Blue Line (St. Louis MetroLink)
The Blue Line is the newer and shorter line of the MetroLink light rail service in Greater St. Louis. It serves 25 stations across three counties and two states.
History
[edit]Much of the Blue Line follows former railroad right of way. Starting north from Shrewsbury, the alignment crosses BNSF's Southeastern Junction and follows former Terminal Railroad Association of St. Louis right of way to Clayton, briefly along Interstate 170. The stretch running eastward along Forest Park Parkway between Clayton and the Forest Park–DeBaliviere station was a Rock Island railroad right of way until it was abandoned in 1931. The section between Pershing and DeBaliviere avenues carried the #1 Kirkwood and the #14 University-Clayton streetcar lines until 1963.[1][2]
In 1999, East-West Gateway staff members submitted an updated conceptual design for Segment 1 of the Cross County extension between Forest Park and Shrewsbury.[3] Metro did not seek federal funding, instead issuing $430 million in bonds against Proposition M sales taxes.[4] After several delays and design changes, construction began on April 9, 2003 with an estimated cost of $550 million.[5]
Citing repeated delays and cost overruns, Metro fired and then sued its general contractor, Cross County Collaborative, in the summer of 2004. Metro sought $81 million in damages for fraud and mismanagement while the Collaborative counter-sued for $17 million for work that Metro hadn't paid for. On December 1, 2007, a jury awarded the Collaborative $2.56 million.[6]
The 8-mile (12.9 km) Cross County extension opened on August 26, 2006 with a final cost of $676 million[7] and added nine stations between Forest Park-DeBaliviere and Shrewsbury–Lansdowne I-44.[4] From its 2006 opening until October 27, 2008, the Blue Line was known as the Shrewsbury branch.[8]
In 2013, the St. Louis County Council authorized loaning Metro $400 million of surplus Proposition A funds to pay off debt related to the Cross County extension.[9]
On July 26, 2022, portions of the Blue Line were impacted by a flash flood that shut down the system for nearly 72 hours and caused roughly $40 million in damage.[10][11] Damages included two elevators, two communications rooms and three signal houses.[12] By that September, normal Red Line service had resumed while restricted service continued on the Blue Line.[13] On July 31, 2023, Metro received $27.7 million in federal emergency disaster relief funding to help cover the cost of flood damage.[14]
In March 2024, Blue Line platform and speed restrictions were lifted with the last damaged signal house now operational.[15]
Route
[edit]The 24-mile (39 km) Blue Line alignment starts in Shrewsbury, Missouri (Shrewsbury-Lansdowne I-44) just west of the River des Peres. It crosses over Interstate 44 and continues north to the next two stations located in Maplewood, Missouri (Sunnen and Maplewood/Manchester). The line then continues north to the Brentwood I-64 station, located in Brentwood, Missouri just south of Interstate 64. It then proceeds north in a tunnel underneath Interstate 64, continuing to the Richmond Heights station serving the popular Saint Louis Galleria shopping mall. The line then proceeds through a sharp turn east to the Clayton station in the median of Forest Park Parkway in Clayton, Missouri where it serves the Central Business District of St. Louis County. It heads further east to the Forsyth station where it then enters a tunnel traveling to the University City-Big Bend subway station. After crossing the St. Louis City/County boundary, the Blue Line makes its last stop at the Skinker subway station serving nearby Washington University. At the following station, Forest Park-DeBaliviere, the Blue Line meets the Red Line. From this station the two services share a track alignment with each other until the Blue Line terminates at the Fairview Heights station in Illinois.
Shared Alignment
[edit]From the Forest Park-DeBaliviere station, the Blue and Red lines share the same set of tracks for the next 16 stations.[16] Continuing east, the Central West End and Cortex stations serve the popular Central West End neighborhood, Washington University Medical Center and Cortex Innovation Community. The Grand station transfers with the busy #70 MetroBus line and serves Saint Louis University and its hospital. Next, the Union Station, Civic Center, Stadium, 8th & Pine, Convention Center and Laclede's Landing stations serve downtown St. Louis and its many popular attractions. Crossing the historic Eads Bridge into Illinois, the line serves the East Riverfront, 5th & Missouri, Emerson Park, Jackie Joyner-Kersee Center, and Washington Park stations in East St. Louis, Illinois. At the next station, Fairview Heights, the Blue Line terminates and the shared alignment ends.
Stations
[edit]From Shrewsbury−Lansdowne I-44 to Fairview Heights (west to east)
Station | Transfer | City/town served | County | Opening date |
---|---|---|---|---|
Shrewsbury–Lansdowne I-44 | Shrewsbury | St. Louis County | August 26, 2006[17] | |
Sunnen | Maplewood | |||
Maplewood–Manchester | ||||
Brentwood I-64 | Brentwood | |||
Richmond Heights | Richmond Heights | |||
Clayton | Clayton | |||
Forsyth | ||||
University City–Big Bend | University City | |||
Skinker | Independent city of St. Louis | |||
Forest Park–DeBaliviere | Red | July 31, 1993[18] | ||
Central West End | ||||
Cortex | July 31, 2018[19] | |||
Grand | July 31, 1993[18] | |||
Union Station | ||||
Civic Center | ||||
Stadium | ||||
8th & Pine | ||||
Convention Center | ||||
Laclede's Landing | ||||
East Riverfront | East St. Louis | St. Clair County | May 14, 1994[20] | |
5th & Missouri | July 31, 1993[18] | |||
Emerson Park | May 5, 2001[21] | |||
Jackie Joyner-Kersee Center | ||||
Washington Park | ||||
Fairview Heights | Fairview Heights |
Public artwork
[edit]In 2002, Metro's Arts in Transit program commissioned a group of artists to join architects and engineers during the design phase of the Cross County extension. This practice of artist participation during system design began during the design and construction of the initial 1993 MetroLink alignment.[22] The work of these artists involved exploration of landscape alternatives, designing the paving patterns for concrete adjacent to stations, and creating the “flow”-patterned retaining walls running along the tracks in the below-grade stretches of the alignment.[22]
In 2006, the Arts in Transit program commissioned a work made for at-grade stretches of the alignment. An overlay of lacy aluminum silhouettes, titled A Walk in the Park, embellishes the concrete privacy fence, called the Catlin Wall, which runs parallel to the tracks between the Skinker and Forest Park-DeBaliviere stations. Created by Andy Cross, Carl Harris, and Ty de LaVenta, the work is a series of cut metal panels depicting trees, vines, leaves, and trellises.[23]
Projects in progress
[edit]System rehabilitation
[edit]In 2023, Metro began a system-wide rehabilitation program that will last up to two years.[24] Work on the Blue Line will include the rehabilitation of the Cross County tunnels and stations between Forsyth and Skinker and will include the construction of a storage siding near the Richmond Heights station.[25] Elsewhere, curve tracks, catenary wire, system conduit, staircases and retaining walls are to be upgraded or replaced.[26]
In 2024, Metro expects to complete upgrades to the Supervisory Control Automated Data Acquisition (SCADA) and Public Address/Customer Information (PA/CIS) systems. The upgraded SCADA/PA/CIS will operate as an integrated system that monitors and controls operations and will allow Metro to provide real-time arrival information to passengers, such as live displays at stations.[27]
Previous proposals
[edit]Previously proposed extensions of the Blue Line are defunct; regional leaders have said their priorities are proposed expansions in the city of St. Louis and North St. Louis County.[28]
Cross County
[edit]- MetroSouth. This 6–12-mile (9.7–19.3 km) extension was envisioned as Cross County Segment 2 and would have extended the current Blue Line from its terminus in Shrewsbury further south beyond Interstates 270/255 to Butler Hill Road. A third alternative would have ended at Watson Road.[29] An environmental impact study was completed in 2004; however, selection of an LPA was deferred due to the lack of local funding sources as well as other factors.[30]
- MetroNorth. This approximately 12-mile (19 km) extension was envisioned as Cross County Segment 3 and would have extended the current Blue Line from Clayton towards Florissant, Missouri. Some of this segment would have followed the former Terminal Railroad Association of St. Louis' Central Belt right-of-way paralleling Interstate 170.[31]
- Daniel Boone. This 8–10-mile (13–16 km) extension would have branched off the Cross County corridor near Olive Boulevard along disused Rock Island Railroad right-of-way. It would then turn west and follow existing trackage operated by Central Midland Railway to Page Avenue where the line would continue to Westport Plaza.[32][33] An approximately 12-mile (19 km) extension to Chesterfield would have been a potential Phase 2 of the Daniel Boone branch. The alignment would have continued west following Page Avenue and Highway 364 then turning towards Creve Coeur Lake Memorial Park. From there it would have headed to Spirit of St. Louis Airport in the Chesterfield Valley.[31] This alignment has not been given serious consideration because of its perceived low ridership potential.
See also
[edit]References
[edit]- ^ Andrew D. Young (1988). The St. Louis Streetcar Story. Glendale, CA: Interurban Press. p. 205.
- ^ Andrew D. Young (1988). The St. Louis Streetcar Story. Glendale, CA: Interurban Press. p. 9.
- ^ "Cross County MetroLink Extension, Conceptual Design 1999" (PDF). East-West Gateway Council of Governments. June 30, 1999. pp. 2–3. Retrieved March 18, 2024.
- ^ a b "Metro Announces August 26 Grand Opening Date for Cross County MetroLink Extension" (PDF) (Press release). Metro. August 7, 2006. Archived from the original (PDF) on October 9, 2007. Retrieved June 7, 2007.
- ^ "Metro Breaks Ground on Cross County MetroLink Extension". STLPR. April 9, 2003. Retrieved March 18, 2024.
- ^ American, Jessica Bassett Of the St Louis (December 6, 2007). "Metro loses suit against Cross County Collaborative". St. Louis American. Archived from the original on September 26, 2023. Retrieved September 26, 2023.
- ^ "MetroLink Cross-County Extension". RailWorks. Retrieved March 18, 2024.
- ^ "World.nycsubway.org: St. Louis, Missouri". Nycsubway.org. Retrieved April 10, 2016.
- ^ "St. Louis County Council Approves Economic Development Merger, $400 Million Loan To Metro". STLPR. June 19, 2013. Retrieved March 19, 2024.
- ^ Lindsey (August 16, 2022). "MetroLink Flood Damage Update". metrostlouis.org. Archived from the original on September 12, 2022. Retrieved September 12, 2022.
- ^ Schrappen, Colleen (August 21, 2022). "MetroLink to resume full service, but cost for flood repairs could double". STLtoday.com. Archived from the original on September 12, 2022. Retrieved September 12, 2022.
- ^ Wanek-Libman, Mischa (July 29, 2022). "Metro St. Louis estimates flood damage between $18-$20 million". Mass Transit. Retrieved February 19, 2024.
- ^ Jerry (September 1, 2022). "MetroLink Changes Starting September 5: Blue Line Service to Operate Between Shrewsbury and Forest Park". Metro Transit – Saint Louis. Retrieved March 18, 2024.
- ^ Schlinkmann, Mark (August 1, 2023). "Metro gets nearly $28 million in federal aid to cover repairs after 2022 flood". STLtoday.com. Archived from the original on September 5, 2023. Retrieved September 5, 2023.
- ^ "Upcoming Schedule Changes". Metro Transit – Saint Louis. Retrieved March 18, 2024.
- ^ "MetroLink Schematic Map" (PDF). Metro St. Louis.
- ^ "Next Stop: Shrewsbury". The St. Louis Post-Dispatch. August 20, 2006. p. C2. Retrieved April 15, 2021 – via Newspapers.com.
- ^ a b c Lindecke, Fred W. (August 1, 1993). "Area Riders Throng to Try MetroLink". The St. Louis Post-Dispatch. pp. 1A, 6A. Retrieved April 15, 2021 – via Newspapers.com.
- ^ "Metro Marks Opening of Cortex Station". The St. Louis Post-Dispatch. August 1, 2018. p. A12. Retrieved April 15, 2021 – via Newspapers.com.
- ^ Goodrich, Robert (April 27, 1994). "E. St. Louis Starring in MetroLink". The St. Louis Post-Dispatch. p. B1. Retrieved April 15, 2021 – via Newspapers.com.
- ^ Leiser, Ken (April 30, 2001). "MetroLink Extension Opens This Weekend With Parking to Spare". The St. Louis Post-Dispatch. p. A9. Retrieved April 15, 2021 – via Newspapers.com.
- ^ a b "Cross County Design Collaboration". Arts in Transit, Inc. Retrieved October 3, 2022.
- ^ "A Walk in the Park". Arts in Transit, Inc. Retrieved October 3, 2022.
- ^ "MetroLink Improvements". Metro Transit – Saint Louis. Retrieved September 26, 2023.
- ^ "MetroLink Improvement Projects". Metro Transit – Saint Louis. Retrieved September 26, 2023.
- ^ "MetroLink Improvement Projects". Metro Transit – Saint Louis. Archived from the original on September 25, 2023. Retrieved September 26, 2023.
- ^ "MetroLink Improvement Projects". Metro Transit – Saint Louis. Archived from the original on September 25, 2023. Retrieved September 26, 2023.
- ^ Schlinkmann, Mark (November 17, 2021). "St. Louis County back in picture for north-south MetroLink expansion". STLtoday.com. Archived from the original on September 11, 2022. Retrieved September 11, 2022.
- ^ "St. Louis Metro South MetroLink Extension: DEIS" (PDF). East-West Gateway Council of Governments. November 1, 2005. p. 2-19. Retrieved March 12, 2024.
- ^ "East-West Gateway Board Defers Selection of MetroLink Alternative for Metro South Study Area" (PDF). East-West Gateway. November 3, 2004. Archived from the original (PDF) on May 15, 2013. Retrieved September 29, 2010.
- ^ a b "LPAs for Daniel Boone, Northside and Southside Study Areas" (PDF). East-West Gateway Council of Governments. Archived from the original (PDF) on April 3, 2019. Retrieved September 25, 2022.
- ^ "MetroLink Planning – Daniel Boone". East-West Gateway. Archived from the original on March 20, 2007. Retrieved June 1, 2007.
- ^ "St. Louis RR Maps". Railsandtrails.com. Archived from the original on June 29, 2022. Retrieved July 25, 2022.
External links
[edit]- Metro – Official website for Metro Transit
- Bi-State Development – Official website for Bi-State Development
- Citizens for Modern Transit – St. Louis transit advocacy group
- Arts in Transit Website