Renewable energy in the Philippines
In 2013, renewable energy provided 26.44% of the total electricity in the Philippines and 19,903 gigawatt-hours (GWh) of electrical energy out of a total demand of 75,266 gigawatt-hours.[1] The Philippines is a net importer of fossil fuels. For the sake of energy security, there is momentum to develop renewable energy sources. The types available include hydropower, geothermal power, wind power, solar power and biomass power. The government of the Philippines has legislated a number of policies in order to increase the use of renewable energy by the country.
The government has committed to raising to 50% the contribution of renewables of its total electricity generating capacity,[2] with 15.3 gigawatts (GW) by 2030.[3] The move would help the country in its commitment to reduce its carbon emissions by 75% by 2030.[4]
Background
[edit]There is momentum to decrease reliance on fossil fuels due to the negative effects such as pollution, climate change and financial uncertainty because of fluctuating fuel prices.[5][6] Legislation passed by the Congress of the Philippines to support the use of renewable energy include the Electric Power Industry Reform Act (2001);[7] the Biofuels Act (2006), which encourages the use of biomass fuels;[8] the Renewable Energy Act (2008);[9][10] and the Climate Change Act (2009), which provides a legal basis for addressing climate change through sustainable development.[11]
Renewable energy implementation is important to the Philippines for several reasons.[12] The geographic characteristics of the country make it vulnerable to the adverse effects of climate change. Rising sea levels are a threat because the Philippines is an archipelago with many cities located in coastal areas. As the coastline recedes due to rising seas, coastal cities become vulnerable to flooding. Climate change has also been linked to changing weather patterns and extreme weather events.[13]
Reliance on fossil fuels is detrimental to the energy security of the Philippines.[14] The Philippines is a net importer of fossil fuels. In 2012, the Philippines imported 20 million tons of coal. Eight million tons were produced domestically.[15] In 2010, the Philippines imported 54 million barrels of oil and produced 33,000 barrels.[16] Given this dependence on imported coal and oil, the Philippines is vulnerable to price fluctuations and supply constraints.[6]
The Philippine Department of Energy wrote:
“The harnessing and utilization of renewable energy comprises a critical component of the government's strategy to provide energy supply for the country. This is evident in the power sector where increased generation from geothermal and hydro resources has lessened the country's dependency on imported and polluting fuels. In the government's rural electrification efforts, on the other hand, renewable energy sources such as solar, micro-hydro, wind and biomass resources are seeing wide-scale use.”[17]
Sources
[edit]The Philippines utilizes renewable energy sources including hydropower, geothermal and solar energy, wind power and biomass resources.[citation needed] In 2013, these sources contributed 19,903 GWh of electrical energy, representing 26.44 percent of the country's electricity needs.[1] Among the renewable energy sources available in the country, geothermal shows to be the cheapest and most (economically) attractive energy source followed by wind, hydropower, and lastly, solar PV.[18]
Year | Geothermal | Hydropower | Biomass | Solar | Wind | Total
renewables |
Total
electricity |
Renewables % of
electricity production |
---|---|---|---|---|---|---|---|---|
2003 | 9,822 | 7,870 | 0 | 0 | 0 | 17,692 | 52,941 | 33.42% |
2004 | 10,282 | 8,593 | 0 | 0 | 0 | 18,875 | 55,957 | 33.73% |
2005 | 9,902 | 8,387 | 0 | 2 | 17 | 18,308 | 56,568 | 32.36% |
2006 | 10,465 | 9,939 | 0 | 1 | 53 | 20,459 | 56,784 | 36.03% |
2007 | 10,215 | 8,563 | 0 | 1 | 58 | 18,836 | 59,612 | 31.60% |
2008 | 10,723 | 9,834 | 0 | 1 | 61 | 20,620 | 60,821 | 33.90% |
2009 | 10,324 | 9,834 | 14 | 1 | 64 | 20,237 | 61,934 | 32.68% |
2010 | 9,929 | 9,788 | 27 | 1 | 62 | 19,807 | 67,743 | 29.24% |
2011 | 9,942 | 7,803 | 115 | 1 | 88 | 17,950 | 69,176 | 25.95% |
2012 | 10,250 | 10,252 | 183 | 1 | 75 | 20,761 | 72,922 | 28.47% |
2013 | 9,605 | 10,019 | 212 | 1 | 66 | 19,903 | 75,266 | 26.44% |
2014 | 10,308 | 9,137 | 196 | 17 | 152 | 19,809 | 77,261 | 25.64% |
2015 | 11,044 | 8,665 | 367 | 139 | 748 | 20,963 | 82,413 | 25.44% |
2016 | 11,070 | 8,111 | 726 | 1,097 | 975 | 21,979 | 90,798 | 24.21% |
2017 | 10,270 | 9,611 | 1,013 | 1,201 | 1,094 | 23,189 | 94,370 | 24.57% |
2018 | 10,435 | 9,384 | 1,105 | 1,249 | 1,153 | 23,326 | 99,765 | 23.38% |
Hydroelectric plants
[edit]Hydropower is one of the main sources of renewable energy in the Philippines. There are hydroelectric plants of both the conventional dam and run-of-the-river types in the country. Of twenty-nine hydroelectric plants, fourteen are conventional dam and fifteen are run-of-the-river systems.[20][21][22] Hydropower accounts for 11.8% of the energy generation and 17-18% of installed capacity in the Philippines.[23][24][25]
Many areas of the Philippines are suitable for hydroelectricity production.[26] However, hydroelectricity production in the Philippines can cause upstream and downstream flooding during monsoonal weather and when excess water is released from dams.[26][27] Hydropower integration also has the potential to disturb pre-existing natural ecosystems and cultures as well as cause land dispossession and community resettlement.[24][28] The methods of using geographic information system (GIS) and remote sensing (RS) to determine suitable sites for constructing hydroelectric plants do not tend to incorporate social or environmental considerations.[29] In response to the construction of large scale hydroelectric infrastructure, opposition movements have arisen. Anti-dam organizations and protests may advocate for indigenous peoples, environmental conservation, anti-capitalism, or anti-imperialism.[25] Vocal environmental human rights defenders have been red-tagged by the government or extrajudicially killed by the military or police.[25][28][30] The rights, concerns, and political agency of indigenous peoples trying to protect their villages and sacred sites from being submerged have often been disregarded due to urban-centric economic development.[25][28]
Incorporating small scale plants, especially micro-hydroelectric plants that have a capacity of less than 0.1 MW (100 kW), may mitigate adverse side effects and be a cost-effective way to bring electricity to rural and off-the-grid communities.[24] Isolated mountain communities have seen improvements in education, community engagement, and economy due to improved lighting provided by micro-hydropower.[31]
2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
Hydropower Output (GWh) | 8,593 | 8,387 | 9,939 | 8,563 | 9,834 | 9,788 | 7,803 | 9,698 | 10,252 | 10,019 | 9,137 | 8,665 |
Percentage Change | (2.40%) | 18.50% | (13.84%) | 14.84% | (0.47%) | (20.28%) | 24.29% | 5.71% | (2,27%) | (8.80%) | (5.45%) |
Facility Name[32][33][34] | Type | Installed Capacity (MW) | Location | Owner | Year Commissioned |
---|---|---|---|---|---|
San Roque | Dam | 411.0 | Pangasinan | San Roque Power Corporation | 2003 |
HEDCOR | Run-of-River | 33.8 | Benguet | HEDCOR | 1993 |
Kalayaan PSPP | Dam | 739.2 | Laguna | CBK Power Company Ltd. | 1998/2004 |
Magat | Run-of-River | 360.0 | Isabela | Aboitiz Power | 1983 |
Caliraya | Dam | 35.0 | Laguna | CBK Power Company Ltd. | 1942/1947/1950 |
Botocan | Run-of-River | 22.8 | Laguna | CBK Power Company Ltd. | 1967/1986 |
Angat | Dam | 246.0 | Bulacan | PSALM | 1967/1986 |
Pantabangan-Masiway | Dam | 132.0 | Nueva Ecija | First Gen Hydro Power Corp. | 1977/1981 |
Ambuklao | Dam | 105.0 | Benguet | Aboitiz Power | 1957 |
Binga | Dam | 132.0 | Benguet | Aboitiz Power | 1960 |
Bakun | Run-of-River | 70.0 | Ilocos Sur | Luzon Hydro Corp. | 2000/2001 |
Casecnan | Dam | 165.0 | Nueva Ecija | CE Casecnan Water & Energy Co. | 2002 |
Sabangan | Run-of-River | 13.2 | Mt. Province | HEDCOR | 2015 |
NIA-Baligtan | Run-of-River | 6.0 | Isabela | NIA | 1987 |
JANOPOL | Run-of-River | 5.2 | Bohol | BOHECO I | 1992 |
AGUS 1 | Dam | 80.0 | Lanao del Sur | PSALM | 1992 |
AGUS 2 | Dam | 180.0 | Lanao del Sur | PSALM | 1992 |
AGUS 4 | Dam | 55.0 | Lanao del Norte | PSALM | 1985 |
AGUS 5 | Dam | 200.0 | Lanao del Norte | PSALM | 1985 |
AGUS 6 | Dam | 54.0 | Lanao del Norte | PSALM | 1953/1971 |
AGUS 7 | Dam | 255.0 | Lanao del Norte | PSALM | 1983 |
Pulangi IV | Run-of-River | 232.0 | Bukidnon | PSALM | 1985/1986 |
Sibulan HEP | Run-of-River | 42.6 | Davao del Sur | HEDCOR | 2010 |
Agusan | Run-of-River | 1.6 | Bukidnon | FG Bukidnon Power Corp. | 1957 |
Bubunawan | Run-of-River | 7.0 | Bukidnon | BPC Inc. | 2001 |
Cabulig HEP | Run-of-River | 9.2 | Misamis Oriental | Mindanao Energy Systems | 2012 |
Talomo HEP | Run-of-River | 4.5 | Davao del Sur | HEDCOR | 1998 |
Tudaya 1 | Run-of-River | 6.6 | Davao del Sur | HEDCOR | 2014 |
Tudaya 2 | Run-of-River | 7.0 | Davao del Sur | HEDCOR | 2014 |
Geothermal power
[edit]In the Philippines, geothermal energy is used to generate electricity. Two types of technologies are used in the Philippines. These are firstly, the higher temperature flash steam method and secondly, the lower temperature binary cycle method.[35] In the Philippines, the first is the more common. The second is used only at the MAKBAN plant. Geothermal plants are suitable for areas with low winds, such as Mindanao, and areas that have rainy weather, such as Batanes. Geothermal energy production can result in the release of toxic substances such as mercury, hydrogen sulfide, arsenic and selenium.[36] In 2014, at a geothermal plant in Biliran, eight plant workers were hospitalized with hydrogen sulphide poisoning.[37]
2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
Geothermal Power Output (GWh) | 10,282 | 9,902 | 10,465 | 10,215 | 10,723 | 10,324 | 9,929 | 9,942 | 10,250 | 9,605 | 10,308 | 11,044 |
Percentage Change | (3.70%) | 5.69% | 2.39% | 4.97% | (3.72%) | (3.83%) | (0.13%) | 3.10% | (6.29%) | 7.32% | 7.14% |
Facility Name[32][33][34] | Type | Installed Capacity (MW) | Location | Owner | Year Commissioned |
---|---|---|---|---|---|
MAKBAN | Flash/Binary | 442.8 | Laguna | AP Renewable Inc. | 1979 |
BACMAN | Flash | 130.0 | Sorsogon | Bac-Man Geothermal Inc. | 1993 |
Tiwi | Flash | 234.0 | Albay | AP Renewable Inc. | 1979 |
MANITO-Lowland | Flash | 1.5 | Albay | Bac-Man Geothermal Inc. | No date |
MAIBARARA | Flash | 20.0 | Batangas | Maibarara Geothermal Inc. | 2014 |
Palinpinon GPP | Flash | 192.5 | Negros Oriental | Green Core Energy | 1983 |
Leyte | Flash | 112.5 | Leyte | Green Core Energy | 1983 |
Unified Leyte | Flash | 610.2 | Leyte | Energy Development Corp. | 1996/1997 |
Nasulo GPP | Flash | 50.0 | Negros Occidental | Energy Development Corp. | 2014 |
Mt. Apo | Flash | 103.0 | North Cotabato | Energy Development Corp. | 1996 |
Solar power
[edit]In 2015, three solar farms were constructed in the Philippines. The Philippines receives over 7kWh per square meter per day during its peak month of April and lowest at 3kWH per square meter per day during its off-peak month of December as observed by Schadow1 Expeditions in 33 cities of the country.[38] Given the country's high solar potential, the solar energy's contribution to the energy mix is expected to increase from the current (2019) 1.2% of 23GW to at least 3.5% of the 43GW total capacity by 2040.[39]
Facility Name[32][33][34] | Type | Installed Capacity (MW) | Location | Owner | Year Commissioned |
---|---|---|---|---|---|
Tarlac-2 | Photovoltaic | 20 | Tarlac, Tarlac | PetroSolar Corp. | 2019 |
Tarlac-1 | Photovoltaic | 50 | Tarlac, Tarlac | PetroSolar Corp. | 2016 |
Majestic | Photovoltaic | 41.3 | Cavite | Majestic Power Corp. | 2015 |
Pampanga Solar | Photovoltaic | 10.0 | Mexico, Pampanga | Raslag Corp. | 2015 |
Burgos Solar | Photovoltaic | 4.0 | Burgos, Ilocos Norte | Solar Philippines | 2015 |
CEPALCO Solar PV | Photovoltaic | 1.0 | Cagayan de Oro, Misamis Oriental | CEPALCO | 2004 |
Valenzuela - Isla | Photovoltaic | 8.6 | Valenzuela, Metro Manila | Valenzuela Solar Energy Inc. | 2015 |
Valenzuela - Tagalag | Photovoltaic | 20.69 | Valenzuela, Metro Manila | Eco-Park Energy of Valenzuela Corporation | 2019 |
2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | |
---|---|---|---|---|---|---|---|---|---|---|---|
Solar, wind, and biomass output (GWh) | 19 | 55 | 59 | 63 | 79 | 90 | 205 | 259 | 279 | 364 | 1,254 |
Percentage change | 189.47% | 7.27% | 6.78% | 25.40% | 13.92% | 127.78% | 26.34% | 7.72% | 30.66% | 244.50% |
Wind power
[edit]All wind power sites in the Philippines are on-shore facilities. Some, such as Ilocos Norte, Pililla Wind Farm in Rizal and Bangui Wind Farm are tourist destinations.[40][41]
On March 13, 2024, Cheloy Garafil announced that German wind and solar farms developer wpd GmbH, per CEO Björn Nullmeyer, committed P392.4B investment for PH renewable energy. “The wpd GmbH plans to invest PHP392.4 billion in the Philippines to set up offshore wind farms in Cavite, Negros Occidental, and Guimaras, the biggest undertaking registered with the Board of Investments (BOI) in February last year,” she explained. “The President met the wpd GmbH officials in Berlin to discuss status updates on the BOI-registered OSW (offshore wind) projects Cavite and Negros (1 & 2) Projects with a combined capacity of 3,260 MW (megawatts) valued at PHP400 billion,” she stressed.[42]
Facility Name[32][33][34] | Type | Installed Capacity (MW) | Location | Owner | Year Commissioned |
---|---|---|---|---|---|
Bangui Wind Farm Power Phase 1 and 2 | On-Shore | 33.0 | Ilocos Norte | North Wind Power Development Corp. | 2005 |
Bangui Wind Farm Power Phase 3 | On-Shore | 18.9 | Ilocos Norte | North Wind Power Development Corp. | 2014 |
Burgos Wind Farm | On-Shore | 150.0 | Ilocos Norte | EDC | 2014 |
Carispisan Wind | On-Shore | 81.0 | Ilocos Norte | North UPC | 2014 |
Pililla Wind Farm | On-Shore | 54.0 | Rizal | Alternegy Philippine Holdings Corp. | 2015 |
TAREC | On-Shore | 54.0 | Guimaras | TAREC | 2014 |
NABAS Wind Phase 1 | On-Shore | 36.0 | Aklan | PWEI | 2015 |
Biomass power
[edit]Biomass energy refers to energy derived from plant and animal sources.[43] Biomass resources are abundant in the Philippines due to its large agricultural industry. Bagasse, rice husks, and coconut husks are used to generate power.[44] The Philippines also uses biogas from landfill as a biomass energy source. The availability of biomass can be affected by events such as drought.[45]|
Facility Name[32][33][34] | Type | Installed Capacity (MW) | Location | Owner | Year Commissioned |
---|---|---|---|---|---|
Green Future | Bagasse | 19.8 | Isabela | Green Future Innovation Inc. | 2014 |
5JC Power | Rice Husk | 12.0 | Nueva Ecija | I Power Corp. | 2015 |
Montalban LFG | Landfill Gas | 9.3 | Rizal | Montalban Methane Power Corp. | 2009 |
Laguna LFG | Landfill Gas | 4.2 | Laguna | Bacavalley Energy Inc. | 2011 |
Lucky PPH | Bagasse | 4.0 | Isabela | Lucky PPH International Inc. | 2008 |
Pangea | Landfill Gas | 1.2 | Metro Manila | Pangea Green Energy Phil Inc. | 2013 |
Legislation
[edit]The Philippine government has passed four laws that seek to improve the state of renewable energy. These are the Electric Power Industry Reform Act of 2001 (RA 9136); the Biofuel Act of 2006 (RA 9367); the Renewable Energy Act of 2008 (RA 9513); and the Climate Change Act of 2009 (RA 9729).
The Electric Power Industry Reform Act (2001) (EPIRA) promotes the use of renewable energy particularly through private sector investment.[7] However, after a decade of EPIRA's enactment, advocacy groups and lawmakers said the law only strengthened monopolies and caused electricity rates to double.[46][47][48][49]
The Biofuels Act (2006) documents state policy to reduce the Philippines' dependence on imported fossil fuels. It encourages investment in biofuels through incentives including reduced tax on local or imported biofuels; and bank loans for Filipino citizens engaged in biofuel production. The law resulted in the formation of the National Biofuel Board (NBB).[8]
The Renewable Energy Act (2008) legislates state policy to accelerate the development and use of renewable energy resources.[10] Under this act (section 6), mandated a minimum percentage of generation of electricity from renewable sources (a renewable portfolio standard (RPS)). Also under this act (section 7), a feed-In tariff system was implemented for electricity produced from renewable sources, giving producers the security of long term fixed prices.[50] Electricity utilities make net metering agreements with qualified end-users of renewable energy systems. A minimum percentage of electricity from renewable sources for the off-grid missionary electrification system was also mandated.
Under the Renewable Energy Act (2008), incentives are available to developers of renewable energy. These incentives include an income tax holiday for the first seven years of the entity's commercial operations; duty-free importation and special realty tax rates on renewable energy machinery, equipment and materials within the first ten years; net operating loss carry-over; zero percent Value-Added Tax (VAT) rate for the sale of fuel or power generated from renewable sources of energy; and Tax Credit on domestic capital equipment and services.
The Climate Change Act (2009) legislated state policy to incorporate a gender-sensitive, pro-children and pro-poor perspective in all climate change and renewable energy efforts.[11]
Feed-in tariff program statistics
[edit]Resource | For Nomination / Conversion | With Certificate of Confirmation of Commerciality | With Certificate of Endorsement to ERC | |||
---|---|---|---|---|---|---|
No. of Projects | Capacity (MW) | No. of Projects | Capacity (MW) | No. of Projects | Capacity (MW) | |
Hydro | – | – | 66 | 610.93 | 4 | 26.60 |
Wind | 7 | 1,023.55 | 5 | 431.00 | 6 | 393.90 |
Solar | 18 | 681.30 | 30 | 892.54 | 6 | 131.90 |
Biomass | – | – | 4 | 24.37 | 11 | 94.25 |
TOTAL | 25 | 1704.85 | 105 | 1,958.84 | 27 | 646.65 |
RE Technology | Proposed FiT ($/kWh)* | Approved FiT ($/kwh)* | Degression Rate |
---|---|---|---|
Solar | 0.407 | 0.220 | 6% after 1 year from effectivity of FiT |
Wind | 0.235 | 0.193 | 0.5% after 2 years from effectivity of FiT |
Biomass | 0.159 | 0.150 | 0.5% after 2 years from effectivity of FiT |
Run-of-River Hydro | 0.139 | 0.134 | 0.5% after 2 years from effectivity of FiT |
*Based on US$1.00 : PHP 44.00 |
Private sector involvement
[edit]The Renewable Energy Act (2008) encourages the involvement of the private sector in renewable energy production through fiscal and non-fiscal incentives.[52]
Fiscal incentives include tax reductions, as well as funding assistance from both government and third parties. A number of international organizations have expressed willingness to aid Philippine businesses in developing local renewable energy infrastructure including German Technical Cooperation (GTZ), United States Agency for International Development (USAID), Asian Development Bank (ADB), United Nations Development Programme (UNDP), and Japan International Cooperation Agency (JICA).[53] Impediments to private sector investment include high transaction costs; social engineering costs; lack of suitable local technology; and caps on electricity prices made by the Energy Regulatory Commission.[54][52]
Required Documents issued by the National Government | Required Documents issued by the Local Government Units |
---|---|
|
|
Renewable energy Technology[52] | Issued FIT rate (per kWh) | Proposed rate (per kWh) |
---|---|---|
Solar | Php 9.68 | Php 17.95 |
Wind | Php 8.53 | Php 10.37 |
Biomass | Php 6.63 | Php 7.00 |
Hydropower | Php 5.90 | Php 6.15 |
Public-private partnership
[edit]Up until June 2015, the Department of Energy (DOE) had awarded 646 service contracts as Public-private partnerships to private sector entities under the Renewable Energy Law with installed capacity of 2,760.52 MW.[55]
Resources | Awarded Projects | Installed Capacity | Potential Capacity |
---|---|---|---|
Geothermal | 42 | 1,896.19 | 750.00 |
Hydro | 407 | 136.73 | 7,884.54 |
Wind | 51 | 426.90 | 1,168.00 |
Solar | 93 | 108.90 | 2,206.51 |
Biomass | 45 | 191.80 | 357.00 |
Ocean energy | 8 | – | 31.00 |
TOTAL | 646 | 2,760.52 | 12,397.05 |
Instances of private sector projects include:
Island Group | Resource | Project Name | Project Proponent |
---|---|---|---|
Luzon[56] | Hydropower | Kapangan | Cordillera Hydro Electric Power Corporation |
Bulanao | DPJ Engineers and Consultants | ||
Prismc | PNOC-Renewables Corporation | ||
Magat A | Isabela Electric Cooperative, Inc. | ||
Magat B | Isabela Electric Cooperative, Inc. | ||
Tubao | Tubao Mini-Hydro Electric Corporation | ||
Catuiran* | Sta. Clara Power Corp. | ||
Inabasan* | Ormin Power, Inc. | ||
Solar | San Rafael Solar Power Plant | SPARC Solar Powered AgriRural Communities Corporation | |
Morong Solar Power Plant | SPARC Solar Powered AgriRural Communities Corporation | ||
Cabanatuan Solar Power Project | First Cabanatuan Renewable Ventures, Inc. | ||
Palauig Solar Power Plant | SPARC Solar Powered AgriRural Communities Corporation | ||
Currimao Solar Photovoltaic Power Project | Mirae Asia energy Corporation | ||
Macabud Solar Photovoltaic Power Project | ATN Philippines Solar energy Group, Inc. | ||
Sta. Rita Solar Power Project | Jobin-Sqm Inc. | ||
YH Green | YH Green | ||
Tarlac Solar Power Project | PetroSolar Corporation | ||
Calatagan Solar Power Project Phase I | Solar Philippines Calatagan Corporation | ||
Geothermal | Bacman 3 (Tanawon) Geothermal Project | energy Development Corporation | |
Maibarara 2 Geothermal Project | Maibarara Geothermal Inc. | ||
Biomass | 2 MW ACNPC WTE Biomass Power Plant Project | Asian Carbon Neutral Power Corporation | |
12 MW Biomass Power Plant Project | Green Innovations for Tomorrow Corporation | ||
5 MW Bicol Biomass energy Corporation | Bicol Biomass energy Corporation | ||
8.8 MW Biogas Power Plant Project | AseaGas Corporation | ||
24 MW SJCiPower Rice Husk-Fired Biomass power Plant Project (Phase 1 – 12MW Phase 2 – 12 MW) | San Jose City I Power Corporation | ||
70 kW Biomass Gasification Power Plant Project* | PowerSource Philippines, Inc. | ||
Visayas[57] | Geothermal | Biliran Geothermal Plant Project | Biliran Geothermal Incorporated |
Hydropower | Villasiga HEP | Sunwest Water & Electric Co., Inc. | |
Igbulo (Bais) Hydroelectric Power Project | Century Peak energy Corporation | ||
Cantakoy | Quadriver energy Corp. | ||
Amlan HEPP | Natural Power Sources Integration, Inc. | ||
Solar | Miag-ao Solar Power Project | COSMO Solar energy, Inc. | |
La Carlota Solar Power Project Phase A (SACASOL II-A) | San Carlos Solar energy Inc. | ||
Cadiz Solar Power Project | Phil.Power Exploration & Development Corporation | ||
Wind | Nabas Wind Power Project Phase I – 34 Phase II-16 | PetroWind energy Corporation | |
Biomass | 12 MW Multi-Feedstock Biomass Power Plant Project | Megawatt Clean energy, Inc. | |
2.5 MW Rice Husk-Fired Biomass Power Plant Project | Megawatt Clean energy, Inc. | ||
Mindanao[58] | Hydropower | Lake Mainit | Agusan Power Corporation |
Puyo Hydroelectric Power Project | First Gen Mindanao Hydropower Corp. | ||
Asiga | Asiga Green energy Corp. | ||
Manolo Fortich I | Hedcor Bukidnon, Inc. | ||
Manolo Fortich 2 | Hedcor Bukidnon, Inc. | ||
Solar | Kibawe Solar Power Project | Asiga Green energy Corp. | |
Digos Solar Power Project Phase I | Enfinity Philippines Renewable Resources, Inc. | ||
Digos Solar Power Project Phase II | Enfinity Philippines Renewable Resources, Inc. | ||
Biomass | 3 MW Biomass Cogeneration Facility | Philippine Trade Center, Inc. | |
15 MW LPC Biomass Power Plant Project | Lamsan Power Corporation | ||
3.5 MW Biomass Cogeneration System | Green Earth Enersource Corporation | ||
10MW Malay-balay Bioenergy Corporation Multi Feedstock Generating Facility | Malaybalay Bio-energy Corporation | ||
23.5 MW EPC Woody Biomass Power Plant Project | Eastern Petroleum Corporation | ||
12 MW Napier Grass-Fired Biomass Power Plant Project | Manolo Fortich Biomass energy Corporation |
*—off grid project
See also
[edit]- Electricity sector in the Philippines
- Energy in the Philippines
- Geothermal power in the Philippines
- Wind power in the Philippines
References
[edit]- ^ a b c d e f Membrere L. "2013 Philippine power statistics" Archived 10 April 2016 at the Wayback Machine Accessed 8 April 2016.
- ^ "Philippines sets 50% renewables target by 2030". Agence France-Presse. Retrieved 31 March 2018.
- ^ Programme, Climate Action. "The Philippines pursues renewable energy expansion". www.climateactionprogramme.org. Retrieved 31 March 2018.
- ^ "Philippines". UNDP Climate Promise. Retrieved 29 May 2023.
- ^ World Journal "See how climate change affects the Philippines" TIME Accessed 8 April 2016.
- ^ a b Brahim S. "Renewable energy and energy security in the Philippines" in Energy Procedia.
- ^ a b ["Republic Act No. 9136 - an Act Ordaining Reforms in the Electric Power Industry, Amending for the Purpose Certain Laws and for Other Purposes". Archived from the original on 21 April 2016. Retrieved 12 April 2016. "Republic Act No. 9136" department of Energy. Accessed 12 April 2016.
- ^ a b "Republic Act No. 9367" Department of Energy Accessed 13 April 2016.
- ^ Renewable Energy Act Reurasia.com 13 September 2016
- ^ a b "Republic Act No. 9513" Archived 31 March 2016 at the Wayback Machine Department of Energy.
- ^ a b "Republic Act No. 9729" Official Gazette of the Republic of the Philippines 23 October 2009. Accessed 13 April 2016
- ^ Latest renewable energies projects Reurasia.com 13 September 2016.
- ^ Verifying greenhouse gas emissions National Research Council Washington DC 2010 p vii – 36. ISBN 978-0-309-15211-2.
- ^ "Energy security" International Energy Agency. Accessed 8 April 2016.
- ^ "Coal statistics" Archived 10 April 2016 at the Wayback Machine Department of Energy. Accessed 8 April 2016.
- ^ "Philippines crude oil production by year" Index Mundi website. Accessed 8 April 2016.
- ^ Membrere L. "Renewable energy" Archived 7 April 2016 at the Wayback Machine Department of Energy. Accessed 8 April 2016.
- ^ Agaton, Casper Boongaling (25 January 2018). "Use coal or invest in renewables: a real options analysis of energy investments in the Philippines". Renewables: Wind, Water, and Solar. 5 (1): 1. doi:10.1186/s40807-018-0047-2. ISSN 2198-994X.
- ^ a b c d "Summary of Installed Capacity, Dependable Capacity, Power Generation and Consumption". Philippines Department of Energy.
- ^ "List of existing plants (Luzon)" Archived 18 April 2016 at the Wayback Machine Department of Energy
- ^ "List of existing plants (Visayas)" Archived 10 June 2016 at the Wayback Machine Department of Energy
- ^ "List of existing plants (Mindanao) Archived 10 June 2016 at the Wayback Machine Department of Energy
- ^ Erdiwansyah; Mamat, R.; Sani, M. S. M.; Sudhakar, K. (20 June 2019). "Renewable energy in Southeast Asia: Policies and recommendations". Science of the Total Environment. 670: 1095–1102. Bibcode:2019ScTEn.670.1095E. doi:10.1016/j.scitotenv.2019.03.273. ISSN 0048-9697. PMID 31018425. S2CID 109529680.
- ^ a b c Guiamel, Ismail Adal; Lee, Han Soo (1 November 2020). "Potential hydropower estimation for the Mindanao River Basin in the Philippines based on watershed modelling using the soil and water assessment tool". Energy Reports. 6: 1010–1028. doi:10.1016/j.egyr.2020.04.025. ISSN 2352-4847. S2CID 218971298.
- ^ a b c d Delina, Laurence L. (1 July 2020). "Indigenous environmental defenders and the legacy of Macli-ing Dulag: Anti-dam dissent, assassinations, and protests in the making of Philippine energyscape". Energy Research & Social Science. 65: 101463. doi:10.1016/j.erss.2020.101463. ISSN 2214-6296. S2CID 213895250.
- ^ a b "Hydropower" Archived 30 April 2016 at the Wayback Machine Department of Energy Accessed 8 April 2016
- ^ "Release of Angat, Ipo dam water aggravates Bulacan floods" InterAksyon.com Accessed 8 April 2016.
- ^ a b c Talamayan, Fernan (1 May 2020). "Mapping Anti-Dam Movements: The Politics of Water Reservoir Construction and Hydropower Development Projects in the Philippines". Rochester, NY. doi:10.2139/ssrn.3748391. S2CID 234896254. SSRN 3748391.
{{cite journal}}
: Cite journal requires|journal=
(help) - ^ Fesalbon, R. M. A.; Blanco, A. C. (23 December 2019). "Hydropower Dam Site Selection and Visualization Using Gis and Rs Techniques: A Case of Marinduque, Philippines". The International Archives of the Photogrammetry, Remote Sensing and Spatial Information Sciences. XLII-4–W19. Copernicus GmbH: 207–214. Bibcode:2019ISPAr4219..207F. doi:10.5194/isprs-archives-XLII-4-W19-207-2019. S2CID 210896283.
- ^ Del Bene, Daniela; Scheidel, Arnim; Temper, Leah (1 May 2018). "More dams, more violence? A global analysis on resistances and repression around conflictive dams through co-produced knowledge". Sustainability Science. 13 (3): 617–633. doi:10.1007/s11625-018-0558-1. ISSN 1862-4057. S2CID 158360331.
- ^ Arnaiz, M.; Cochrane, T. A.; Hastie, R.; Bellen, C. (1 August 2018). "Micro-hydropower impact on communities' livelihood analysed with the capability approach". Energy for Sustainable Development. 45: 206–210. doi:10.1016/j.esd.2018.07.003. hdl:10092/15826. ISSN 0973-0826. S2CID 158665491.
- ^ a b c d e "List of existing plants (Luzon)" Archived 18 April 2016 at the Wayback Machine Department of Energy
- ^ a b c d e "List of existing plants (Visayas)" Archived 10 June 2016 at the Wayback Machine Department of Energy
- ^ a b c d e "List of existing plants (Mindanao) Archived 10 June 2016 at the Wayback Machine Department of Energy
- ^ "Geothermal power and electricity production" Renewable energy world website. Accessed 8 April 2016.
- ^ "Geothermal energy" National Geographic Society 20 November 2012. Accessed 8 April 2016.
- ^ "At Biliran geothermal project eight workers hurt in gas poisoning" philstar.com 22 June 2014. Accessed 8 April 2016.
- ^ Malicdem, Ervin (17 February 2015). "Optimal Tilt of Solar Panels in the Philippines". Schadow1 Expeditions: 6. doi:10.13140/RG.2.2.19886.61764. Retrieved 5 November 2017.
- ^ Guno, Charmaine Samala; Agaton, Casper Boongaling; Villanueva, Resy Ordona; Villanueva, Riza Ordona (1 February 2021). "Optimal Investment Strategy for Solar PV Integration in Residential Buildings: A Case Study in The Philippines". International Journal of Renewable Energy Development. 10 (1): 79–89. doi:10.14710/ijred.2021.32657. ISSN 2252-4940.
- ^ "Ilocos N. breaks tourists record" The Manila Bulletin Accessed 8 April 2016.
- ^ "Wind farm drawing tourists to Rizal" The Philippine Star Accessed 8 April 2016.
- ^ Gita-Carlos, Ruth Abbey (14 March 2024). "German wind, solar developer commits P392.4B for PH renewable energy". Philippine News Agency. Retrieved 14 March 2024.
- ^ "What is biomass" Biomass Energy Centre UK Accessed 8 April 2016.
- ^ "Biomass, solar, wind and ocean" Archived 23 March 2016 at the Wayback Machine Department of Energy. Accessed 8 April 2016.
- ^ "Advantages and Disadvantages" Science 134 website. Accessed 8 April 2016.
- ^ "Repeal EPIRA: PH power rates double in 15 years–IBON". IBON Foundation. Retrieved 30 March 2018.
- ^ Arado, Jennie P. (7 April 2017). "Electric consumer group calls for review of Epira". SunStar. Retrieved 30 March 2018.
- ^ "Drilon: Review EPIRA after 'apparent failure'". Rappler. Retrieved 30 March 2018.
- ^ Cabacungan, Gil. "Solon pines for pre-Epira days in power generation". Retrieved 30 March 2018.
- ^ a b Roxas, Fernando; Santiago, Andrea (2016). "Alternative framework for renewable energy planning in the Philippines". Renewable and Sustainable Energy Reviews. 59: 1396–1404. doi:10.1016/j.rser.2016.01.084.
- ^ "FIT Monitoring Board Summary". www.doe.gov.ph. Archived from the original on 16 March 2016. Retrieved 16 April 2016.
- ^ a b c Brahim, Sahara Piang (2014). "Renewable Energy and Energy Security in the Philippines". Energy Procedia. 52: 480–486. doi:10.1016/j.egypro.2014.07.101.
- ^ Marquardt, Jens (2015). "The politics of energy and development: Aid diversification in the Philippines". Energy Research & Social Science. 10: 259–272. doi:10.1016/j.erss.2015.07.013.
- ^ a b Taguibao, Jalton Garces (2011). "Renewable energy (RE) Sector Development in the Philippines Based on the Perspectives and Experiences of Selected Industry Managers". Asia-Pacific Social Science Review. 10 (2). doi:10.3860/apssr.v10i2.1903.
- ^ "Renewable energy on the rise" Philippine analyst July 2015
- ^ "2016 PRIVATE SECTOR INITIATED POWER PROJECTS IN LUZON (COMMITTED)" (PDF). Archived from the original (PDF) on 10 June 2016.
- ^ "2016 PRIVATE SECTOR INITIATED POWER PROJECTS IN VISAYAS (COMMITTED)" (PDF). Archived from the original (PDF) on 10 June 2016.
- ^ "2016 PRIVATE SECTOR INITIATED POWER PROJECTS IN MINDANAO (COMMITTED)" (PDF). Archived from the original (PDF) on 10 June 2016.