Jump to content

LNG Hrvatska

From Wikipedia, the free encyclopedia
(Redirected from Adria LNG)
LNG Hrvatska
Company typePublic
IndustryOil and gas industry
Founded8 June 2010
Headquarters
Zagreb
,
Croatia
Key people
Ivan Fugaš, Managing director[1]
ServicesGas transportation
RevenueIncrease 42.420 million EUR (2023)
Increase 1.132 million EUR (2023)
OwnerRepublic of Croatia
Number of employees
33 (2023)
ParentHrvatska elektroprivreda d.d.
Plinacro d.o.o.
Websitehttps://lng.hr/en/home/

LNG Hrvatska d.o.o. (also LNG Croatia LLC) is a company that operates a floating liquefied natural gas (LNG) regasification terminal in Omišalj on the island of Krk, Croatia. It commenced operations on 1 January 2021, with full capacity (2.6 billion cubic meters annually) booked for the next three years.[2]

History

[edit]

The project was first considered in 1995 when initial exploratory work was undertaken. A feasibility study was completed by 2008 and the location permit was issued in 2010 after environmental impact assessment was carried out.[3] The project was developed by Adria LNG, which shareholders were E.ON Ruhrgas, Total S.A., OMV, RWE, and Geoplin.[4] The consortium slated a 25% stake for Croatian partners, expecting to include oil company INA (14%), power company HEP and gas pipeline operator Plinacro (together 11%).[3][5]

In October 2009, one of the project partners RWE moved out from the project.[4][6] In December 2010 the consortium closed its office in Croatia, which marked the end of the project.[7]

In April 2016 First Deputy prime minister Tomislav Karamarko announced the restart of the project.[8]

On 30 November 2017 Front-End Engineering and Design, has been developed by Belgian company Tractebel. FEED is like a basic variant of floating construction LNG terminal on the island of Krk predicted the "most complex" scenario, which involves the FSRU ship of larger dimensions and the construction of the foundations of the concrete shore system reinforced concrete caissons.[9]

The construction chronology:[10]

  • 04/2019 - Site registration and start of construction work
  • 06/2019 - Start of construction work on jetty and the mooring dolphins
  • 08/2019 - Construction work on the gas pipeline and water supply system
  • 09/2019 - Start of dredging the terminal sea access path
  • 11/2019 - Delivery of pipes for gas pipeline to the construction site and start of welding works
  • 01/2020 - Start of laying the gas pipeline and setting up the permanent air quality monitoring station
  • 03/2020 - Start of construction of the terminal firefighting water tank
  • 04/2020 - Installation of prestressed girder for jetty access bridge
  • 05/2020 - Start of construction of the terminal control building
  • 06/2020 - Delivery of high-pressure offloading arms to the construction site
  • 07/2020 - Installation of high-pressure offloading arms with mechanical completion of the pipeline and start of the tests
  • 09/2020 - Completion of land construction work
  • 10/2020 - Final works of arrangement of the terminal plateau
  • 11/2020 - Final works on the terminal
  • 12/2020 - Test run and issuance of the use permit for the terminal

The project was officially inaugurated in January 2021.[11]

In April 2022, due to the outbreak of the crisis caused by the Russian invasion of Ukraine, a decision was made to increase the LNG gasification capacity to 338,000 m3/hour, which is about 2.9 billion cubic meters annually.[12]

Due to the energy crisis, the Government of the Republic of Croatia made a strategic decision on August 18, 2022, to increase the capacity of the LNG terminal and gas pipeline Zlobin - Bosiljevo. The capacity of the terminal will be increased to 6.1 billion cubic meters, and the investment will cost a total of 180 million euros, of which 25 million relate to the terminal and 155 million to the gas pipeline.[13]

On April 14, 2023, Wartsila Gas Solutions from Norway and LNG Croatia concluded a contract worth 22.97 million euros for the delivery of an additional gasification module that will be installed at the Terminal, with a maximum capacity of 250 thousand cubic meters of natural gas per hour, which will increase the terminal's capacity to almost doubled, to 6.1 billion cubic meters of natural gas per year. Production will last 22 months, and it will be installed on the ship LNG Croatia in the summer of 2025.[14]

Significance

[edit]

The terminal has a geopolitical and strategic dimension in the context of strengthening the European energy market and increasing the security of gas supply to European Union countries and especially to Central and Southeast European countries that want to secure a new reliable gas supply route. It is a project of strategic importance for the European Union and the Republic of Croatia.

The terminal will provide additional source of natural gas for the Croatian market, which relies on natural gas for 48% of its energy needs. The terminal will also be a distribution point for natural gas to the surrounding market including Italy, Austria, Hungary, Romania and Slovenia, as Croatia's demand only stands at 3.2 billion cubic metres (110 billion cubic feet) per year which is significantly below the expected capacity of the terminal. For this purpose, a new natural gas pipeline between Croatia and Hungary was built.

Technical features

[edit]

The annual handling capacity of the vessel is 2.6 billion cubic meters. The terminal can accommodate all ship sizes from 3,500 to 265,000 cubic meters.[15]

FSRU vessel

[edit]

FSRU (Floating Storage & Regasification Unit) vessel consists of LNG storage tanks, equipment for LNG loading and unloading and LNG regasification equipment. All processes on board are monitored by the operator from the central control room while autonomous safety systems are in operation in case of fire and gas occurrence.[15]

The FSRU vessel is equipped with four LNG storage tanks with a total capacity of 140,206 m3, three LNG regasification units with a maximum regasification rate of 451,840 m3/h and with power plant which generates electricity for the purpose of operating the terminal.[15]

Regasification of LNG is performed by exchanging the heat of seawater and LNG over glycol as an intermediate fluid. Seawater transfers its heat to glycol and is afterwards discharged back to the sea without any treatment. The glycol afterwards transfers heat to the LNG which is regasified during this process. Natural gas is then through high-pressure offloading arms, delivered to the gas transmission system of the Republic of Croatia.[15]

Onshore part of the terminal

[edit]

The onshore part of the LNG terminal consists of the jetty head, breasting dolphins for FSRU berthing, mooring dolphins for FSRU and LNG carrier berthing, quick release hooks, the access bridge, the high-pressure offloading arms with connecting pipeline, pig launching station, firefighting system, terminal control building, and associated facilities.[15]

The FSRU vessel is moored to the jetty and connected to the high-pressure offloading arms through which natural gas enters the connecting pipeline. In addition to the mooring of the FSRU, the jetty is also designed for the indirect acceptance of the LNG carrier, which is moored side by side to the FSRU vessel during transfer of the LNG.[15]

Jetty head is the main part of the jetty, constructed as a platform on concrete piles. High pressure offloading arms with a connection to the connecting pipeline are located on the top part of the jetty head. The natural gas is transported through the connecting pipeline to the Omišalj gas node where the connecting pipeline is connected to transmission system of the Republic of Croatia.[15]

Breasting dolphins for FSRU vessel berthing are constructed on concrete piles, equipped with fenders for safe berthing of the FSRU vessel.[15]

The mooring dolphins for FSRU vessel and LNG carrier mooring are constructed on concrete piles, equipped with quick release hook mooring system to carry out unmooring of FSRU vessel in a safe and fast way in case of emergency.[15]

The jetty head, breasting dolphins and mooring dolphins for FSRU and LNG carrier berthing are connected by catwalks. A 90 m long access bridge, with access pavement and sidewalk, connects the jetty head with onshore part of the jetty.[15]

The connecting gas pipeline, with nominal diameter 1.000 mm and operating pressure of 100 bar is 4.2 km long. Starting point of the connecting pipeline is located at the jetty head and the end point is located on the Omišalj gas node. Main function of the connecting pipeline is send-out of the natural gas from terminal and its delivery to transmission system of the Republic of Croatia.[15]

The connecting water supply line, with nominal diameter 90 mm and with a total length of 2.5 km is connected to the public water supply system at manhole near the state road D102. Main function of the water supply system is to provide water on the LNG facility for sanitary purposes, as well as for the filling of terminal firefighting water tank.[15]

Port facility Omišalj-Njivice

[edit]

Special Purpose Port – Industrial Port LNG Terminal, Omišalj-Njivice is placed on the north part of the Krk island, 1.7 NM southeast of the Cape Tenka Punta.

  • Port Facility: Omišalj – Njivice (LNG)
  • IMO: HROMI-0003
  • NBL number: HR807
  • Port focus: LAT 45°12’02.7″N, LONG 14°31’58.6″E
  • Port e-mail: port@lng.hr
  • Port Authority: LNG Croatia LLC, Development and Port Security Department

Project company

[edit]

The project is developed by LNG Hrvatska. The shareholders of the company are:[16]

Both of the shareholders are in 100% ownership of the Republic of Croatia.

The managing director of the company is Ivan Fugaš, since 1 June 2023.

References

[edit]
  1. ^ "Management structure". LNG Hrvatska. Retrieved 29 August 2023.
  2. ^ "Croatia's floating LNG terminal starts commercial operations". Croatia Week. 1 January 2021. Retrieved 14 April 2023.
  3. ^ a b Ilic, Igor (2009-03-03). "Adria LNG terminal consortium gets new structure". Reuters. Retrieved 2009-04-04.
  4. ^ a b Ilic, Igor (2009-12-10). "Croatia, investors see no delay for LNG terminal". Reuters. Retrieved 2012-01-16.
  5. ^ Ilic, Igor (2009-01-20). "Russian gas cut may spur Croatia LNG project". Reuters. Retrieved 2009-04-04.
  6. ^ Hromadko, Jan (2009-10-20). "RWE Exits Adria LNG consortium On Review Of LNG Operations". Capital.gr. Dow Jones Newswires. Retrieved 2012-01-16.
  7. ^ https://www.novilist.hr/Vijesti/Gospodarstvo/Adria-LNG-zatvorio-ured-u-Hrvatskoj/ Novi List
  8. ^ Lasić, Igor (12 April 2016). "Hrvatska sve bliže plutajućem LNG-terminalu na Krku" [Croatia is getting closer to the floating LNG terminal on Krk]. DW (in Croatian). Retrieved 14 April 2023.
  9. ^ https://lng.hr/cms/api/public/uploads/LNG%20Terminal_Pregled%20i%20Status%20projekta_05092019%20(002)(1).pdf LNG Hrvatska
  10. ^ "Project flow". LNG Hrvatska. Retrieved 22 September 2021.
  11. ^ Čulina, Stanko (29 January 2021). "Otvoren LNG terminal na Krku" [LNG terminal opened on Krk]. Vijesti HRT (in Croatian). Retrieved 22 September 2021.
  12. ^ "Povećan kapacitet uplinjavanja na LNG terminalu u Omišlju" [Increased gasification capacity at the LNG terminal in Omišalj]. pomorac (in Croatian). 11 April 2022. Retrieved 19 August 2022.
  13. ^ Skočajić, Silvana (18 August 2022). "Zbog plinske krize Vlada povećava kapacitet LNG terminala na Krku" [Due to the gas crisis, the Government is increasing the capacity of the LNG terminal on Krk]. HRT Vijesti (in Croatian). Retrieved 19 August 2022.
  14. ^ Glavan, Marinko (14 April 2023). "Potpisan ugovor za udvostručenje kapaciteta LNG terminala. Filipović: 'Postajemo energetsko čvorište za ovaj dio Europe'" [Signed contract for doubling the capacity of the LNG terminal. Filipović: 'We are becoming an energy hub for this part of Europe']. Novi List (in Croatian). Retrieved 14 April 2023.
  15. ^ a b c d e f g h i j k l "About terminal". LNG Hrvatska. 22 September 2021.
  16. ^ "Izvješće o poslovanju i održivosti HEP grupe za 2021. godinu" [Report on operations and sustainability of the HEP Group for 2021] (PDF). HEP (in Croatian). 22 September 2021. p. 15.