Jump to content

Trtar-Krtolin Wind Farm

Coordinates: 43°45′09″N 15°58′04″E / 43.75250°N 15.96778°E / 43.75250; 15.96778
From Wikipedia, the free encyclopedia
(Redirected from Trtar-Krtolin wind farm)
Trtar-Krtolin wind farm
Four of the fourteen turbines of Trtar-Krtolin
Map
CountryCroatia
Location
  • Trtar
Coordinates43°45′09″N 15°58′04″E / 43.75250°N 15.96778°E / 43.75250; 15.96778
StatusUnder construction
Construction began
  • November 2005
Commission date2006
Construction cost
  • 12.5 million €
  • WPD
  • WPD
Site elevation
  • 450 m (1,480 ft)
Power generation
Units operational14 x 800 kW
Make and modelEnercon E48/800
Nameplate capacity11.2 MW
Annual net output
  • 28 GWh
External links
CommonsRelated media on Commons

The Trtar-Krtolin wind farm is a wind farm located in Croatia. With a capacity of 11.2 MW, it was constructed in 2006. It is composed of 14 Enercon E48/800 turbines, with a capacity of 800 kW each.[1]

References

[edit]
  1. ^ "Trtar-Krtolin (Croatia)". The Wind Power. The Wind Power. Retrieved 4 February 2019.