Jump to content

Kai Tak Cruise Terminal

Coordinates: 22°18′27″N 114°12′46″E / 22.3074°N 114.2128°E / 22.3074; 114.2128
From Wikipedia, the free encyclopedia

Kai Tak Cruise Terminal
啟德郵輪碼頭
Kai Tak Cruise Terminal in June 2014
Kai Tak Cruise Terminal is located in Hong Kong
Kai Tak Cruise Terminal
General information
StatusOperating
Location33 Shing Fung Road, Kai Tak, Kowloon, Hong Kong
Coordinates22°18′27″N 114°12′46″E / 22.3074°N 114.2128°E / 22.3074; 114.2128
Completedapprox. August 2014
Opened12 June 2013; 11 years ago (2013-06-12)
Cost$7.2 billion Hong Kong dollars[1]
OwnerGovernment of Hong Kong
Technical details
Floor count4
Floor area184,000 m2 (1,980,000 sq ft),
(with about 5,600 m2 (60,000 sq ft) of commercial area)
Design and construction
Architect(s)Foster + Partners (architect of record Wong Tung and Partners)
Main contractorDragages Hong Kong Limited
Website
kaitakcruiseterminal.com.hk
Kai Tak Cruise Terminal
Traditional Chinese啟德郵輪碼頭
Simplified Chinese启德邮轮码头
Transcriptions
Standard Mandarin
Hanyu PinyinQǐdé Yóulún Mǎtóu
Yue: Cantonese
JyutpingKai2dak1 jau4 leon4 maa5 tau4
Kai Tak Cruise Terminal Park
Courtyard inside terminal
Coach Drop off area
Outside access

Kai Tak Cruise Terminal is a cruise ship terminal on the former Kai Tak Airport runway in Hong Kong. Its completion date was delayed into 2013 due to re-tendering. Following an international competition, Foster + Partners was chosen to design the cruise terminal. The first ship berthed on 12 June 2013.[2] The terminal has the capacity to berth two large 360-metre (1,180 ft) long vessels, which carry a total of 5,400 passengers and 1,200 crew, as well as anticipating the demands of cruise liners currently on the drawing board.[3]

The Government announced that it would focus on the development of a new cruise terminal at Kai Tak development area[4] to help Hong Kong become a regional transport hub for cruise ships.[5] It was built by Dragages Hong Kong Limited and site formation was completed by Penta-Ocean Construction Company.

History and development

[edit]

The annual berth utilisation rate of Ocean Terminal in Tsim Sha Tsui, which offers two berths accommodating vessels of up to 50,000 tonnes (49,000 long tons), rose to 76% last year[when?] from 71% in 2003. Between 2001 and 2005, some 11 cruise vessels had to berth mid-stream and at container terminals because Ocean Terminal could not meet market demand.

Hong Kong's Secretary for Economic Development, Stephen Ip, said Hong Kong needs an additional berths between 2009 and 2015, and one to two more berths beyond 2015 to capture the growth of the regional cruise market.

  • Berthing facilities – two alongside berths of 850 metres (2,790 ft), an apron area, fender system and passenger gangways;
  • Support facilities – located mainly in the cruise terminal building, such as customs, immigration, quarantine counters, and 20 baggage handling areas; and,
  • A commercial area inside the cruise terminal building with a maximum gross floor area of 5,600 square metres (60,000 sq ft) for retail facilities.

The Government at first adopted a market-driven approach in the new development. Selected through an open tender exercise, the successful bidder would have owned the 76,000 square metres (19 acres) of land for a 50-year period and form the site as well as design, build and operate the terminal.

A pre-tender consultation with relevant trades was conducted in the first half of next year[when?] to expedite the pace of development, followed by invitation of tenders in the fourth quarter. The tender was to be awarded in the second quarter of 2008. The estimated development cost, excluding that for the commercial area, was about $2.4 billion HKD.

Tender

[edit]

The Hong Kong Special Administrative Region Government issued an open tender on 9 November 2007 for the development of the new cruise terminal.

The new cruise terminal is designed with about 30,000 square metres (320,000 sq ft) for a baggage handling area, a passenger waiting/queuing area, a customs, immigration and health quarantine area and accommodation for other government departments; a maximum of 50,000 square metres (540,000 sq ft) in the cruise terminal building was set aside for such purposes as hotels, retail space, convention halls, offices, shops and eating places; and at least 22,000 square metres (240,000 sq ft) for a landscaped deck.

On 9 July 2008, the Secretary for Commerce & Economic Development Frederick Ma announced that the Kai Tak cruise development project will be re-tendered as submissions received in the previous exercise did not conform with requirements. Ma said two submissions were received in the previous tendering exercise which closed in March. One submission called for hotel rooms to be individually sold off, while the other asked to develop more commercial area.[6][7]

Subject to lawmakers' approval, the Government will re-tender the site by year's end, aiming to award the tender by the third quarter of 2009. The first berth of the new cruise terminal was expected to begin operation by the second quarter of 2013.[6]

Construction

[edit]

The Government wanted to seek lawmakers' approval to fund the site formation works and facilities required for the provision of government services in the fourth quarter of 2008. At that time, the estimated cost ranges from $1.8 billion to $2 billion.

The Civil Engineering & Development Department awarded a $407 million contract for stage-one infrastructure works at the former Kai Tak Airport on 2 September 2009. Works started on 4 September for completion in four years. The contract comprises the construction of a 1.8 km (1.1 mi)-long two-lane road, associated drainage, sewerage and water works, and a fireboat berth and public landing steps. The works will provide infrastructure to serve the early development of the southern part of the former runway area, which includes the first cruise terminal berth and a park. The works have been designed by AECOM Asia which will also supervise construction.[8]

Permanent Secretary for Development (Works), Mak Chai-kwong, and the Managing Director of Dragages Hong Kong Limited, Nicolas Borit, signed a design and build contract for the Kai Tak Cruise Terminal Building on 8 May 2010. The first berth was to be commissioned in mid-2013 and was to be capable of accommodating the world's largest cruise vessels. The second berth was to commence operation in 2014 for berthing medium-sized cruise vessels.[9][10] The second berth will be ready from early 2016.

Architectural design

[edit]

The cruise terminal was designed by architects Foster + Partners. The terminal currently has the capacity to disembark a total of 8,400 (peak design load) or 5400 (base design load) passengers and 1,200 crew and its design also anticipates the demands of a new generation of larger cruise liners currently being designed. The interior, which spans 70 metres (230 ft), can be converted into a venue for performances, events and exhibitions, supported by the terminal's restaurants and shops. This flexibility ensures that the building will be used all year round and can fully utilize down time. The sustainable design combines a number of energy-saving measures, and will generate power from renewable sources, as well as making use of recycled rain water for cooling.[3]

The design, routing and functionality of the new terminal are based on the much smaller Passenger Terminal Amsterdam (PTA)[11] in Amsterdam, the Netherlands. Partner in the Bouygues-led consortium which won the tender, is Amsterdam Port Consultants (APC)[12] which consists of Haven Amsterdam, the government owner of the PTA terminal, and Ingenieursbureau Lievense, which was responsible for the design of PTA.[13] The Dutch terminal, PTA, although smaller was chosen as a model for the new Hong Kong terminal on the basis of PTA's multifunctionality.[11]

Operation and management

[edit]

On 8 March 2012, the Worldwide Cruise Terminals Consortium was awarded the right to operate and manage the cruise terminal at Kai Tak. The consortium is required to pay the government a fixed rent of around HK$13 million for the 10-year operation. In addition, the government will receive a percentage of the operator's gross receipts as variable rent, with the percentage increasing from 7.3 per cent to 34 per cent as gross receipts rise. The grouping is made up of Worldwide Flight Services, Royal Caribbean Cruises and Neo Crown.[14] Mariner of the Seas was the first cruise ship to dock at the new terminal on 12 June 2013.[15]

Home port

[edit]

Roughly 80% of the ship calls at the Kai Tak Cruise Terminal have been turnaround or 'homeporting' calls.[16] The first major homeport season was by Voyager of the Seas, which was based at Kai Tak from June to October 2015.

Lines

[edit]

The Kai Tak Cruise Terminal ("KTCT") commenced operation in 2013 and has since welcomed cruise ships from a wide variety of cruise lines. Lines calling or scheduled to call at the KTCT include:

Year-on-year development

[edit]
Kai Tak Cruise Terminal Year-On-Year Development[18]
Jun–Dec 2013 2014 2015 2016 2017
Revenue Passengers 35,322 100,866 228,809 372,946 732,586
Monthly Avg 5,046 8,046 19,067 31,079 61,049
Lines Calling 4 8 9 18 16
Total Calls 9 28 56 95 190
Turns 4 17 43 69 161
Transits 5 11 13 26 29
Call Months 4 of 7 10 11 12 12
Ship Days/ Utilization 15 49 75 120 216

* confirmed bookings as of Jan 2018

Passenger numbers based on ship’s declarations and do not include crew

References

[edit]
  1. ^ Ng, Teddy and Li. Joseph (1 October 2008). "Govt to finance cruise terminal with HK$7.2b". China Daily. Archived from the original on 11 August 2014.
  2. ^ Wong, Hiufu (13 June 2013). "Hong Kong's $1 billion cruise terminal opens". CNN Travel. Archived from the original on 18 June 2013.
  3. ^ a b "Kai Tak Cruise Terminal, Hong Kong, 2010". Foster + Partners. Archived from the original on 11 August 2014.
  4. ^ "Hong Kong Kai Tak Development plan". China Daily. 30 June 2012. Archived from the original on 11 August 2014.
  5. ^ "Kai Tak Cruise Terminal: Explanatory Note on Proposed User Requirements for Terminal Operation and Ancillary Facilities" (PDF). Tourism Commission, Commerce and Economic Development Bureau, Hong Kong Government. April 2009. Archived (PDF) from the original on 28 April 2013.
  6. ^ a b Li. Joseph (10 July 2008). "Govt to re-tender Kai Tak cruise development project". China Daily. p. 1. Archived from the original on 11 August 2014.
  7. ^ "Re-tender for development of a new cruise terminal in Hong Kong". Government of Hong Kong. 9 July 2008. Archived from the original on 12 August 2014.
  8. ^ Contract awarded for Kai Tak works
  9. ^ "Contract signed to start construction of Kai Tak Cruise Terminal Building (with photos/video)". Government of Hong Kong. 8 May 2010.
  10. ^ CGI Animation of Kai Tak Cruise Terminal Building. Youtube.com. Retrieved on 9 March 2012.
  11. ^ a b "Hongkong kiest PTA als voorbeeld bouw terminal" (in Dutch). Passenger Terminal Amsterdam. 21 May 2010. Archived from the original on 12 August 2014.
  12. ^ "Cruise terminal design, Hong Kong". Amsterdam Port Consultants. Archived from the original on 12 August 2014.
  13. ^ "Start van de realisatie van de Kai-Tak cruise terminal in Hong Kong" (in Dutch). Ingenieursbureau Lievense. Archived from the original on 12 August 2014.
  14. ^ Luk, Eddie (9 March 2012). "New grouping wins rights to Kai Tak cruise terminal". The Standard. Archived from the original on 12 August 2014. Retrieved 9 March 2012.
  15. ^ John Tsang (27 February 2013). "Promoting Tourism Industry - 2013-14 Budget". Hong Kong Government.
  16. ^ "Kai Tak Cruise Terminal 2018". Archived from the original on 22 January 2019. Retrieved 4 September 2018.
  17. ^ "Cruise Schedule". Kai Tak Cruise Terminal Website. 20 October 2015.
  18. ^ "Kai Tak Cruise Terminal Highlights". kaitakcruiseterminal.com.hk. Retrieved 3 October 2018.
[edit]