Delivery reliability
Delivery reliability is one of the five attributes in supply-chain management according to SCOR-model, developed by the management consulting firm PRTM, now part of PricewaterhouseCoopers LLP (PwC) and endorsed by the Supply-Chain Council (SCC) as the cross-industry de facto standard diagnostic tool for supply chain management, SCOR measures the supplier’s ability to predictably complete processes as promised. It is measured by perfect order fulfillment and demonstrates the degree to which a supplier is able to serve its customers within the promised delivery time.
Following the nomenclature of the DR-DP-Matrix, three main approaches to measure DR can be distinguished:
- (=CLIP)
- Type of measurement: volume (V)/singular(S)
- Type of view: on time (T)/ delivery (D)
Formula
[edit]If ()
- =
Note: In the case that supplier notifies the appropriate partner in the supply chain that a promised delivery date/quantity cannot be met which is called delivery early warning (DEW), the sum of DEW issued to reduce the commit for a certain week is added in the denominator.
Else
- NULL
Demand: Suppliers confirmed quantity; c: Product identifier; p: Time period e.g. a day, a week, a month ...
The cumulation over a period and a group of product identifiers c is done as follows:
whereas p is determined by demand period
Singular/delivery and singular/on Time
[edit]Singular case definition
[edit]To fit to the needs of the environment, the granularity of a singular case () has to be defined. In general a singular case is described by an n-Tuple consisting of a set of the following order and delivery details:
- order number
- customer identifier
- product identifier
- wish date of customer
- confirmed date of supplier
- ship to information
- delivery date
- delivery note number
Formula
[edit]1)
- After a singular case has been delivered to the customer its DR is measured as follows:
- If (wish date <= arrival date <= confirmed date of supplier) then
- DRsingular case=1
- else
- DRsingular case=0
- If (wish date <= arrival date <= confirmed date of supplier) then
arrival date = delivery date + transit time
By cumulating the results of singular cases over a certain period p and, if necessary, additional criteria c (e.g. customer, product, ...) the delivery reliability is calculated as follows:
whereas p is determined by the arrival date
2)
- After a period has elapsed all singular cases with first confirmed date within period are considered and their DR is measured as follows:
- If (wish date <= arrival date <= confirmed date of supplier) then
- DRsingular case=1
- else
- DRsingular case=0
- If (wish date <= arrival date <= confirmed date of supplier) then
arrival date = delivery date + transit time
By cumulating the results of singular cases over a certain period p and, if necessary, additional criteria c (e.g. customer, product, ...) the delivery reliability is calculated as follows:
whereas p is determined by the first confirmed date
Result
[edit]0%≤≤100%