
Stations6[1]
Service
TypeRapid transit line
SystemSuburban Rail Loop
History
Opened2035 (projected)
AnnouncedNovember 2018
Early construction commencedJune 2022
Major construction commenced2023
Technical
Line length26 km (16 mi)

Suburban Rail Loop East (SRL East) is a rapid transit underground rail project currently under construction in Melbourne, Victoria, Australia. It involves constructing a orbital rail line from Cheltenham in the south-eastern suburbs to Box Hill in the eastern suburbs of Melbourne via Clayton, Monash University, Glen Waverley and Burwood. SRL East is being managed by Suburban Rail Loop Authority.[2]

SRL East is the first stage of the stand-alone Suburban Rail Loop system. Construction commenced in 2022 and is expected to open in 2035.

Project history

[edit]

Following the initial announcement of the SRL development in August 2018, the state government formed the Suburban Rail Loop Authority in September 2019, at the same time as confirming the six station precincts for SRL East.[3] In November 2019, the government announced that the loop would be an operationally independent, standalone line using different rail technology from the existing suburban rail network.[4][5] The system would use new, smaller metro rollingstock that is four to five carriages long, allowing shorter platforms.[5][4] The Premier announced an intention to use private investment to help fund the line, but did not indicate whether the line would be driverless.[5]

In 2020, the government committed a further $2.2 billion for initial and early works on the loop, with expressions of interest opened for contractors to deliver these works.[6] Jacinta Allan, who in her role as Minister for Transport Infrastructure had overseen the SRL since its inception, was given the additional role of Minister for the Suburban Rail Loop.

Construction

[edit]
Map of the Melbourne metropolitan rail network showing SRL East.
Map showing the Melbourne metropolitan rail network, with SRL East shown as a dotted line. Early construction began in 2022 on SRL East, the system's first stage and the city's first stand-alone orbital rail line.

On 2 June 2022, early works began on SRL East with major construction expected to commence in 2023, followed by tunnelling works in 2026.[7]

Early works

[edit]

In November 2021, the State Government committed $9.3 billion in funding towards SRL East on top of $2.5 billion previously allocated for planning and early works.[8][9] Engineering firm Laing O'Rourke was awarded the contract to deliver early works, which were set to begin in 2022.[8]

In March 2022, a tender process was opened for two major works packages to deliver the SRL East tunnels.[10] The first is a 16 km (9.9 mi) tunnel contract between Cheltenham and Glen Waverley, the second is from Glen Waverley to Box Hill. The government announced that up to ten tunnel boring machines would be used to dig SRL East.[10]

In May 2022, prior to the 2022 Australian federal election, Labor leader Anthony Albanese pledged $2.2 billion in federal funding for the SRL if his party was elected.[11] Following the party's success at the election, the new Albanese Government allocated the money in its October 2022-3 budget.[12]

In June 2022, construction work began on the project with early works and utility relocations commencing at the Clayton precinct.[7][13][14] Early works in 2023 included the relocation of the tram terminus of Route 109 on Whitehorse Road in order to allow the excavation of the Box Hill SRL station, the preparation of a tunnel boring machine (TBM) launch site at Burwood, and the moving of water, sewerage, electricity and gas services at each station site.[15]

Major construction

[edit]
Construction underway for Suburban Rail Loop East in the Whitehorse Road median at Market Street in Box Hill.

In August 2022, the Victorian Environment Minister Lily D'Ambrosio approved the Environment Effects Statement planning process, meaning the project could proceed to other necessary planning approvals and towards major construction.[16][17] The approval recommended a number of extra actions by the SRLA to minimise impacts to local residents, including replacing open space on the project, limiting construction noise, additional cycling and walking connections, and more support for local businesses.[18]

In August 2023, a preferred bidder was announced for the first package of 16 km (9.9 mi) of SRL East tunnels between Cheltenham and Glen Waverley.[19][20] The Suburban Connect consortium consisted of the Australian construction firm CPB Contractors, Italian civil engineering company Ghella and the Spanish construction company Acciona.[20] The arrival of TBMs and the commencement of tunnelling is expected by 2026.[19] A second contract for the remaining 10 km (6.2 mi) of tunnelling was awarded in July 2024 to Consortium Terra Verde, made up of Italian construction firm WeBuild, Korean engineering company GS Engineering and Construction, and French construction company Bouygues Construction.[20][21] At the same time the state government released a discussion paper for community consultation on precinct plans for the six stations on SRL East.[22][23]

Project design

[edit]
The growth suburb of Box Hill is planned to become an important interchange on the SRL, with shops on the right set to be acquired for construction of the loop.

The 2021 Environmental Effects Statement outlined the key design elements of the project, saying the SRL would provide a high-frequency metro service with fully automated, four-car trains.[24] The trains would be approximately 93 metres (305 ft 1 in) long, 3.2 metres (10 ft 6 in) wide and 4 metres (13 ft 1 in) high, capable of an operating line speed of 100 kilometres per hour (62 mph), running on an alternating current system.[24] This design differs from Melbourne's existing heavy rail system, which uses longer, heavier rolling-stock on a direct current power system.

The project has two initial stages, SRL East and SRL North, which will consist of 13 stations and twin tunnels running 60 km (37 mi) from Cheltenham in the city's south-east to Melbourne Airport in the north-west. The design of a future western stage from the airport to Werribee was not detailed in the project's 2021 business case.[25] SRL East will be the first section to be built, with planning and construction to move immediately onto SRL North.[25] SRL East from Cheltenham to Box Hill is planned to be open by 2035, with SRL North to then open in two stages, the first from Box Hill to Reservoir, and the second from Reservoir to Melbourne Airport.[25]

Stations will be two level, with large concourses and escalators, with interchanges to connecting train and bus services.[24] Stations are also set to include bicycle parking, over-site developments and broader precinct redevelopments.[24] A train stabling and maintenance facility is planned to be built in Heatherton on a former landfill site to accommodate the train fleet for both SRL East and North.[26][25]

Under state legislation passed in 2021, the Suburban Rail Loop Authority was given planning powers over the area 1.6 km (0.99 mi) from each SRL station.[27][28][29] This grants the authority the power to bypass local councils and rezone or develop land in the station precincts, allowing for increased housing and job density, a move that prompted criticism from councils.[29]

Route

[edit]
SRL East
SRL North Future Extension
Box Hill
Burwood
Glen Waverley
Monash
Clayton
Heatherton Train Stabling Site
Southland


SRL East will run between Southland station on the Frankston line and Box Hill station on the Belgrave and Lilydale lines and will be entirely underground along a new alignment.[30] From south to north, SRL East would also include stations at Clayton on the Dandenong rail corridor; Monash University's Clayton campus; Glen Waverley station, the terminus of Glen Waverley line; and Burwood, near the main campus of Deakin University.[31] Government press releases identify Clayton as the location of a "super-hub", allowing interchange between SRL services, frequent Dandenong corridor services, and regional Gippsland line services.[32]

A train stabling and maintenance depot will be built between Southland and Clayton stations in the suburb of Heatherton at the current Kingston Road landfill site.[33] The rail line will briefly surface to enter the depot, which will initially house 13 trains but will be large enough to accommodate 30.[33]

Planned extension

[edit]

The Suburban Rail Loop North project is planned to extend the line to through the northern suburbs of Melbourne and on to Melbourne Airport with twin tunnels from just north of Box Hill station via Doncaster and under La Trobe University towards Heidelberg, Reservoir, Fawkner and Broadmeadows, before terminating at Melbourne Airport. As of October 2024, only preliminary planning has been done on the project, with construction not expected to commence until the 2030s.

Criticism

[edit]

See also

[edit]

References

[edit]
  1. ^ "SRL East". Suburban Rail Loop. Victoria's Big Build. 2 October 2024. Retrieved 24 October 2024.
  2. ^ "SRL East". Suburban Rail Loop. Victoria's Big Build. 2 October 2024. Retrieved 24 October 2024.
  3. ^ Preiss, Benjamin (3 September 2019). "Suburban rail line loops in three big interchanges as route firms up". The Age. Archived from the original on 3 September 2019. Retrieved 3 September 2019.
  4. ^ a b "New Dedicated Trains For Standalone Suburban Rail Loop". Premier of Victoria. 24 November 2019. Archived from the original on 15 November 2022. Retrieved 28 November 2019.
  5. ^ a b c Precel, Nicole (24 November 2019). "Daniel Andrews eyes private investors to fund Suburban Rail Link". The Age. Archived from the original on 28 November 2019. Retrieved 28 November 2019.
  6. ^ Premier of Victoria (16 November 2020). "Works To Kick Off On The Suburban Rail Loop". Archived from the original on 14 November 2022. Retrieved 13 May 2022.
  7. ^ a b "Works Start Today On Victoria's Suburban Rail Loop | Premier of Victoria". www.premier.vic.gov.au. Archived from the original on 1 June 2022. Retrieved 2 June 2022.
  8. ^ a b "VIC Government provides $9.3b funding for Suburban Rail Loop works". Infrastructure Magazine. 26 November 2021. Archived from the original on 27 June 2022. Retrieved 13 May 2022.
  9. ^ "Massive Funding Boost Means SRL Build Starts Next Year | Premier of Victoria". www.premier.vic.gov.au. Archived from the original on 17 March 2022. Retrieved 13 May 2022.
  10. ^ a b "New Tunnelling Packages And Community Fund For SRL | Premier of Victoria". www.premier.vic.gov.au. Archived from the original on 28 March 2022. Retrieved 13 May 2022.
  11. ^ "What to know about Anthony Albanese's $2.2bn pledge for Victoria's Suburban Rail Loop". The Guardian. 10 May 2022. Archived from the original on 29 November 2022. Retrieved 29 November 2022.
  12. ^ Gordon, Josh (25 October 2022). "Infrastructure cuts loom as Suburban Rail Loop grant evens up Victoria's ledger". The Sydney Morning Herald. Archived from the original on 29 November 2022. Retrieved 29 November 2022.
  13. ^ Build, Victoria’s Big (2 June 2022). "Construction starts today on SRL East". Victoria’s Big Build. Archived from the original on 12 August 2022. Retrieved 5 June 2022.
  14. ^ "Construction begins on Victoria's Suburban Rail Loop". Infrastructure Magazine. 2 June 2022. Archived from the original on 2 June 2022. Retrieved 5 June 2022.
  15. ^ Build, Victoria’s Big (29 August 2023). "SRL construction blitz with works underway in Box Hill and Burwood". Victoria’s Big Build. Retrieved 31 August 2023.
  16. ^ "Suburban Rail Loop gets green light from environment minister". Ground Engineering (GE). 17 August 2022. Archived from the original on 17 August 2022. Retrieved 17 August 2022.
  17. ^ "Suburban Rail Loop East project". Victoria Department of Environment, Land, Water and Planning. 6 June 2024. Archived from the original on 17 August 2022. Retrieved 22 July 2024.
  18. ^ Build, Victoria’s Big (11 August 2022). "Green light for Suburban Rail Loop East". Victoria’s Big Build. Archived from the original on 17 August 2022. Retrieved 17 August 2022.
  19. ^ a b Build, Victoria’s Big (29 August 2023). "Preferred bidder announced for SRL East tunnelling contract". Victoria’s Big Build. Retrieved 31 August 2023.
  20. ^ a b c Duboudin, Tony (30 August 2023). "Preferred bidder named for Melbourne Suburban Rail Loop tunnelling". International Railway Journal. Retrieved 31 August 2023.
  21. ^ Victoria’s Big Build (8 July 2024). "Preferred bidder announced for second tunnelling contract". Victoria’s Big Build. Retrieved 8 July 2024.
  22. ^ Chan, Ray (29 August 2023). "TBMs on the way for SRL". Rail Express. Retrieved 31 August 2023.
  23. ^ Build, Victoria’s Big (29 August 2023). "Planning for the future of SRL neighbourhoods". Victoria’s Big Build. Retrieved 31 August 2023.
  24. ^ a b c d Suburban Rail Loop Authority (November 2021). "Suburban Rail Loop Environmental Effects Statement". srleastees.vic.gov.au. Archived from the original on 18 May 2022. Retrieved 13 May 2022.
  25. ^ a b c d "Business and Investment Case". Suburban Rail Loop. Victorian Government. Archived from the original on 6 September 2021. Retrieved 6 September 2021.
  26. ^ Build, Victoria’s Big (16 November 2021). "SRL East: Train stabling facility fact sheet". Victoria’s Big Build. Archived from the original on 17 August 2022. Retrieved 17 August 2022.
  27. ^ "Major planning changes under new Suburban Rail Loop law". www.holdingredlich.com. Archived from the original on 8 December 2021. Retrieved 13 May 2022.
  28. ^ Waters, Cara (19 November 2021). "Streamlined or autocratic? Minister's planning powers gradually grow". The Age. Archived from the original on 13 May 2022. Retrieved 13 May 2022.
  29. ^ a b Jacks, Timna (28 September 2021). "'Unconscionable': Councils fear government rail loop land grab". The Age. Archived from the original on 13 May 2022. Retrieved 13 May 2022.
  30. ^ Willingham, Richard. "Melbourne's new Suburban Rail Loop to start at Cheltenham, $2.2 billion announced for early works". Archived from the original on 23 November 2020. Retrieved 24 November 2020.
  31. ^ Development Victoria 2018, p. 26.
  32. ^ "Rail loop set to connect Gippsland". Archived from the original on 4 November 2018. Retrieved 3 November 2018.
  33. ^ a b Build, Victoria’s Big (30 October 2022). "Train stabling facility". Victoria’s Big Build. Archived from the original on 25 February 2023. Retrieved 25 February 2023.
[edit]