Maama Mai Solar Farm

Coordinates: 21°09′28.2″S 175°10′49.6″W / 21.157833°S 175.180444°W / -21.157833; -175.180444
From Wikipedia, the free encyclopedia

Maama Mai Solar Farm
Map
CountryTonga
LocationNukuʻalofa
Coordinates21°09′28.2″S 175°10′49.6″W / 21.157833°S 175.180444°W / -21.157833; -175.180444
StatusOperational
Construction began2011
Commission dateJuly 2012
Construction costNZD $7.9 million
Power generation
Nameplate capacity1.325 MW[1]
Annual net output1,880 MWh

The Maama Mai Solar Farm is a photovoltaic power plant in Nukuʻalofa, Tonga. It was the first renewable power plant in the country. The plant has an output of 1.325MW and produces 1,880 MWh of electricity per annum.[2] The plant's name is Tongan for "let there be light".[3]

History

[edit]

Funding for the plant was announced by New Zealand foreign affairs minister Murray McCully in July 2010.[4] The plant was to be built and operated by Meridian Energy, with the electricity sold to Tonga Power.[4] Funding of NZ$7.9 million was provided by the New Zealand Agency for International Development.[5]

Construction of the power plant started in 2011 and completed in 2012. It was then commissioned by King Tupou VI in July 2012, making it the first renewable power plant in the country.[2][6] In 2017, the power plant ownership was fully transferred to Tonga Power.[3]

See also

[edit]

References

[edit]
  1. ^ "Maama Mai Solar Farm - Tongatapu - Tonga". Reid Technology. Retrieved 9 January 2024.
  2. ^ a b "Maama Mai Solar". Tonga Power Ltd. Retrieved 9 January 2024.
  3. ^ a b "Maama Mai solar farm". Meridian. Retrieved 9 January 2024.
  4. ^ a b "NZ to help Tonga build solar power plant". RNZ. 7 July 2010. Retrieved 9 January 2024.
  5. ^ "NZ to help fund Tonga solar energy plant". RNZ. 6 September 2011. Retrieved 9 January 2024.
  6. ^ "NZ-funded solar facility opens in Tonga". Stuff. 24 July 2012. Retrieved 9 January 2024.