SLTEC Calaca Power Station
SLTEC Calaca Power Station | |
---|---|
Country | Philippines |
Location | Calaca, Batangas |
Coordinates | 13°55′08.7″N 120°49′36.7″E / 13.919083°N 120.826861°E |
Status | Operational |
Commission date | 2015 |
Owner | South Luzon Thermal Corp. |
Operator | South Luzon Thermal Corp. |
Thermal power station | |
Primary fuel | Coal |
Power generation | |
Nameplate capacity | 270 MW |
The SLTEC Calaca Power Station is a 270-MW coal-fired power station in Calaca, Batangas, Philippines.
History
[edit]The power plant was a project of South Luzon Thermal Corp. (SLTEC), a company jointly owned by Trans-Asia Oil and Energy Development Corp. of the PHINMA Group and AC Energy (ACEN) of the Ayala Group.[1]
The first unit of SLTEC's coal power station in Calaca, Batangas became operational on April 24, 2015[1] and the second one on February 25, 2016.[2]
By 2021, ACEN would acquire full stakes on SLTEC, acquiring the shares of Axia Power Holdings Philippines of Marubeni.[3] ACEN would completely divest it shares on SLTEC in 2022, marking its full transition to renewable energy.[4] This marks the commencement of the plant's early retirement by 2030.[5]
References
[edit]- ^ a b "SLTEC doubles capacity of Batangas coal plant". The Philippine Star. February 25, 2016. Retrieved December 8, 2023.
- ^ Lectura, Lenie (February 25, 2016). "SLTEC's second coal plant in Batangas now operational". BusinessMirror. Retrieved December 8, 2023.
- ^ "AC Energy takes full control over Batangas power plant". BusinessWorld. September 30, 2021. Retrieved December 8, 2023.
- ^ Jose, Ashley Erika (November 8, 2022). "ACEN fully divests from its coal power plant unit". BusinessWorld. Retrieved December 8, 2023.